NYSDOT contract D265692 bid tabulation
ADA ACCESSIBILITY IMPROVEMENTS - Various Locations. Let by New York State DOT on February 5, 2026, Clinton, Franklin, Region 07. 4 bids received; low bid $1,099,118 by Tadcon Electric LLC.
- Owner
- New York State DOT
- Letting
- 05 FEB 2026
- Pay items
- 55
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Tadcon Electric LLC | $1,099,118 | Low |
| 2 | Bothar Construction LLC | $1,479,480 | +35% |
| 3 | Luck Brothers Inc | $1,600,000 | +46% |
| 4 | Kubricky-Jointa Lime LLC | $1,984,714 | +81% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Tadcon Electric LLC | 2. Bothar Construction LLC | 3. Luck Brothers Inc | 4. Kubricky-Jointa Lime LLC |
|---|---|---|---|---|---|---|---|
| 1 | Unclassified Excavation and Disposal (203.02) | CY | 552 | $144.50 | $152.76 | $106.30 | $125.10 |
| 2 | Embankment In Place (203.03) | CY | 2 | $60.00 | $81.99 | $275.45 | $98.64 |
| 3 | Select Granular Fill (203.07) | CY | 21 | $284.92 | $112.52 | $147.98 | $85.25 |
| 4 | Trench and Culvert Excavation (206.0201) | CY | 41 | $181.28 | $96.06 | $125.28 | $114.16 |
| 5 | Conduit Excavation and Backfill including Surface Restoration (206.03) | LF | 85 | $107.18 | $90.85 | $130.69 | $44.38 |
| 6 | Seed and Mulch – Temporary (209.1003) | SY | 298 | $5.86 | $9.72 | $12.23 | $20.49 |
| 7 | Subbase Course, Type 2 (304.12) | CY | 424 | $153.32 | $254.40 | $198.67 | $246.38 |
| 8 | (404.0983) | TON | 57 | $276.26 | $307.93 | $507.66 | $457.69 |
| 9 | (404.2589) | TON | 170 | $202.88 | $277.55 | $502.06 | $457.69 |
| 10 | (603.98080007) | 84 | $61.99 | $138.89 | $114.60 | $61.54 | |
| 11 | (604.070101) | EACH | 7 | $757.98 | $1,234.66 | $2,286.23 | $4,151.51 |
| 12 | (604.07260011) | 1 | $756.59 | $851.53 | $1,543.87 | $1,608.45 | |
| 13 | (604.300103) | LF | 6 | $1,136.04 | $1,348.99 | $1,449.70 | $1,543.72 |
| 14 | (607.95000008) | 135 | $11.19 | $41.68 | $54.87 | $45.90 | |
| 15 | Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.000013) | QUALITY UNIT | 1 | $90.00 | $90.00 | $90.00 | $90.00 |
| 16 | Concrete Sidewalks and Driveways (608.0101) | CY | 97 | $1,636.86 | $2,800.00 | $3,488.43 | $3,067.32 |
| 17 | Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102) | TON | 84 | $417.86 | $307.93 | $404.53 | $345.00 |
| 18 | (608.21000003) | 59 | $626.64 | $315.00 | $447.10 | $299.98 | |
| 19 | (609.0401) | LF | 1,482 | $103.33 | $125.00 | $153.32 | $156.58 |
| 20 | (609.40000015) | 5 | $594.69 | $555.00 | $624.42 | $961.28 | |
| 21 | Turf Establishment – Performance (610.1605) | SY | 149 | $10.15 | $45.97 | $128.14 | $96.10 |
| 22 | Transplanting 0 to 48 inch in height (611.10) | EACH | 20 | $189.45 | $170.35 | $863.12 | $273.25 |
| 23 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $195,000 | $322,831 | $301,727 | $625,000 |
| 24 | Type III Construction Barricades (619.04) | EACH | 96 | $103.13 | $108.30 | $254.79 | $55.00 |
| 25 | Survey Operations (625.01) | LS | 1 | $12,000 | $12,917 | $11,800 | $75,000 |
| 26 | (627.50140008) | 2,094 | $10.29 | $7.44 | $5.59 | $10.22 | |
| 27 | Cleaning and Preparation of Pavement Surfaces-Lines (635.0103) | LF | 2,142 | $5.34 | $12.09 | $1.96 | $5.81 |
| 28 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $681.38 | $1,720.13 | $1,044.75 | $683.12 |
| 29 | Engineer’s Field Office – Type 2 (637.12) | MONTH | 17 | $1,817.87 | $2,548.34 | $3,087.83 | $2,771.39 |
| 30 | Office Technology and Supplies (637.34) | DOL | 3,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 31 | Construction Testing supplies – Consumables (637.36) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 |
| 32 | Type A Sign Posts (645.81) | EACH | 13 | $475.40 | $584.08 | $383.78 | $478.18 |
| 33 | Relocate Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.31) | EACH | 23 | $239.09 | $274.84 | $191.89 | $239.09 |
| 34 | Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61) | EACH | 12 | $62.50 | $274.84 | $27.41 | $34.16 |
| 35 | Welded Frame & Reticuline Grate 3 (655.1103) | EACH | 2 | $2,367.79 | $1,510.71 | $2,448.59 | $2,445.36 |
| 36 | Adjust Existing Valve Box Elevation (663.33) | EACH | 1 | $391.95 | $503.48 | $979.44 | $152.63 |
| 37 | Pole Excavation and Concrete Foundation (680.5001) | CY | 5 | $2,353.86 | $4,335.50 | $4,522.12 | $5,634.38 |
| 38 | (680.51020009) | 3 | $781.78 | $584.78 | $589.94 | $735.04 | |
| 39 | (680.520506) | LF | 85 | $21.38 | $25.30 | $7.87 | $9.81 |
| 40 | (680.6805) | EACH | 2 | $2,210.60 | $2,001.00 | $1,687.57 | $2,102.65 |
| 41 | (680.6812) | EACH | 2 | $2,450.60 | $2,288.50 | $1,841.09 | $2,293.92 |
| 42 | Shielded Lead-in Cable (680.71) | LF | 555 | $3.40 | $4.02 | $2.95 | $3.68 |
| 43 | (680.730514) | LF | 525 | $4.29 | $5.12 | $4.28 | $5.33 |
| 44 | (680.80324515) | 1 | $3,577.76 | $5,071.50 | $3,095.53 | $3,856.90 | |
| 45 | Install Pedestrian Signal Module (680.813104) | EACH | 8 | $165.11 | $138.00 | $4.06 | $5.06 |
| 46 | Pedestrian Signal Section - Polycarbonate, Type I, 12-inch (680.813106) | EACH | 8 | $343.44 | $464.60 | $432.03 | $538.30 |
| 47 | Pedestrian Signal Bracket Mount Assembly (680.8141) | EACH | 4 | $479.58 | $817.65 | $514.27 | $640.77 |
| 48 | (680.8151) | EACH | 4 | $1,051.80 | $1,545.60 | $1,327.90 | $1,654.52 |
| 49 | Performance Concrete Quality Adjustment (680.99) | QUALITY UNIT | 1 | $15.00 | $15.00 | $15.00 | $15.00 |
| 50 | White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102) | LF | 1,902 | $7.90 | $13.60 | $3.94 | $15.10 |
| 51 | Field Change Payment (FCP) (697.03) | DOL | 65,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 52 | Asphalt Price Adjustment (698.04) | DOL | 158 | $1.00 | $1.00 | $1.00 | $1.00 |
| 53 | Fuel Price Adjustment (698.05) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 |
| 54 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 |
| 55 | Mobilization (699.040001) | LS | 1 | $42,081 | $50,000 | $61,500 | $75,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of February 5, 2026. Compiled by Mirage Metrics.