NYSDOT contract D265690 bid tabulation
BRIDGE & CULVERT REPLACE; NY RT 5 & US RT 20, Twn of Evans. Let by New York State DOT on March 12, 2026, Erie, Region 05. 4 bids received; low bid $23,840,973 by Union Concrete & Construction Corp.
- Owner
- New York State DOT
- Letting
- 12 MAR 2026
- Pay items
- 254
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Union Concrete & Construction Corp | $23,840,973 | Low |
| 2 | Oakgrove Construction Inc | $24,347,307 | +2.0% |
| 3 | Concrete Applied Technologies Corp/DBA:Catco | $29,630,584 | +24% |
| 4 | Cold Spring Construction Company | $30,039,000 | +26% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Union Concrete & Construction Corp | 2. Oakgrove Construction Inc | 3. Concrete Applied Technologies Corp/DBA:Catco | 4. Cold Spring Construction Company |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.06) | LS | 1 | $75,000 | $50,000 | $30,000 | $50,000 |
| 2 | Clearing and Grubbing (201.07) | ACRE | 0.30 | $60,000 | $130,000 | $65,000 | $325,000 |
| 3 | (202.120001) | LS | 1 | $400,000 | $150,000 | $250,000 | $275,000 |
| 4 | (202.120002) | LS | 1 | $14,000 | $25,000 | $150,000 | $50,000 |
| 5 | (202.120003) | LS | 1 | $8,000.00 | $20,000 | $64,000 | $50,000 |
| 6 | Removal of Substructures (202.19) | CY | 3,370 | $165.00 | $175.00 | $200.00 | $175.00 |
| 7 | Unclassified Excavation and Disposal (203.02) | CY | 3,535 | $39.00 | $30.00 | $75.00 | $55.00 |
| 8 | Embankment In Place (203.03) | CY | 7,870 | $38.00 | $30.00 | $45.00 | $40.00 |
| 9 | Select Granular Fill (203.07) | CY | 1,384 | $120.00 | $60.00 | $110.00 | $70.00 |
| 10 | Select Structural Fill (203.21) | CY | 1,998 | $93.00 | $80.00 | $90.00 | $100.00 |
| 11 | (203.24010017) | 91 | $110.00 | $100.00 | $150.00 | $100.00 | |
| 12 | Controlled Low Strength Material (CLSM) (204.01) | CY | 6 | $440.00 | $700.00 | $500.00 | $750.00 |
| 13 | Structure Excavation (206.01) | CY | 10,557 | $27.00 | $40.00 | $60.00 | $65.00 |
| 14 | Trench and Culvert Excavation (206.0201) | CY | 4,381 | $50.00 | $25.00 | $60.00 | $55.00 |
| 15 | (206.03060005) | 170 | $66.00 | $60.00 | $90.00 | $50.00 | |
| 16 | Test Pit Excavation (206.05) | EACH | 19 | $800.00 | $2,500.00 | $2,000.00 | $2,500.00 |
| 17 | Geotextile Bedding (207.20) | SY | 351 | $5.00 | $4.00 | $10.00 | $5.00 |
| 18 | Geotextile Separation (207.21) | SY | 1,100 | $1.85 | $4.00 | $4.00 | $4.00 |
| 19 | Geotextile Drainage (207.22) | SY | 6 | $20.00 | $100.00 | $25.00 | $50.00 |
| 20 | Prefabricated Composite Integral Abutment Drain (207.27) | SY | 655 | $22.00 | $15.00 | $25.00 | $20.00 |
| 21 | Seed and Mulch – Temporary (209.1003) | SY | 8,097 | $0.65 | $2.00 | $0.01 | $0.25 |
| 22 | Check Dam (Ditch Bottom Width 0.0 to 3′), Stone – Temporary (209.110101) | EACH | 28 | $175.00 | $750.00 | $50.00 | $500.00 |
| 23 | Turbidity Curtain – Temporary (209.1501) | LF | 1,901 | $20.00 | $15.00 | $22.00 | $15.00 |
| 24 | Rolled Erosion Control Product, Class II Type C, Intermediate (209.190301) | SY | 962 | $3.15 | $6.00 | $7.00 | $6.00 |
| 25 | Sediment Filter Log, 12″ (209.2301) | LF | 4,928 | $5.00 | $8.00 | $1.00 | $5.00 |
| 26 | (304.15200005) | 2,979 | $116.00 | $85.00 | $90.00 | $115.00 | |
| 27 | Pavement Density Quality Adjustment to Asphalt Items (404.0002) | QUALITY UNIT | 35 | $100.00 | $100.00 | $100.00 | $100.00 |
| 28 | (404.0189) | TON | 775 | $160.00 | $125.00 | $225.00 | $225.00 |
| 29 | (404.0962) | TON | 1,022 | $150.00 | $100.00 | $165.00 | $175.00 |
| 30 | (404.0982) | TON | 718 | $120.00 | $100.00 | $175.00 | $165.00 |
| 31 | (404.1989) | TON | 2,477 | $140.00 | $95.00 | $145.00 | $155.00 |
| 32 | (404.3789) | TON | 2,495 | $118.00 | $95.00 | $140.00 | $150.00 |
| 33 | Diluted Tack Coat (407.0102) | GAL | 3,412 | $12.00 | $5.00 | $7.00 | $15.00 |
| 34 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 11,599 | $0.80 | $0.25 | $1.50 | $1.25 |
| 35 | Miscellaneous Cold Milling of Bituminous Concrete (490.30) | SY | 13,855 | $8.00 | $5.00 | $8.00 | $10.00 |
| 36 | Shields and Shoring (552.17) | SF | 37,603 | $0.10 | $1.00 | $1.00 | $0.75 |
| 37 | (552.2001) | LF | 211 | $145.00 | $125.00 | $2.00 | $250.00 |
| 38 | (552.2101) | LF | 87 | $1,425.00 | $1,050.00 | $2.00 | $2,500.00 |
| 39 | (552.2201) | LF | 302 | $175.00 | $175.00 | $950.00 | $200.00 |
| 40 | (552.230201) | SF | 1,311 | $33.00 | $75.00 | $20.00 | $45.00 |
| 41 | (553.020001) | EACH | 1 | $40,000 | $30,000 | $500.00 | $50,000 |
| 42 | (553.020002) | EACH | 1 | $20,000 | $35,000 | $500.00 | $50,000 |
| 43 | (553.020003) | EACH | 1 | $9,000.00 | $35,000 | $500.00 | $50,000 |
| 44 | (553.020004) | EACH | 1 | $7,000.00 | $35,000 | $500.00 | $15,000 |
| 45 | (553.020005) | EACH | 1 | $15,000 | $35,000 | $500.00 | $25,000 |
| 46 | (553.020006) | EACH | 1 | $9,000.00 | $35,000 | $500.00 | $30,000 |
| 47 | (553.020007) | EACH | 1 | $7,000.00 | $35,000 | $500.00 | $15,000 |
| 48 | (553.030001) | EACH | 1 | $75,000 | $1.00 | $500.00 | $15,000 |
| 49 | (553.030002) | EACH | 1 | $20,000 | $80,000 | $500.00 | $15,000 |
| 50 | (553.030003) | EACH | 1 | $22,000 | $80,000 | $500.00 | $15,000 |
| 51 | (554.3001) | SF | 1,353 | $68.00 | $75.00 | $5.50 | $85.00 |
| 52 | Footing Concrete, Performance (555.0011) | CY | 718 | $1,100.00 | $650.00 | $1,450.00 | $1,500.00 |
| 53 | Concrete for Structures, Performance (555.0021) | CY | 829 | $1,500.00 | $1,450.00 | $2,600.00 | $2,500.00 |
| 54 | (555.97020016) | 6 | $4,300.00 | $3,000.00 | $4,000.00 | $6,000.00 | |
| 55 | Performance Concrete Quality Adjustment – Footing Concrete (555.9901) | QUALITY UNIT | 1 | $4.55 | $4.55 | $4.55 | $4.55 |
| 56 | Performance Concrete Quality Adjustment – Concrete for Structures (555.9902) | QUALITY UNIT | 1 | $9.00 | $9.00 | $9.00 | $9.00 |
| 57 | Uncoated Bar Reinforcement for Concrete Structures (556.0201) | LB | 16,996 | $2.00 | $2.00 | $2.60 | $3.00 |
| 58 | Epoxy-Coated Bar Reinforcement for Structures (556.0202) | LB | 238,581 | $2.25 | $2.50 | $3.00 | $3.50 |
| 59 | Stud Shear Connectors for Bridges (556.03) | EACH | 4,830 | $5.50 | $6.00 | $8.00 | $8.00 |
| 60 | (557.1013) | SY | 373 | $575.00 | $500.00 | $725.00 | $725.00 |
| 61 | (557.1019) | SY | 285 | $660.00 | $475.00 | $725.00 | $725.00 |
| 62 | (557.1119) | SY | 683 | $715.00 | $575.00 | $800.00 | $1,500.00 |
| 63 | Winter Surface Treatment – Superstructure Slabs and Structural Approach Slabs (557.29) | SY | 2,325 | $0.01 | $0.01 | $1.00 | $10.00 |
| 64 | Sidewalks and Safety Walks (557.30) | SY | 242 | $210.00 | $350.00 | $550.00 | $250.00 |
| 65 | (557.75010216) | 150 | $180.00 | $250.00 | $390.00 | $325.00 | |
| 66 | (557.75010316) | 2,850 | $368.00 | $350.00 | $400.00 | $275.00 | |
| 67 | Performance Concrete Quality Adjustment – Superstructure and Approach Slab (557.9901) | QUALITY UNIT | 1 | $10.97 | $10.97 | $10.97 | $10.97 |
| 68 | Performance Concrete Quality Adjustment – Sidewalks and Safety Walks (557.9902) | QUALITY UNIT | 1 | $7.50 | $7.50 | $7.50 | $7.50 |
| 69 | Longitudinal Sawcut Grooving of Structural Slab Surface (558.02) | SY | 1,215 | $30.00 | $15.00 | $26.00 | $20.00 |
| 70 | Protective Sealing of Structural Concrete on New Bridge Decks and Bridge Deck Overlays (559.01) | SF | 10,900 | $0.50 | $1.00 | $1.00 | $2.00 |
| 71 | Protective Sealing of New Structural Concrete (559.02) | SF | 11,470 | $0.80 | $2.00 | $1.50 | $2.00 |
| 72 | Prestressed Concrete Box Beam Units (563.02) | SF | 9,130 | $215.00 | $180.00 | $220.00 | $290.00 |
| 73 | (564.0501) | LS | 1 | $1,400,000 | $755,000 | $825,500 | $925,000 |
| 74 | Type E.L. Bearing (56 to 111 k) (565.1922) | EACH | 34 | $315.00 | $500.00 | $675.00 | $1,500.00 |
| 75 | Type E.L. Bearing (112 to 168 k) (565.1923) | EACH | 34 | $375.00 | $500.00 | $765.00 | $1,500.00 |
| 76 | Type E.B. Expansion Bearing (Over 225 k) (565.2035) | EACH | 12 | $3,000.00 | $3,000.00 | $3,400.00 | $4,000.00 |
| 77 | Armorless Bridge Joint (567.60) | LF | 207 | $340.00 | $200.00 | $400.00 | $375.00 |
| 78 | Steel Bridge Railing (Four-Rail) (568.51) | LF | 285 | $445.00 | $500.00 | $590.00 | $600.00 |
| 79 | Steel Bridge Railing (Three-Rail) (568.54) | LF | 115 | $420.00 | $400.00 | $318.00 | $300.00 |
| 80 | Transition Bridge Railing (568.70) | LF | 547 | $268.00 | $250.00 | $263.00 | $250.00 |
| 81 | Pedestrian and Bicycle Railing (Four-Rail) (568.83) | LF | 306 | $300.00 | $300.00 | $247.00 | $225.00 |
| 82 | Single Slope (Half-Section) Concrete Bridge Barrier (569.04) | LF | 286 | $345.00 | $350.00 | $375.00 | $425.00 |
| 83 | Performance Concrete Quality Adjustment–Cast-In-Place Concrete Barrier (569.99) | QUALITY UNIT | 1 | $9.92 | $9.92 | $9.92 | $9.92 |
| 84 | (570.090001) | LS | 1 | $100.00 | $1,500.00 | $5,000.00 | $1.00 |
| 85 | (570.10) | LS | 1 | $200.00 | $1,500.00 | $5,000.00 | $1.00 |
| 86 | (572.00020101) | LS | 1 | $175,000 | $150,000 | $145,000 | $175,000 |
| 87 | Drilling and Grouting Bolts or Reinforcing Bars (586.0201) | EACH | 92 | $48.00 | $0.01 | $75.00 | $60.00 |
| 88 | Bridge Railing Removal and Disposal (587.01) | LF | 169 | $15.00 | $20.00 | $12.00 | $20.00 |
| 89 | (595.50000018) | 2,721 | $8.00 | $5.00 | $8.00 | $8.00 | |
| 90 | (603.171216) | EACH | 2 | $215.00 | $500.00 | $1,200.00 | $1,750.00 |
| 91 | (603.171316) | EACH | 1 | $235.00 | $500.00 | $1,200.00 | $1,750.00 |
| 92 | (603.171416) | EACH | 2 | $310.00 | $600.00 | $1,500.00 | $2,000.00 |
| 93 | (603.171614) | EACH | 1 | $710.00 | $750.00 | $1,100.00 | $2,500.00 |
| 94 | (603.172112) | EACH | 1 | $3,350.00 | $3,500.00 | $4,500.00 | $6,000.00 |
| 95 | (603.6002) | LF | 92 | $49.00 | $100.00 | $180.00 | $150.00 |
| 96 | (603.64160515) | 68 | $4,325.00 | $4,000.00 | $6,420.00 | $4,000.00 | |
| 97 | (603.65241015) | 69 | $7,050.00 | $6,000.00 | $4,090.00 | $5,750.00 | |
| 98 | (603.7302) | EACH | 4 | $3,300.00 | $2,000.00 | $4,000.00 | $3,500.00 |
| 99 | Concrete Collars (603.77) | EACH | 6 | $1,200.00 | $2,500.00 | $3,500.00 | $2,500.00 |
| 100 | (603.9812) | LF | 76 | $20.00 | $75.00 | $80.00 | $115.00 |
| 101 | (603.9815) | LF | 712 | $23.00 | $55.00 | $65.00 | $120.00 |
| 102 | (603.9818) | LF | 796 | $35.00 | $55.00 | $75.00 | $125.00 |
| 103 | (603.9824) | LF | 184 | $48.00 | $80.00 | $90.00 | $145.00 |
| 104 | (603.9848) | LF | 254 | $140.00 | $150.00 | $220.00 | $225.00 |
| 105 | (604.300103) | LF | 49.80 | $600.00 | $900.00 | $950.00 | $1,400.00 |
| 106 | (604.300403) | LF | 24.10 | $880.00 | $800.00 | $1,000.00 | $1,400.00 |
| 107 | (604.310303) | LF | 6.50 | $720.00 | $800.00 | $1,500.00 | $1,400.00 |
| 108 | (604.4048) | LF | 10.90 | $500.00 | $800.00 | $2,500.00 | $1,800.00 |
| 109 | (604.4060) | LF | 14.30 | $600.00 | $800.00 | $3,000.00 | $2,250.00 |
| 110 | Underdrain Filter, Type II (605.1001) | CY | 326 | $115.00 | $50.00 | $95.00 | $135.00 |
| 111 | Underdrain Filter, Type III (605.1101) | CY | 5 | $115.00 | $85.00 | $200.00 | $100.00 |
| 112 | (605.1601) | LF | 87 | $7.50 | $50.00 | $50.00 | $5.00 |
| 113 | (605.1701) | LF | 4,347 | $1.50 | $8.00 | $7.00 | $4.00 |
| 114 | Box Beam Guide Railing (606.10) | LF | 1,791 | $58.00 | $65.00 | $66.00 | $65.00 |
| 115 | Box Beam Guide Railing (Shop Bent or Shop Mitered) (606.100002) | LF | 11 | $169.00 | $200.00 | $180.00 | $185.00 |
| 116 | Box Beam End Piece (606.120101) | EACH | 7 | $965.00 | $1,000.00 | $835.00 | $1,000.00 |
| 117 | Box Beam Guide Railing End Assembly Type I (606.120102) | EACH | 1 | $4,925.00 | $5,000.00 | $5,570.00 | $6,000.00 |
| 118 | Box Beam Guide Railing End Assembly Type IIA (606.120201) | EACH | 6 | $2,630.00 | $3,000.00 | $2,640.00 | $3,000.00 |
| 119 | Box Beam End Assembly Type III (606.1203) | EACH | 3 | $6,700.00 | $8,000.00 | $8,520.00 | $8,000.00 |
| 120 | Removing and Disposing Box Beam Guide Railing (606.73) | LF | 1,721 | $7.50 | $5.00 | $15.00 | $20.00 |
| 121 | (607.41010010) | 222 | $7.00 | $7.00 | $15.00 | $5.00 | |
| 122 | Concrete Sidewalks and Driveways (608.0101) | CY | 65 | $1,100.00 | $1,500.00 | $2,000.00 | $1,500.00 |
| 123 | Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102) | TON | 217 | $275.00 | $250.00 | $325.00 | $325.00 |
| 124 | Stone Curb – Bridge (Type A) (609.0301) | LF | 336 | $140.00 | $250.00 | $130.00 | $185.00 |
| 125 | Stone Curb – Bridge (Type F1) (609.0302) | LF | 289 | $86.00 | $150.00 | $95.00 | $150.00 |
| 126 | (609.0401) | LF | 1,217 | $49.00 | $60.00 | $140.00 | $65.00 |
| 127 | Mulch for Planting Type A, B & D Wood Chips and Shredded Bark (610.1101) | CY | 14 | $165.00 | $150.00 | $200.00 | $170.00 |
| 128 | Topsoil - Roadside (610.1402) | CY | 160 | $100.00 | $90.00 | $100.00 | $160.00 |
| 129 | Topsoil - Lawns (610.1403) | CY | 118 | $90.00 | $100.00 | $120.00 | $160.00 |
| 130 | Turf Establishment – Performance (610.1605) | SY | 9,414 | $16.00 | $15.00 | $18.00 | $25.00 |
| 131 | Wildflower Seeding (610.17) | SY | 1,380 | $2.95 | $2.00 | $6.00 | $6.00 |
| 132 | (611.0151) | EACH | 5 | $1,650.00 | $2,000.00 | $1,500.00 | $1,500.00 |
| 133 | (611.0211) | EACH | 3 | $1,375.00 | $1,500.00 | $1,400.00 | $1,500.00 |
| 134 | (611.0442) | EACH | 3 | $165.00 | $200.00 | $500.00 | $200.00 |
| 135 | (611.0452) | EACH | 11 | $220.00 | $400.00 | $800.00 | $375.00 |
| 136 | (611.0461) | EACH | 6 | $715.00 | $750.00 | $1,200.00 | $450.00 |
| 137 | (611.0591) | EACH | 4 | $825.00 | $1,000.00 | $1,300.00 | $475.00 |
| 138 | (611.0751) | EACH | 22 | $88.00 | $100.00 | $400.00 | $100.00 |
| 139 | (611.19010024) | 5 | $55.00 | $50.00 | $50.00 | $200.00 | |
| 140 | (611.19020024) | 3 | $55.00 | $50.00 | $50.00 | $200.00 | |
| 141 | (611.19030024) | 4 | $55.00 | $50.00 | $50.00 | $100.00 | |
| 142 | (611.19040024) | 20 | $11.00 | $10.00 | $50.00 | $100.00 | |
| 143 | (611.19070024) | 22 | $11.00 | $10.00 | $50.00 | $25.00 | |
| 144 | (614.060204) | EACH | 5 | $250.00 | $1,000.00 | $750.00 | $1,500.00 |
| 145 | (614.060304) | EACH | 5 | $625.00 | $1,500.00 | $1,250.00 | $2,000.00 |
| 146 | (614.060404) | EACH | 8 | $1,900.00 | $3,500.00 | $2,500.00 | $2,500.00 |
| 147 | (614.060504) | EACH | 7 | $3,000.00 | $5,000.00 | $4,000.00 | $3,500.00 |
| 148 | (617.10000024) | 8,878 | $37.00 | $0.01 | $1.50 | $25.00 | |
| 149 | (617.11000024) | LS | 1 | $500.00 | $1,000.00 | $100.00 | $2,000.00 |
| 150 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $418,000 | $3,678,325 | $1,250,000 | $800,000 |
| 151 | Type III Construction Barricades (619.04) | EACH | 95 | $145.00 | $100.00 | $175.00 | $150.00 |
| 152 | (619.0501) | LS | 1 | $1,150,000 | $800,000 | $1,850,000 | $1,375,000 |
| 153 | (619.0502) | LS | 1 | $200,000 | $150,000 | $115,000 | $200,000 |
| 154 | (619.0503) | LS | 1 | $1,000,000 | $800,000 | $1,700,000 | $1,375,000 |
| 155 | (619.06010009) | 2 | $125,000 | $150,000 | $380,000 | $250,000 | |
| 156 | (619.080101) | LF | 11,279 | $0.40 | $1.00 | $1.00 | $0.75 |
| 157 | (619.080102) | LF | 890 | $0.40 | $3.00 | $4.00 | $3.50 |
| 158 | (619.080106) | LF | 3,863 | $1.90 | $3.50 | $2.50 | $2.00 |
| 159 | Cover Existing Pavement Marking Stripes (Removable Tape) (619.0803) | LF | 300 | $8.00 | $10.00 | $12.00 | $8.00 |
| 160 | (619.100101) | LF | 27,047 | $0.48 | $0.75 | $0.60 | $0.50 |
| 161 | (619.100103) | LF | 17,085 | $1.70 | $3.00 | $1.75 | $6.00 |
| 162 | (619.100201) | EACH | 5 | $105.00 | $250.00 | $300.00 | $350.00 |
| 163 | (619.111113) | EACH | 6 | $20,000 | $10,000 | $14,000 | $20,000 |
| 164 | (619.130201) | EACH | 3 | $18,000 | $15,000 | $30,000 | $60,000 |
| 165 | Maintain Traffic Signal Equipment (Requirement C) Intersection (619.1613) | MONTH | 20 | $165.00 | $150.00 | $250.00 | $500.00 |
| 166 | (619.17060005) | 4,280 | $4.00 | $5.00 | $6.00 | $1.00 | |
| 167 | Temporary Positive Barrier – Category 1 (Pinning Prohibited) (619.1711) | LF | 2,972 | $48.00 | $20.00 | $65.00 | $75.00 |
| 168 | Temporary Positive Barrier – Category 2 (Pinning Permitted) (619.1712) | LF | 270 | $125.00 | $20.00 | $75.00 | $75.00 |
| 169 | Temporary Positive Barrier – Category 3 (Pinning Prohibited) (619.1713) | LF | 270 | $35.00 | $30.00 | $65.00 | $75.00 |
| 170 | Temporary Positive Barrier – Category 6 (Pinning Required) (619.1716) | LF | 1,471 | $67.00 | $30.00 | $75.00 | $75.00 |
| 171 | Temporary Positive Barrier – Category 7 (Pinning and Box-Beam-Stiffening Required) (619.1717) | LF | 280 | $125.00 | $40.00 | $90.00 | $150.00 |
| 172 | Temporary Impact Attenuator - Redirective (Test Level 3) (619.1803) | EACH | 17 | $5,500.00 | $3,500.00 | $5,000.00 | $6,500.00 |
| 173 | Mailboxes (619.27) | EACH | 6 | $240.00 | $300.00 | $300.00 | $500.00 |
| 174 | Stone Filling (Light) (620.03) | CY | 66 | $175.00 | $200.00 | $225.00 | $175.00 |
| 175 | Stone Filling (Medium) (620.04) | CY | 223 | $150.00 | $225.00 | $170.00 | $250.00 |
| 176 | Stone Filling (Heavy) (620.05) | CY | 968 | $155.00 | $175.00 | $175.00 | $300.00 |
| 177 | Bedding Material, Type 1 (620.0801) | CY | 176 | $114.00 | $150.00 | $150.00 | $150.00 |
| 178 | Bedding Material, Type 2 (620.0802) | CY | 156 | $100.00 | $160.00 | $150.00 | $150.00 |
| 179 | (620.29010009) | 202 | $95.00 | $65.00 | $250.00 | $100.00 | |
| 180 | Cleaning Culverts with Span of More Than 50 in. (621.02) | LF | 20 | $125.00 | $50.00 | $200.00 | $250.00 |
| 181 | (621.51000015) | 96 | $7.00 | $30.00 | $15.00 | $10.00 | |
| 182 | Crushed Stone (In-Place Measure) (623.12) | CY | 481 | $150.00 | $100.00 | $125.00 | $125.00 |
| 183 | Survey Operations (625.01) | LS | 1 | $150,000 | $65,000 | $800,000 | $275,000 |
| 184 | Concrete Right of Way Markers Type L (Low) (625.04) | EACH | 11 | $675.00 | $750.00 | $860.00 | $800.00 |
| 185 | Steel Pin and Cap Right of Way Markers (625.05) | EACH | 12 | $300.00 | $100.00 | $1,250.00 | $500.00 |
| 186 | Permanent Survey Markers (625.06) | EACH | 4 | $950.00 | $1,000.00 | $2,500.00 | $1,500.00 |
| 187 | (627.50140008) | 5,128 | $4.50 | $3.00 | $10.00 | $8.00 | |
| 188 | Concrete Cylinder Curing Equipment (637.04) | EACH | 3 | $750.00 | $2,000.00 | $3,500.00 | $5,000.00 |
| 189 | Engineer’s Field Office – Type 2 (637.12) | MONTH | 40 | $1,900.00 | $2,000.00 | $3,000.00 | $3,250.00 |
| 190 | Office Technology and Supplies (637.34) | DOL | 6,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 191 | Partnering Workshop (637.35) | DOL | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 192 | Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102) | SF | 89 | $46.00 | $45.00 | $65.00 | $60.00 |
| 193 | Type A Sign Posts (645.81) | EACH | 20 | $235.00 | $225.00 | $270.00 | $275.00 |
| 194 | Reference Marker Panel (646.21) | EACH | 16 | $40.00 | $40.00 | $50.00 | $45.00 |
| 195 | Delineator, Snowplowing Marker, Supplementary Snowplowing Marker Panels (646.22) | EACH | 24 | $11.00 | $15.00 | $50.00 | $25.00 |
| 196 | Large Delineator, Large Snowplowing Marker, Large Supplementary Snowplowing Marker Panel (646.23) | EACH | 21 | $20.00 | $20.00 | $30.00 | $30.00 |
| 197 | Steel Post, 2.0 lb/ft (646.32) | EACH | 47 | $73.00 | $75.00 | $120.00 | $125.00 |
| 198 | Brackets for Barrier and Multidirectional Mounting (646.50) | EACH | 2 | $110.00 | $100.00 | $120.00 | $125.00 |
| 199 | Remove and Store Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.41) | EACH | 2 | $75.00 | $100.00 | $20.00 | $25.00 |
| 200 | Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61) | EACH | 22 | $75.00 | $65.00 | $20.00 | $25.00 |
| 201 | (647.83001002) | 26 | $18.00 | $35.00 | $20.00 | $25.00 | |
| 202 | Centerline Audible Roadway Delineators (CARDs) (649.11) | LF | 3,908 | $1.25 | $2.50 | $1.50 | $1.25 |
| 203 | Welded Frame & Rectangular Grate 3 (655.1003) | EACH | 1 | $1,500.00 | $1,000.00 | $2,000.00 | $1,500.00 |
| 204 | Welded Frame & Reticuline Grate 3 (655.1103) | EACH | 13 | $1,900.00 | $1,000.00 | $2,500.00 | $1,500.00 |
| 205 | Manhole Frame & Cover (655.1202) | EACH | 4 | $2,100.00 | $1,000.00 | $2,500.00 | $1,500.00 |
| 206 | (663.0106) | LF | 5 | $195.00 | $250.00 | $1,000.00 | $275.00 |
| 207 | (663.0112) | LF | 16 | $135.00 | $200.00 | $800.00 | $200.00 |
| 208 | (663.0124) | LF | 321 | $430.00 | $850.00 | $715.00 | $900.00 |
| 209 | (663.0406) | LF | 18 | $61.00 | $100.00 | $750.00 | $100.00 |
| 210 | (663.0408) | LF | 551 | $135.00 | $350.00 | $265.00 | $400.00 |
| 211 | (663.0420) | LF | 329 | $250.00 | $650.00 | $475.00 | $750.00 |
| 212 | (663.0603) | LF | 74 | $23.00 | $25.00 | $100.00 | $20.00 |
| 213 | (663.1006) | EACH | 1 | $2,700.00 | $2,500.00 | $3,000.00 | $8,000.00 |
| 214 | (663.1008) | EACH | 6 | $3,355.00 | $3,500.00 | $4,000.00 | $8,000.00 |
| 215 | (663.1012) | EACH | 2 | $5,900.00 | $6,000.00 | $6,500.00 | $8,000.00 |
| 216 | (663.1124) | EACH | 2 | $21,000 | $15,000 | $14,000 | $20,000 |
| 217 | (663.1301) | EACH | 1 | $6,500.00 | $10,000 | $8,000.00 | $10,000 |
| 218 | (663.1724) | EACH | 2 | $285,000 | $200,000 | $190,000 | $200,000 |
| 219 | (663.1806) | EACH | 6 | $960.00 | $1,000.00 | $1,200.00 | $1,000.00 |
| 220 | (663.1824) | EACH | 2 | $1,750.00 | $6,000.00 | $5,000.00 | $7,000.00 |
| 221 | Iron Water Main Fittings (3 - 8 inch diameter) (663.2001) | LB | 1,626 | $16.00 | $13.00 | $17.00 | $12.00 |
| 222 | Iron Water Main Fittings (10 - 16 inch diameter) (663.2002) | LB | 253 | $18.00 | $15.00 | $17.00 | $13.00 |
| 223 | Iron Water Main Fittings (18 inch diameter and larger) (663.2003) | LB | 5,617 | $15.00 | $16.00 | $17.00 | $15.00 |
| 224 | (663.2306) | LF | 21 | $2.30 | $2.00 | $10.00 | $2.00 |
| 225 | (663.2308) | LF | 68 | $2.30 | $2.00 | $10.00 | $2.00 |
| 226 | (663.2312) | LF | 26 | $2.50 | $3.00 | $10.00 | $3.00 |
| 227 | (663.2324) | LF | 349 | $3.00 | $7.00 | $10.00 | $6.50 |
| 228 | (663.2503) | EACH | 1 | $2,700.00 | $7,500.00 | $2,500.00 | $8,000.00 |
| 229 | (663.2507) | EACH | 3 | $4,500.00 | $5,000.00 | $3,500.00 | $6,000.00 |
| 230 | (663.2701) | EACH | 1 | $11,000 | $6,000.00 | $6,000.00 | $8,000.00 |
| 231 | (663.2702) | EACH | 1 | $11,000 | $6,000.00 | $6,000.00 | $8,000.00 |
| 232 | (663.4106) | LF | 558 | $3.00 | $50.00 | $10.00 | $20.00 |
| 233 | (663.4124) | LF | 331 | $8.00 | $110.00 | $20.00 | $150.00 |
| 234 | Remove and Dispose of Existing Water Valve & Valve Box (663.42) | EACH | 4 | $315.00 | $3,000.00 | $600.00 | $5,000.00 |
| 235 | Remove and Dispose of Existing Water Service Connection (663.44) | EACH | 1 | $250.00 | $650.00 | $500.00 | $2,000.00 |
| 236 | Remove and Store Existing Hydrant (663.46) | EACH | 1 | $680.00 | $650.00 | $2,500.00 | $2,000.00 |
| 237 | (663.66031704) | 1 | $68.00 | $200.00 | $1,000.00 | $225.00 | |
| 238 | (680.510201) | EACH | 1 | $2,145.00 | $2,500.00 | $2,500.00 | $3,000.00 |
| 239 | (680.520506) | LF | 125 | $18.00 | $20.00 | $30.00 | $20.00 |
| 240 | (680.53080305) | 38 | $21.00 | $25.00 | $50.00 | $60.00 | |
| 241 | Inductance Loop Installation (680.54) | LF | 700 | $19.00 | $20.00 | $30.00 | $20.00 |
| 242 | Shielded Lead-in Cable (680.71) | LF | 2,012 | $3.30 | $5.00 | $4.00 | $5.00 |
| 243 | Inductance Loop Wire (680.72) | LF | 1,360 | $2.20 | $5.00 | $5.00 | $5.00 |
| 244 | (680.78010005) | 2 | $660.00 | $750.00 | $1,000.00 | $2,000.00 | |
| 245 | White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102) | LF | 12,629 | $0.65 | $0.75 | $1.00 | $0.75 |
| 246 | Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202) | LF | 9,004 | $0.65 | $0.75 | $1.00 | $0.75 |
| 247 | White Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3104) | LF | 158 | $6.30 | $6.00 | $33.00 | $7.50 |
| 248 | White Epoxy Reflectorized Pavement Symbols - 20 mil Portable/Hand Application (685.3404) | EACH | 2 | $415.00 | $400.00 | $450.00 | $500.00 |
| 249 | (691.04000020) | 136,500 | $1.00 | $1.00 | $1.00 | $1.00 | |
| 250 | Field Change Payment (FCP) (697.03) | DOL | 1,710,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 251 | Asphalt Price Adjustment (698.04) | DOL | 8,697 | $1.00 | $1.00 | $1.00 | $1.00 |
| 252 | Fuel Price Adjustment (698.05) | DOL | 2,194 | $1.00 | $1.00 | $1.00 | $1.00 |
| 253 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 |
| 254 | Mobilization (699.040001) | LS | 1 | $916,500 | $936,178 | $1,100,000 | $1,154,252 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of March 12, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.