NYSDOT contract D265504 bid tabulation
INTERSECTION IMPROVEMENTS; NY 952J at Murphy Rd and Duerr Rd. Let by New York State DOT on June 26, 2025, Erie, Region 05. 4 bids received; low bid $3,086,000 by Union Concrete & Construction Corp.
- Owner
- New York State DOT
- Letting
- 26 JUN 2025
- Pay items
- 158
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Union Concrete & Construction Corp | $3,086,000 | Low |
| 2 | McLaughlin Construction Corp/DBA Edbauer Construction | $3,747,004 | +21% |
| 3 | D&H Excavating Inc | $3,796,553 | +23% |
| 4 | Concrete Applied Technologies Corp/DBA:Catco | $4,196,590 | +36% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Union Concrete & Construction Corp | 2. McLaughlin Construction Corp/DBA Edbauer Construction | 3. D&H Excavating Inc | 4. Concrete Applied Technologies Corp/DBA:Catco |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.06) | LS | 1 | $5,000.00 | $50,000 | $5,000.00 | $15,000 |
| 2 | Unclassified Excavation and Disposal (203.02) | CY | 8,600 | $13.50 | $24.00 | $39.00 | $42.00 |
| 3 | Embankment In Place (203.03) | CY | 4,250 | $7.00 | $16.00 | $30.00 | $20.00 |
| 4 | Select Granular Fill (203.07) | CY | 590 | $96.00 | $71.00 | $103.00 | $85.00 |
| 5 | (203.24010017) | 20 | $115.00 | $100.00 | $75.00 | $200.00 | |
| 6 | Controlled Low Strength Material (CLSM) (204.01) | CY | 14 | $240.00 | $300.00 | $880.00 | $440.00 |
| 7 | Trench and Culvert Excavation (206.0201) | CY | 1,270 | $29.00 | $24.00 | $127.00 | $40.00 |
| 8 | Conduit Excavation and Backfill including Surface Restoration (206.03) | LF | 1,170 | $65.00 | $10.00 | $71.00 | $110.00 |
| 9 | Test Pit Excavation (206.05) | EACH | 7 | $1,000.00 | $3,000.00 | $1,050.00 | $1,500.00 |
| 10 | Geotextile Bedding (207.20) | SY | 54 | $5.50 | $20.00 | $10.00 | $25.00 |
| 11 | Geotextile Separation (207.21) | SY | 582 | $2.50 | $3.00 | $6.00 | $5.00 |
| 12 | (208.01030022) | 475 | $110.00 | $110.00 | $83.00 | $150.00 | |
| 13 | Seed and Mulch – Temporary (209.1003) | SY | 2,647 | $0.85 | $1.00 | $3.50 | $1.00 |
| 14 | Rolled Erosion Control Product, Class II Type C, Intermediate (209.190301) | SY | 1,245 | $2.25 | $3.30 | $7.50 | $10.00 |
| 15 | Stabilized Construction Access (209.22) | SY | 80 | $15.00 | $10.00 | $5.00 | $75.00 |
| 16 | (209.23010009) | 213 | $6.00 | $4.00 | $15.00 | $12.00 | |
| 17 | (304.15010005) | 3,800 | $77.00 | $75.00 | $80.00 | $80.00 | |
| 18 | (404.0001) | TON | 204 | $90.00 | $90.00 | $90.00 | $90.00 |
| 19 | (404.0982) | TON | 650 | $133.00 | $170.00 | $115.00 | $140.00 |
| 20 | (404.1989) | TON | 1,030 | $110.00 | $165.00 | $110.00 | $130.00 |
| 21 | (404.3789) | TON | 2,400 | $105.00 | $128.00 | $95.00 | $120.00 |
| 22 | Diluted Tack Coat (407.0102) | GAL | 1,400 | $10.00 | $10.00 | $7.50 | $5.00 |
| 23 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 4,130 | $0.30 | $1.00 | $1.00 | $1.00 |
| 24 | Production Cold Milling of Bituminous Concrete (490.10) | SY | 1,500 | $5.50 | $8.00 | $5.00 | $10.00 |
| 25 | Miscellaneous Cold Milling of Bituminous Concrete (490.30) | SY | 180 | $13.50 | $15.00 | $15.00 | $40.00 |
| 26 | (502.12110018) | 95 | $890.00 | $890.00 | $1,200.00 | $960.00 | |
| 27 | Shields and Shoring (552.17) | SF | 4,000 | $0.10 | $0.50 | $0.50 | $1.00 |
| 28 | (553.030001) | EACH | 1 | $100.00 | $100.00 | $10,500 | $100.00 |
| 29 | (601.01110001) | 557 | $48.00 | $52.00 | $85.00 | $75.00 | |
| 30 | Structural Paving of Inverts with Portland Cement Concrete (602.2002) | SF | 1,450 | $38.00 | $96.00 | $95.00 | $140.00 |
| 31 | Culvert-End Safety Grate (603.0101) | SF | 24 | $38.00 | $58.00 | $45.00 | $60.00 |
| 32 | (603.142408) | LF | 60 | $290.00 | $348.00 | $500.00 | $650.00 |
| 33 | (603.171416) | EACH | 2 | $350.00 | $384.00 | $730.00 | $700.00 |
| 34 | (603.171614) | EACH | 2 | $575.00 | $572.00 | $1,100.00 | $1,100.00 |
| 35 | (603.171814) | EACH | 1 | $800.00 | $952.00 | $1,500.00 | $1,700.00 |
| 36 | (603.552412) | EACH | 1 | $11,500 | $15,065 | $15,000 | $15,000 |
| 37 | Concrete Collars (603.77) | EACH | 1 | $3,000.00 | $2,870.00 | $20,000 | $11,500 |
| 38 | (603.98100402) | 540 | $4.00 | $23.00 | $25.00 | $10.00 | |
| 39 | (603.9815) | LF | 275 | $15.00 | $57.00 | $42.00 | $40.00 |
| 40 | (603.9824) | LF | 233 | $30.00 | $90.00 | $52.00 | $50.00 |
| 41 | (603.9830) | LF | 75 | $40.00 | $134.00 | $81.00 | $80.00 |
| 42 | (603.9836) | LF | 560 | $53.00 | $92.00 | $62.00 | $130.00 |
| 43 | (604.070501) | EACH | 1 | $1,100.00 | $2,836.00 | $4,400.00 | $1,500.00 |
| 44 | (604.300103) | LF | 62 | $650.00 | $990.00 | $675.00 | $900.00 |
| 45 | (604.300211) | LF | 15 | $625.00 | $1,008.00 | $625.00 | $1,200.00 |
| 46 | (604.300511) | LF | 14 | $675.00 | $1,200.00 | $850.00 | $1,310.00 |
| 47 | (604.300611) | LF | 13 | $690.00 | $1,250.00 | $775.00 | $1,200.00 |
| 48 | Underdrain Filter, Type II (605.1001) | CY | 400 | $60.00 | $64.00 | $85.00 | $65.00 |
| 49 | (605.98101518) | 522 | $14.00 | $57.00 | $39.00 | $40.00 | |
| 50 | (605.98101818) | 59 | $21.00 | $92.00 | $51.00 | $80.00 | |
| 51 | (605.98102418) | 120 | $28.00 | $96.00 | $53.00 | $90.00 | |
| 52 | Box Beam Guide Railing (606.10) | LF | 174 | $68.00 | $68.00 | $72.00 | $72.00 |
| 53 | Box Beam Guide Railing (Shop Bent or Shop Mitered) (606.100002) | LF | 24 | $76.00 | $76.00 | $80.00 | $80.00 |
| 54 | Box Beam End Piece (606.120101) | EACH | 1 | $835.00 | $844.00 | $885.00 | $890.00 |
| 55 | Box Beam Guide Railing End Assembly Type IIA (606.120201) | EACH | 1 | $2,750.00 | $2,765.00 | $2,900.00 | $2,900.00 |
| 56 | (607.99870011) | 15 | $18.00 | $45.00 | $69.00 | $50.00 | |
| 57 | Concrete Sidewalks and Driveways (608.0101) | CY | 250 | $845.00 | $804.00 | $900.00 | $810.00 |
| 58 | Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102) | TON | 32 | $225.00 | $350.00 | $280.00 | $270.00 |
| 59 | (608.21000003) | 36 | $550.00 | $544.00 | $550.00 | $570.00 | |
| 60 | (609.0401) | LF | 124 | $85.00 | $88.00 | $114.00 | $95.00 |
| 61 | (609.0403) | LF | 2,425 | $36.00 | $36.00 | $59.00 | $48.00 |
| 62 | (609.0407) | LF | 254 | $85.00 | $88.00 | $101.00 | $83.00 |
| 63 | Compost (610.10) | CY | 18 | $165.00 | $110.00 | $125.00 | $150.00 |
| 64 | (610.11041209) | 27 | $105.00 | $174.00 | $140.00 | $200.00 | |
| 65 | Topsoil - Roadside (610.1402) | CY | 800 | $57.00 | $110.00 | $52.00 | $90.00 |
| 66 | Turf Establishment -Lawns (610.1602) | SY | 6,810 | $1.25 | $0.10 | $2.30 | $2.00 |
| 67 | Watering Vegetation (610.19) | 1,000 GALLONS | 97 | $12.00 | $25.00 | $0.01 | $170.00 |
| 68 | (611.0151) | EACH | 8 | $1,050.00 | $890.00 | $1,150.00 | $1,100.00 |
| 69 | (611.0361) | EACH | 6 | $1,000.00 | $900.00 | $1,050.00 | $1,100.00 |
| 70 | (611.0422) | EACH | 10 | $130.00 | $276.00 | $145.00 | $150.00 |
| 71 | (611.0461) | EACH | 6 | $450.00 | $442.00 | $500.00 | $500.00 |
| 72 | (611.0471) | EACH | 13 | $550.00 | $507.00 | $600.00 | $600.00 |
| 73 | (611.0522) | EACH | 9 | $130.00 | $278.00 | $145.00 | $150.00 |
| 74 | (611.19010024) | 8 | $52.00 | $180.00 | $57.00 | $60.00 | |
| 75 | (611.19030024) | 6 | $52.00 | $190.00 | $57.00 | $60.00 | |
| 76 | (611.19040024) | 29 | $11.00 | $62.00 | $12.00 | $15.00 | |
| 77 | (611.19050024) | 9 | $11.00 | $94.00 | $12.00 | $15.00 | |
| 78 | (614.060204) | EACH | 20 | $500.00 | $450.00 | $500.00 | $600.00 |
| 79 | (614.060304) | EACH | 5 | $1,000.00 | $980.00 | $1,000.00 | $1,600.00 |
| 80 | (614.060404) | EACH | 1 | $1,350.00 | $4,200.00 | $2,400.00 | $1,900.00 |
| 81 | (617.10000024) | 40 | $17.00 | $35.00 | $60.00 | $180.00 | |
| 82 | (617.11000024) | LS | 1 | $100.00 | $100.00 | $350.00 | $2,500.00 |
| 83 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $198,500 | $195,101 | $70,000 | $142,800 |
| 84 | Type III Construction Barricades (619.04) | EACH | 14 | $80.00 | $250.00 | $1,000.00 | $150.00 |
| 85 | Cover Existing Pavement Marking Stripes (Removable Tape) (619.0803) | LF | 1,085 | $1.50 | $5.38 | $0.01 | $5.50 |
| 86 | (619.0901) | LF | 300 | $1.25 | $5.44 | $6.00 | $10.00 |
| 87 | (619.100103) | LF | 7,375 | $1.40 | $2.50 | $0.01 | $5.50 |
| 88 | (619.111113) | EACH | 6 | $6,000.00 | $10,000 | $5,800.00 | $10,000 |
| 89 | (619.17060005) | 635 | $1.00 | $2.00 | $0.01 | $7.00 | |
| 90 | Temporary Positive Barrier – Category 6 (Pinning Required) (619.1716) | LF | 1,180 | $29.00 | $70.00 | $0.01 | $40.00 |
| 91 | Temporary Impact Attenuator - Redirective (Test Level 2) (619.1802) | EACH | 3 | $4,000.00 | $10,000 | $0.01 | $7,000.00 |
| 92 | Mailboxes (619.27) | EACH | 4 | $235.00 | $350.00 | $500.00 | $600.00 |
| 93 | Stone Filling (Fine) (620.02) | CY | 15 | $90.00 | $110.00 | $250.00 | $200.00 |
| 94 | Stone Filling (Medium) (620.04) | CY | 40 | $155.00 | $140.00 | $240.00 | $200.00 |
| 95 | Bedding Material, Type 1 (620.0801) | CY | 50 | $95.00 | $110.00 | $120.00 | $115.00 |
| 96 | (621.51000015) | 100 | $5.50 | $15.00 | $20.00 | $35.00 | |
| 97 | Crushed Gravel (In-Place Measure) (623.11) | CY | 82 | $130.00 | $110.00 | $100.00 | $95.00 |
| 98 | (624.01) | 88 | $36.00 | $40.00 | $37.00 | $25.00 | |
| 99 | Survey Operations (625.01) | LS | 1 | $40,000 | $58,000 | $55,000 | $80,000 |
| 100 | Concrete Right of Way Markers Type L (Low) (625.04) | EACH | 10 | $550.00 | $970.00 | $1,000.00 | $600.00 |
| 101 | Steel Pin and Cap Right of Way Markers (625.05) | EACH | 2 | $275.00 | $320.00 | $475.00 | $650.00 |
| 102 | Permanent Survey Markers (625.06) | EACH | 4 | $850.00 | $1,050.00 | $1,050.00 | $2,000.00 |
| 103 | (625.09010015) | LS | 1 | $1,500.00 | $0.01 | $5,000.00 | $100.00 |
| 104 | (627.50140008) | 3,500 | $2.40 | $5.00 | $3.00 | $5.00 | |
| 105 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $500.00 | $500.00 | $1,200.00 | $4,000.00 |
| 106 | Engineer’s Field Office – Type 3 (637.13) | MONTH | 18 | $2,150.00 | $1,800.00 | $2,300.00 | $2,800.00 |
| 107 | Office Technology and Supplies (637.34) | DOL | 500 | $1.00 | $1.00 | $1.00 | $1.00 |
| 108 | Construction Testing supplies – Consumables (637.36) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 |
| 109 | White Paint Reflectorized Pavement Stripes – 15 mils (640.10) | LF | 1,500 | $1.15 | $1.20 | $1.25 | $2.00 |
| 110 | Yellow Paint Reflectorized Pavement Stripes - 15 mils (640.11) | LF | 1,500 | $1.15 | $1.20 | $1.25 | $2.00 |
| 111 | Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102) | SF | 1,101 | $38.00 | $43.00 | $45.00 | $45.00 |
| 112 | Type A Sign Posts (645.81) | EACH | 141 | $185.00 | $210.00 | $220.00 | $220.00 |
| 113 | High-Capacity Type A Sign Posts with Soil Plates Only (645.8106) | EACH | 2 | $1,140.00 | $1,354.00 | $1,400.00 | $1,400.00 |
| 114 | (645.81090003) | 88 | $48.00 | $80.00 | $85.00 | $85.00 | |
| 115 | (645.830202) | EACH | 9 | $2,785.00 | $3,028.00 | $3,200.00 | $3,200.00 |
| 116 | Reference Marker Panel (646.21) | EACH | 10 | $4.00 | $42.00 | $45.00 | $45.00 |
| 117 | Steel Post, 2.0 lb/ft (646.32) | EACH | 10 | $78.00 | $97.00 | $100.00 | $100.00 |
| 118 | Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61) | EACH | 50 | $45.00 | $7.00 | $7.50 | $7.50 |
| 119 | (647.83001002) | 10 | $30.00 | $6.00 | $6.00 | $7.00 | |
| 120 | Welded Frame & Reticuline Grate 3 (655.1103) | EACH | 15 | $1,600.00 | $1,682.00 | $2,000.00 | $1,100.00 |
| 121 | Welded Frame & Reticuline Grate 11 (655.1111) | EACH | 8 | $1,850.00 | $1,700.00 | $2,100.00 | $1,200.00 |
| 122 | (663.1008) | EACH | 1 | $5,300.00 | $5,000.00 | $7,500.00 | $11,000 |
| 123 | Adjust Existing Valve Box Elevation (663.33) | EACH | 2 | $450.00 | $550.00 | $510.00 | $350.00 |
| 124 | (670.0109) | EACH | 9 | $3,100.00 | $2,400.00 | $3,300.00 | $4,200.00 |
| 125 | (670.03240009) | 1 | $630.00 | $137.00 | $700.00 | $600.00 | |
| 126 | (670.1130) | EACH | 9 | $3,100.00 | $3,044.00 | $3,400.00 | $3,100.00 |
| 127 | (670.1308) | EACH | 9 | $785.00 | $925.00 | $850.00 | $800.00 |
| 128 | Breakaway Transformer Base (Aluminum) (670.19) | EACH | 9 | $970.00 | $925.00 | $1,050.00 | $975.00 |
| 129 | (670.21311210) | 20 | $31.50 | $20.00 | $35.00 | $27.50 | |
| 130 | (670.2308) | LF | 30 | $126.00 | $127.00 | $140.00 | $120.00 |
| 131 | (670.2603) | LF | 1,570 | $21.00 | $6.23 | $23.00 | $18.00 |
| 132 | Pullboxes 5 to 7 1/2 cubic feet, inside volume (Lighting) (670.3006) | EACH | 6 | $1,840.00 | $2,521.00 | $2,000.00 | $2,750.00 |
| 133 | (670.53070304) | 1 | $9,450.00 | $14,367 | $10,300 | $8,100.00 | |
| 134 | Photoelectric Controls (670.60) | EACH | 1 | $79.00 | $108.00 | $85.00 | $11,000 |
| 135 | (670.7003) | LF | 60 | $4.20 | $7.00 | $4.50 | $5.00 |
| 136 | (670.7004) | LF | 4,120 | $3.15 | $3.00 | $3.50 | $3.50 |
| 137 | (670.7006) | LF | 900 | $2.65 | $3.15 | $3.00 | $2.75 |
| 138 | Ground Wire No. 6 AWG. (670.7501) | LF | 1,232 | $3.15 | $1.20 | $3.50 | $3.50 |
| 139 | (670.75060011) | 50 | $2.90 | $1.00 | $3.00 | $6.00 | |
| 140 | (670.75070011) | 450 | $2.60 | $1.00 | $3.00 | $2.75 | |
| 141 | Remove and Dispose of Lamppost Assembly (670.81) | EACH | 1 | $945.00 | $1,394.00 | $1,050.00 | $1,500.00 |
| 142 | (670.92010008) | 1 | $2,415.00 | $1,971.00 | $2,600.00 | $750.00 | |
| 143 | (670.98000105) | 9 | $935.00 | $712.00 | $1,015.00 | $900.00 | |
| 144 | (670.98000205) | 9 | $79.00 | $143.00 | $85.00 | $75.00 | |
| 145 | Performance Concrete Quality Adjustment (670.99) | QUALITY UNIT | 1 | $6.72 | $6.72 | $6.72 | $6.72 |
| 146 | (680.50500005) | 2 | $630.00 | $100.00 | $700.00 | $650.00 | |
| 147 | (685.07200910) | 20 | $132.00 | $135.00 | $145.00 | $140.00 | |
| 148 | White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102) | LF | 7,140 | $1.55 | $1.63 | $1.60 | $1.70 |
| 149 | Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202) | LF | 5,790 | $1.55 | $1.63 | $1.60 | $1.70 |
| 150 | White Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3104) | LF | 1,320 | $5.15 | $5.33 | $5.00 | $5.50 |
| 151 | Yellow Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3204) | LF | 950 | $5.15 | $5.33 | $5.00 | $5.50 |
| 152 | White Epoxy Reflectorized Pavement Letters - 20 mil Portable/Hand Application (685.3304) | EACH | 20 | $83.00 | $86.00 | $80.00 | $90.00 |
| 153 | White Epoxy Reflectorized Pavement Symbols - 20 mil Portable/Hand Application (685.3404) | EACH | 6 | $310.00 | $320.00 | $300.00 | $320.00 |
| 154 | Field Change Payment (FCP) (697.03) | DOL | 155,200 | $1.00 | $1.00 | $1.00 | $1.00 |
| 155 | Asphalt Price Adjustment (698.04) | DOL | 7,900 | $1.00 | $1.00 | $1.00 | $1.00 |
| 156 | Fuel Price Adjustment (698.05) | DOL | 11,540 | $1.00 | $1.00 | $1.00 | $1.00 |
| 157 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 |
| 158 | Mobilization (699.040001) | LS | 1 | $117,884 | $144,000 | $144,000 | $160,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of June 26, 2025. Compiled by Mirage Metrics.