NYSDOT contract D265653 bid tabulation
PAVEMENT PREVENTATIVE MAINTENANCE - I-287. Let by New York State DOT on February 5, 2026, Westchester, Region 08. 6 bids received; low bid $25,928,265 by Grace Industries LLC.
- Owner
- New York State DOT
- Letting
- 05 FEB 2026
- Pay items
- 55
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Grace Industries LLC | $25,928,265 | Low |
| 2 | Jrcruz Corp | $29,852,904 | +15% |
| 3 | Yonkers Contracting Company Inc | $30,711,237 | +18% |
| 4 | Restani Construction Corp | $35,224,932 | +36% |
| 5 | Elq Industries Inc | $36,296,197 | +40% |
| 6 | J D'Annunzio & Sons Inc | $36,344,287 | +40% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Grace Industries LLC | 2. Jrcruz Corp | 3. Yonkers Contracting Company Inc | 4. Restani Construction Corp | 5. Elq Industries Inc | 6. J D'Annunzio & Sons Inc |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Pavement Density Quality Adjustment to Asphalt Items (404.0002) | QUALITY UNIT | 3,031 | $140.00 | $140.00 | $140.00 | $140.00 | $140.00 | $140.00 |
| 2 | Longitudinal Joint Density Quality Adjustment to Asphalt Items (404.0003) | QUALITY UNIT | 1,000 | $140.00 | $140.00 | $140.00 | $140.00 | $140.00 | $140.00 |
| 3 | (404.0179) | TON | 2,700 | $180.00 | $200.00 | $150.00 | $100.00 | $166.00 | $200.00 |
| 4 | (404.1979) | TON | 3,650 | $237.00 | $300.00 | $475.00 | $385.00 | $732.00 | $700.00 |
| 5 | (406.1251) | TON | 60,620 | $193.00 | $205.00 | $155.00 | $185.00 | $178.40 | $165.00 |
| 6 | Straight Tack Coat (407.0103) | GAL | 27,020 | $4.75 | $9.00 | $10.00 | $15.00 | $8.40 | $4.00 |
| 7 | (407.01120007) | 3,700 | $7.50 | $6.00 | $20.00 | $10.00 | $13.00 | $20.00 | |
| 8 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 649,420 | $0.20 | $1.00 | $0.80 | $1.00 | $0.70 | $0.65 |
| 9 | Production Cold-Mill Surface Planing of Bituminous Concrete (490.15) | SY | 478,920 | $6.00 | $8.00 | $6.00 | $8.00 | $7.90 | $7.50 |
| 10 | Miscellaneous Cold Milling of Bituminous Concrete (490.30) | SY | 12,240 | $20.00 | $25.00 | $75.00 | $95.00 | $131.35 | $150.00 |
| 11 | (502.0021) | 20 | $1,900.00 | $1,500.00 | $275.00 | $1,350.00 | $499.00 | $3,000.00 | |
| 12 | Performance Concrete Quality Adjustment - PCC Pavement (502.99) | QUALITY UNIT | 1 | $3.50 | $3.50 | $3.50 | $3.50 | $3.50 | $3.50 |
| 13 | (604.070801) | EACH | 10 | $2,100.00 | $1,600.00 | $5,500.00 | $1,750.00 | $2,600.00 | $4,000.00 |
| 14 | (604.07290010) | 400 | $100.00 | $100.00 | $150.00 | $100.00 | $75.00 | $70.00 | |
| 15 | (604.07600008) | 160 | $2,100.00 | $5,250.00 | $5,500.00 | $4,500.00 | $6,760.00 | $4,975.00 | |
| 16 | (604.07610008) | 100 | $3,200.00 | $5,500.00 | $5,600.00 | $5,000.00 | $7,545.00 | $6,250.00 | |
| 17 | Concrete Sidewalks and Driveways (608.0101) | CY | 10 | $3,500.00 | $750.00 | $3,000.00 | $2,500.00 | $3,000.00 | $2,525.00 |
| 18 | (608.02010015) | 30 | $250.00 | $90.00 | $700.00 | $200.00 | $337.00 | $500.00 | |
| 19 | (608.02020015) | 10 | $250.00 | $250.00 | $75.00 | $100.00 | $516.00 | $200.00 | |
| 20 | (608.21000003) | 60 | $300.00 | $250.00 | $300.00 | $600.00 | $350.00 | $500.00 | |
| 21 | (609.0401) | LF | 2,780 | $90.00 | $115.00 | $75.00 | $200.00 | $120.00 | $170.00 |
| 22 | Turf Establishment – Performance (610.1605) | SY | 870 | $17.00 | $10.00 | $15.00 | $30.00 | $17.00 | $16.00 |
| 23 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $1,200,000 | $2,500,000 | $2,989,001 | $4,570,000 | $4,490,000 | $4,000,000 |
| 24 | (619.0901) | LF | 335,055 | $0.40 | $0.50 | $0.40 | $0.40 | $0.40 | $0.40 |
| 25 | (619.110511) | EACH | 8 | $20,000 | $10,000 | $15,000 | $15,275 | $25,000 | $30,000 |
| 26 | Maintain Traffic Signal Equipment (Requirement B) Intersection (619.1612) | MONTH | 8 | $296.00 | $450.00 | $250.00 | $350.00 | $270.00 | $300.00 |
| 27 | Nighttime Operations (Entire Project) (619.24) | LS | 1 | $610,000 | $250,000 | $1,400,000 | $2,000,000 | $2,000,000 | $2,000,000 |
| 28 | Traffic Control Supervisor (619.25) | MONTH | 22 | $8,500.00 | $12,000 | $30,000 | $25,000 | $28,000 | $24,000 |
| 29 | Pavement Patching (Force Acount) (619.2601) | DOL | 20,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 30 | Cleaning Closed Drainage Systems (621.03) | LF | 12,420 | $14.00 | $10.00 | $9.00 | $9.70 | $14.20 | $9.00 |
| 31 | Cleaning Drainage Structures (621.04) | EACH | 400 | $770.00 | $1,000.00 | $575.00 | $1,100.00 | $694.00 | $500.00 |
| 32 | Clean, Grade and Shape Existing Roadside Section (621.05) | LF | 48,620 | $7.50 | $1.50 | $7.00 | $6.00 | $6.55 | $5.00 |
| 33 | Survey Operations (625.01) | LS | 1 | $30,000 | $100,000 | $75,000 | $500,000 | $97,000 | $516,473 |
| 34 | (627.50140008) | 10,140 | $6.25 | $5.00 | $9.00 | $32.89 | $6.00 | $20.00 | |
| 35 | (633.05040008) | LS | 1 | $625,000 | $25,000 | $2,000,000 | $250,000 | $640,000 | $2,000,000 |
| 36 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $3,000.00 | $3,500.00 | $3,000.00 | $15,000 | $6,500.00 | $10,000 |
| 37 | Engineer’s Field Office – Type 4 (637.14) | MONTH | 24 | $5,000.00 | $8,200.00 | $7,000.00 | $15,000 | $7,300.00 | $10,000 |
| 38 | Office Technology and Supplies (637.34) | DOL | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 39 | Milled-In Audible Roadway Delineators (MIARDs) (649.01) | LF | 110,880 | $0.40 | $0.50 | $0.70 | $0.14 | $0.60 | $0.65 |
| 40 | Pavement Ride Quality Adjustment to Asphalt Level 2 (653.1020) | QUALITY UNIT | 2,400 | $90.00 | $90.00 | $90.00 | $90.00 | $90.00 | $90.00 |
| 41 | Cast Frame F2, UnMountable Curb Box CU2 & Reticuline Grate G2 (655.0705) | EACH | 60 | $1,600.00 | $3,000.00 | $2,800.00 | $1,500.00 | $1,800.00 | $1,600.00 |
| 42 | (680.05010007) | 8 | $33,300 | $30,000 | $28,200 | $29,806 | $30,400 | $28,500 | |
| 43 | (680.05020007) | 8 | $5,670.00 | $7,500.00 | $4,800.00 | $4,381.00 | $5,200.00 | $5,000.00 | |
| 44 | (680.51200208) | 32 | $1,580.00 | $1,800.00 | $200.00 | $1,334.00 | $304.00 | $1,600.00 | |
| 45 | (685.07200810) | 5 | $100.00 | $110.00 | $85.00 | $85.00 | $92.00 | $80.00 | |
| 46 | (685.16010014) | 213,310 | $1.50 | $1.50 | $1.30 | $1.30 | $1.40 | $1.25 | |
| 47 | (685.17010014) | 121,760 | $1.50 | $1.50 | $1.30 | $1.30 | $1.40 | $1.25 | |
| 48 | White Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3104) | LF | 32,430 | $3.00 | $3.20 | $2.50 | $2.50 | $2.70 | $2.45 |
| 49 | White Epoxy Reflectorized Pavement Letters - 20 mil Portable/Hand Application (685.3304) | EACH | 112 | $171.00 | $200.00 | $145.00 | $145.00 | $157.00 | $150.00 |
| 50 | White Epoxy Reflectorized Pavement Symbols - 20 mil Portable/Hand Application (685.3404) | EACH | 39 | $195.00 | $220.00 | $165.00 | $165.00 | $178.00 | $170.00 |
| 51 | Field Change Payment (FCP) (697.03) | DOL | 1,250,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 52 | Asphalt Price Adjustment (698.04) | DOL | 98,700 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 53 | Fuel Price Adjustment (698.05) | DOL | 135,003 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 54 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 55 | Mobilization (699.040001) | LS | 1 | $990,000 | $1,148,189 | $1,000,000 | $1,354,162 | $1,390,000 | $1,380,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of February 5, 2026. Compiled by Mirage Metrics.