NYSDOT contract D265648 bid tabulation
ROADWAY RESURFACING - Route 303, SH 8448, 5002. Let by New York State DOT on January 8, 2026, Rockland, Region 08. 8 bids received; low bid $9,220,000 by Morano Brothers Corp.
- Owner
- New York State DOT
- Letting
- 08 JAN 2026
- Pay items
- 64
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Morano Brothers Corp | $9,220,000 | Low |
| 2 | Tilcon New York Inc | $9,474,000 | +3.0% |
| 3 | J D'Annunzio & Sons Inc | $9,771,680 | +6.0% |
| 4 | Kyle Conti Construction LLC | $10,999,999 | +19% |
| 5 | Yonkers Contracting Company Inc | $11,411,499 | +24% |
| 6 | Crisdel Group Inc | $11,428,673 | +24% |
| 7 | Elq Industries Inc | $12,373,607 | +34% |
| 8 | Montesano Bros Inc | $13,351,384 | +45% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Morano Brothers Corp | 2. Tilcon New York Inc | 3. J D'Annunzio & Sons Inc | 4. Kyle Conti Construction LLC | 5. Yonkers Contracting Company Inc | 6. Crisdel Group Inc |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Unclassified Excavation and Disposal (203.02) | CY | 447 | $105.00 | $265.00 | $115.00 | $185.00 | $225.00 | $268.04 |
| 2 | Embankment In Place (203.03) | CY | 4 | $150.00 | $500.00 | $155.00 | $110.00 | $100.00 | $127.30 |
| 3 | Select Granular Fill (203.07) | CY | 14 | $48.00 | $450.00 | $100.00 | $110.00 | $100.00 | $127.30 |
| 4 | (203.24010017) | 15 | $180.00 | $285.00 | $200.00 | $375.00 | $400.00 | $150.88 | |
| 5 | Trench and Culvert Excavation (206.0201) | CY | 26 | $38.00 | $350.00 | $500.00 | $155.00 | $100.00 | $3.31 |
| 6 | (304.11000008) | 168 | $122.00 | $415.00 | $200.00 | $180.00 | $75.00 | $478.57 | |
| 7 | Pavement Density Quality Adjustment to Asphalt Items (404.0002) | QUALITY UNIT | 1 | $140.00 | $140.00 | $140.00 | $140.00 | $140.00 | $140.00 |
| 8 | Longitudinal Joint Density Quality Adjustment to Asphalt Items (404.0003) | QUALITY UNIT | 260 | $140.00 | $140.00 | $140.00 | $140.00 | $140.00 | $140.00 |
| 9 | (404.0179) | TON | 1,238 | $143.00 | $150.00 | $160.00 | $180.00 | $125.00 | $184.63 |
| 10 | (404.02000118) | 30 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 | |
| 11 | (404.2579) | TON | 382 | $210.00 | $365.00 | $240.00 | $170.00 | $250.00 | $270.51 |
| 12 | (404.3779) | TON | 215 | $168.00 | $365.00 | $300.00 | $185.00 | $250.00 | $320.92 |
| 13 | (406.1261) | TON | 28,238 | $139.00 | $150.00 | $153.00 | $167.50 | $140.00 | $157.86 |
| 14 | Straight Tack Coat (407.0103) | GAL | 18,149 | $13.00 | $0.50 | $3.50 | $6.00 | $8.00 | $4.51 |
| 15 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 136,988 | $1.10 | $0.05 | $1.25 | $0.75 | $1.50 | $0.68 |
| 16 | Production Cold Milling of Bituminous Concrete (490.10) | SY | 84 | $121.00 | $325.00 | $200.00 | $27.00 | $400.00 | $282.95 |
| 17 | Production Cold-Mill Surface Planing of Bituminous Concrete (490.15) | SY | 208,826 | $5.60 | $5.35 | $7.40 | $6.50 | $10.00 | $7.74 |
| 18 | (502.0021) | 3 | $4,200.00 | $3,500.00 | $750.00 | $2,500.00 | $2,500.00 | $1,199.70 | |
| 19 | Performance Concrete Quality Adjustment - PCC Pavement (502.99) | QUALITY UNIT | 1 | $3.50 | $3.50 | $3.50 | $3.50 | $3.50 | $3.50 |
| 20 | (603.6003) | LF | 6 | $1,300.00 | $1,200.00 | $60.00 | $340.00 | $525.00 | $922.01 |
| 21 | Concrete Collars (603.77) | EACH | 4 | $1,500.00 | $5,000.00 | $1,500.00 | $700.00 | $2,500.00 | $2,635.54 |
| 22 | (604.070801) | EACH | 1 | $1,800.00 | $5,500.00 | $4,100.00 | $3,800.00 | $10,000 | $1,560.71 |
| 23 | (604.07600008) | 14 | $1,800.00 | $4,500.00 | $4,400.00 | $3,800.00 | $12,000 | $4,342.40 | |
| 24 | (604.300303) | LF | 10 | $1,200.00 | $2,100.00 | $400.00 | $975.00 | $3,000.00 | $1,224.27 |
| 25 | Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.000013) | QUALITY UNIT | 1 | $140.00 | $140.00 | $140.00 | $140.00 | $140.00 | $140.00 |
| 26 | Concrete Sidewalks and Driveways (608.0101) | CY | 1 | $1,100.00 | $3,500.00 | $2,500.00 | $1,800.00 | $2,000.00 | $850.98 |
| 27 | (609.0401) | LF | 65 | $270.00 | $300.00 | $90.00 | $221.00 | $120.00 | $98.34 |
| 28 | Topsoil - Roadside (610.1402) | CY | 2 | $80.00 | $950.00 | $500.00 | $575.00 | $1,625.00 | $1,723.80 |
| 29 | Turf Establishment - Roadside (610.1601) | SY | 17 | $2.00 | $310.00 | $100.00 | $62.00 | $250.00 | $265.20 |
| 30 | Basic Work Zone Traffic Control (Daily Operations) (619.0101) | LS | 1 | $300,000 | $485,000 | $409,489 | $475,000 | $700,001 | $950,000 |
| 31 | (619.0901) | LF | 145,000 | $0.50 | $0.30 | $0.25 | $0.45 | $0.38 | $0.32 |
| 32 | (619.110522) | EACH | 7 | $8,700.00 | $9,500.00 | $10,000 | $18,000 | $8,000.00 | $5,000.00 |
| 33 | Nighttime Operations (Entire Project) (619.24) | LS | 1 | $190,000 | $165,000 | $300,000 | $410,000 | $160,000 | $658,000 |
| 34 | Traffic Control Supervisor (619.25) | MONTH | 6 | $33,000 | $30,000 | $20,000 | $37,000 | $30,000 | $47,871 |
| 35 | (620.06520009) | 6 | $138.00 | $700.00 | $200.00 | $900.00 | $275.00 | $102.58 | |
| 36 | Cleaning Closed Drainage Systems (621.03) | LF | 840 | $14.00 | $35.00 | $10.00 | $10.00 | $10.00 | $10.08 |
| 37 | Cleaning Drainage Structures (621.04) | EACH | 65 | $580.00 | $1,250.00 | $400.00 | $500.00 | $850.00 | $689.52 |
| 38 | Clean, Grade and Shape Existing Roadside Section (621.05) | LF | 3,000 | $4.00 | $10.00 | $6.00 | $23.00 | $15.00 | $9.16 |
| 39 | Asphalt Gutter (624.020101) | TON | 115 | $204.00 | $175.00 | $400.00 | $255.00 | $350.00 | $284.98 |
| 40 | Plant Production Quality Adjustment to 624.020101 (624.020110) | QUALITY UNIT | 6 | $110.00 | $110.00 | $110.00 | $110.00 | $110.00 | $110.00 |
| 41 | Survey Operations (625.01) | LS | 1 | $50,000 | $35,000 | $35,000 | $78,500 | $50,000 | $27,415 |
| 42 | (627.50140008) | 1,673 | $5.00 | $10.00 | $4.00 | $5.70 | $10.00 | $1.87 | |
| 43 | (633.05040008) | LS | 1 | $220,000 | $195,000 | $250,000 | $180,000 | $742,000 | $73,458 |
| 44 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $7,200.00 | $2,000.00 | $1,000.00 | $34,000 | $3,000.00 | $5,304.00 |
| 45 | Engineer’s Field Office – Type 3 (637.13) | MONTH | 10 | $7,500.00 | $10,000 | $6,000.00 | $10,750 | $15,000 | $5,571.50 |
| 46 | Office Technology and Supplies (637.34) | DOL | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 47 | (649.31000008) | 13,796 | $1.30 | $1.50 | $1.25 | $1.50 | $1.50 | $0.53 | |
| 48 | (655.07030010) | 8 | $3,000.00 | $2,450.00 | $1,700.00 | $3,150.00 | $3,500.00 | $2,831.30 | |
| 49 | Cast Frame F3, UnMountable Curb Box CU3 & Reticuline Grate G3 (655.0706) | EACH | 4 | $3,200.00 | $2,600.00 | $1,700.00 | $3,600.00 | $3,500.00 | $3,090.17 |
| 50 | (680.05010007) | 6 | $26,000 | $27,000 | $20,000 | $37,500 | $24,640 | $25,739 | |
| 51 | (680.51200208) | 15 | $160.00 | $1,200.00 | $1,000.00 | $1,800.00 | $130.00 | $1,490.42 | |
| 52 | (685.02000007) | 330 | $25.00 | $10.00 | $10.00 | $34.00 | $25.00 | $106.08 | |
| 53 | (685.16010014) | 186,169 | $1.50 | $1.40 | $1.05 | $1.70 | $1.35 | $1.06 | |
| 54 | (685.17010009) | 21,420 | $1.20 | $0.70 | $0.65 | $1.30 | $1.05 | $1.06 | |
| 55 | (685.17010014) | 62,243 | $1.50 | $1.40 | $1.00 | $1.70 | $1.35 | $1.06 | |
| 56 | White Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3104) | LF | 107,044 | $2.70 | $2.50 | $1.50 | $3.15 | $2.50 | $2.76 |
| 57 | Yellow Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3204) | LF | 117,847 | $2.00 | $2.50 | $1.50 | $2.50 | $1.95 | $2.76 |
| 58 | White Epoxy Reflectorized Pavement Letters - 20 mil Portable/Hand Application (685.3304) | EACH | 170 | $135.00 | $75.00 | $45.00 | $160.00 | $125.00 | $265.20 |
| 59 | White Epoxy Reflectorized Pavement Symbols - 20 mil Portable/Hand Application (685.3404) | EACH | 65 | $160.00 | $215.00 | $160.00 | $190.00 | $150.00 | $265.20 |
| 60 | Field Change Payment (FCP) (697.03) | DOL | 400,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 61 | Asphalt Price Adjustment (698.04) | DOL | 2,643 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 62 | Fuel Price Adjustment (698.05) | DOL | 6,660 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 63 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 64 | Mobilization (699.040001) | LS | 1 | $291,467 | $125,863 | $375,000 | $310,104 | $400,000 | $420,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of January 8, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.