NYSDOT contract D265367 bid tabulation
Bridge Deck Replacement. Let by New York State DOT on January 9, 2025, Westchester, Region 08. 7 bids received; low bid $7,410,000 by El Sol Contracting / Es II Enterprises JV.
- Owner
- New York State DOT
- Letting
- 09 JAN 2025
- Pay items
- 105
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | El Sol Contracting / Es II Enterprises JV | $7,410,000 | Low |
| 2 | Transit-Halmar JV | $8,633,343 | +17% |
| 3 | Elq Industries Inc | $8,950,183 | +21% |
| 4 | Defoe Corporation | $9,502,721 | +28% |
| 5 | Gianfia Corp | $9,557,916 | +29% |
| 6 | McNamee Construction Corp | $10,174,000 | +37% |
| 7 | John Civetta & Sons Inc | $11,972,300 | +62% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. El Sol Contracting / Es II Enterprises JV | 2. Transit-Halmar JV | 3. Elq Industries Inc | 4. Defoe Corporation | 5. Gianfia Corp | 6. McNamee Construction Corp |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.06) | LS | 1 | $15,000 | $75,000 | $50,000 | $50,000 | $35,000 | $117,000 |
| 2 | Removal of Steel Supported Structural Slabs (with shear connectors) – Type A (202.2201) | SF | 16,200 | $65.00 | $110.00 | $75.00 | $107.00 | $52.00 | $70.00 |
| 3 | Structure Excavation (206.01) | CY | 450 | $50.00 | $240.00 | $154.00 | $165.00 | $320.00 | $150.00 |
| 4 | Conduit Excavation and Backfill including Surface Restoration (206.03) | LF | 1,887 | $50.00 | $25.00 | $1.00 | $70.00 | $44.00 | $48.00 |
| 5 | Test Pit Excavation (206.05) | EACH | 1 | $1,500.00 | $3,000.00 | $3,100.00 | $3,500.00 | $2,300.00 | $4,000.00 |
| 6 | Prefabricated Composite Structural Drain (207.26) | SY | 80 | $70.00 | $20.00 | $28.00 | $95.00 | $7.00 | $33.00 |
| 7 | Sediment Filter Log, 12″ (209.2301) | LF | 120 | $10.00 | $40.00 | $24.00 | $55.00 | $28.00 | $10.00 |
| 8 | Removal and Disposal of Bond Breaker/Filler ACM (BV14) (210.3312) | SF | 100 | $145.00 | $150.00 | $284.00 | $145.00 | $295.00 | $150.00 |
| 9 | (404.0001) | TON | 36 | $110.00 | $110.00 | $110.00 | $110.00 | $110.00 | $110.00 |
| 10 | (404.0973) | TON | 716 | $280.00 | $200.00 | $275.00 | $290.00 | $280.00 | $225.00 |
| 11 | Straight Tack Coat (407.0103) | GAL | 284 | $30.00 | $15.00 | $39.00 | $27.00 | $50.00 | $30.00 |
| 12 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 6,024 | $5.00 | $1.50 | $4.50 | $3.00 | $1.00 | $2.00 |
| 13 | Miscellaneous Cold Milling of Bituminous Concrete (490.30) | SY | 8,081 | $13.00 | $5.00 | $20.00 | $13.00 | $14.00 | $6.50 |
| 14 | Concrete for Structures, Performance (555.0021) | CY | 15 | $8,000.00 | $1,500.00 | $3,500.00 | $2,500.00 | $3,900.00 | $4,400.00 |
| 15 | Performance Concrete Quality Adjustment – Concrete for Structures (555.9902) | QUALITY UNIT | 1 | $17.50 | $17.50 | $17.50 | $17.50 | $17.50 | $17.50 |
| 16 | Epoxy-Coated Bar Reinforcement for Structures (556.0202) | LB | 3,000 | $5.00 | $3.00 | $2.10 | $3.00 | $2.12 | $4.25 |
| 17 | Stud Shear Connectors for Bridges (556.03) | EACH | 7,410 | $8.00 | $9.00 | $14.00 | $8.00 | $7.00 | $7.00 |
| 18 | (557.1012) | SY | 560 | $600.00 | $700.00 | $700.00 | $400.00 | $715.00 | $1,000.00 |
| 19 | (557.1112) | SY | 1,800 | $800.00 | $960.00 | $1,075.00 | $931.00 | $750.00 | $870.00 |
| 20 | Winter Surface Treatment – Superstructure Slabs and Structural Approach Slabs (557.29) | SY | 2,425 | $5.00 | $11.00 | $12.00 | $9.00 | $31.00 | $31.00 |
| 21 | Sidewalks and Safety Walks (557.30) | SY | 1,000 | $150.00 | $150.00 | $230.00 | $220.00 | $186.00 | $185.00 |
| 22 | Performance Concrete Quality Adjustment – Superstructure and Approach Slab (557.9901) | QUALITY UNIT | 1 | $33.96 | $33.96 | $33.96 | $33.96 | $33.96 | $33.96 |
| 23 | Performance Concrete Quality Adjustment – Sidewalks and Safety Walks (557.9902) | QUALITY UNIT | 1 | $9.00 | $9.00 | $9.00 | $9.00 | $9.00 | $9.00 |
| 24 | Longitudinal Sawcut Grooving of Structural Slab Surface (558.02) | SY | 1,344 | $16.00 | $25.00 | $76.00 | $19.00 | $14.88 | $50.00 |
| 25 | Protective Sealing of Structural Concrete on New Bridge Decks and Bridge Deck Overlays (559.01) | SF | 22,000 | $2.00 | $1.25 | $1.35 | $1.25 | $2.00 | $2.00 |
| 26 | Protective Sealing of New Structural Concrete (559.02) | SF | 4,000 | $2.00 | $2.25 | $2.50 | $2.25 | $4.00 | $2.00 |
| 27 | (560.13060108) | 600 | $65.00 | $195.00 | $210.00 | $200.00 | $185.00 | $180.00 | |
| 28 | (564.100001) | LB | 1,475 | $75.00 | $125.00 | $125.00 | $130.00 | $76.93 | $30.00 |
| 29 | (564.510001) | LB | 4,500 | $75.00 | $125.00 | $90.00 | $110.00 | $88.36 | $61.00 |
| 30 | Armorless Bridge Joint (567.60) | LF | 106 | $500.00 | $75.00 | $470.00 | $570.00 | $485.00 | $375.00 |
| 31 | Steel Bridge Railing (Four-Rail) (568.51) | LF | 800 | $450.00 | $375.00 | $452.00 | $420.00 | $350.00 | $275.00 |
| 32 | Transition Bridge Railing (568.70) | LF | 130 | $400.00 | $275.00 | $400.00 | $370.00 | $270.00 | $175.00 |
| 33 | Lead-Exposure Control Plan (570.01) | LS | 1 | $3,500.00 | $5,000.00 | $1,140.00 | $10,500 | $4,300.00 | $5,000.00 |
| 34 | Medical Testing (570.02) | DOL | 1,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 35 | Personal-Exposure-Monitoring Sample Analysis (570.03) | DOL | 1,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 36 | Decontamination Facilities (570.04) | CALENDAR WEEK | 1 | $5,000.00 | $2,000.00 | $1,930.00 | $5,250.00 | $1,700.00 | $5,000.00 |
| 37 | (570.090003) | LS | 1 | $2,500.00 | $25,000 | $25,000 | $10,500 | $20,400 | $750,000 |
| 38 | (570.100001) | LS | 1 | $2,500.00 | $25,000 | $25,000 | $10,500 | $22,000 | $350,000 |
| 39 | Disposal of Hazardous Paint Removal Waste Containing Lead (571.03) | LB | 100 | $10.00 | $30.00 | $68.00 | $105.00 | $25.40 | $10.00 |
| 40 | (572.010001) | SF | 3,000 | $13.60 | $20.00 | $18.00 | $20.00 | $25.65 | $5.00 |
| 41 | (574.030001) | SF | 325 | $275.00 | $365.00 | $412.00 | $275.00 | $364.62 | $450.00 |
| 42 | Scuppers (Type B) (576.02) | EACH | 2 | $6,000.00 | $7,500.00 | $7,000.00 | $4,700.00 | $7,600.00 | $25.00 |
| 43 | Removal of Structural Concrete (580.01) | CY | 75 | $950.00 | $1,750.00 | $1,550.00 | $1,800.00 | $950.00 | $3,000.00 |
| 44 | Removal and Replacement of Structural Concrete (582.0051) | CY | 10 | $9,000.00 | $2,750.00 | $4,500.00 | $16,000 | $4,750.00 | $5,500.00 |
| 45 | (582.99) | 1 | $0.50 | $0.50 | $0.50 | $0.50 | $0.50 | $0.50 | |
| 46 | (585.01) | EACH | 7 | $20,000 | $35,000 | $30,000 | $22,000 | $7,796.75 | $23,000 |
| 47 | Drilling and Grouting Bolts or Reinforcing Bars (586.0201) | EACH | 300 | $45.00 | $50.00 | $70.00 | $72.00 | $48.00 | $150.00 |
| 48 | Drilling and Grouting Bolts or Reinforcing Bars with Pullout Test (586.0301) | EACH | 300 | $45.00 | $50.00 | $70.00 | $104.00 | $221.00 | $175.00 |
| 49 | Field Drill Holes in Existing Structural Steel (586.10) | EACH | 300 | $65.00 | $75.00 | $120.00 | $74.00 | $103.96 | $250.00 |
| 50 | Bridge Railing Removal and Disposal (587.01) | LF | 617 | $50.00 | $40.00 | $1.00 | $37.00 | $35.00 | $55.00 |
| 51 | (589.010001) | LB | 2,150 | $3.00 | $85.00 | $41.00 | $85.00 | $87.32 | $54.00 |
| 52 | (607.06400016) | 617 | $155.00 | $110.00 | $160.00 | $146.00 | $112.00 | $175.00 | |
| 53 | (607.99870011) | 610 | $20.00 | $40.00 | $16.00 | $15.00 | $50.00 | $25.00 | |
| 54 | Stone Curb – Bridge (Type F1) (609.0302) | LF | 800 | $120.00 | $85.00 | $55.00 | $51.00 | $48.00 | $75.00 |
| 55 | (617.11000024) | LS | 1 | $15,000 | $3,500.00 | $3,700.00 | $10,500 | $6,645.00 | $2,200.00 |
| 56 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $600,000 | $250,000 | $550,000 | $630,000 | $1,110,000 | $1,361,624 |
| 57 | Type III Construction Barricades (619.04) | EACH | 10 | $100.00 | $150.00 | $670.00 | $485.00 | $450.00 | $225.00 |
| 58 | (619.080101) | LF | 70 | $2.00 | $1.75 | $3.00 | $2.00 | $2.14 | $2.00 |
| 59 | (619.080102) | LF | 4,050 | $2.00 | $1.75 | $2.10 | $2.00 | $2.14 | $2.00 |
| 60 | (619.100101) | LF | 4,150 | $1.00 | $0.65 | $0.77 | $1.00 | $0.78 | $2.00 |
| 61 | (619.100103) | LF | 1,150 | $3.50 | $3.50 | $4.00 | $4.00 | $4.29 | $2.00 |
| 62 | (619.111112) | EACH | 2 | $5,000.00 | $20,000 | $25,000 | $21,000 | $30,000 | $20,000 |
| 63 | Temporary Positive Barrier – Category 1 (Pinning Prohibited) (619.1711) | LF | 980 | $23.00 | $10.00 | $32.00 | $62.00 | $117.00 | $20.00 |
| 64 | Temporary Positive Barrier – Category 6 (Pinning Required) (619.1716) | LF | 300 | $55.00 | $25.00 | $173.00 | $180.00 | $250.00 | $125.00 |
| 65 | Warning Lights on Temporary Positive Barriers (619.1719) | EACH | 41 | $70.00 | $75.00 | $230.00 | $236.00 | $173.00 | $25.00 |
| 66 | Nighttime Operations (Entire Project) (619.24) | LS | 1 | $45,000 | $20,000 | $88,000 | $115,000 | $1,210,000 | $15,000 |
| 67 | (619.67020010) | LS | 1 | $93,000 | $75,000 | $78,000 | $75,000 | $68,750 | $70,000 |
| 68 | Survey Operations (625.01) | LS | 1 | $80,000 | $125,000 | $100,000 | $254,000 | $84,000 | $175,000 |
| 69 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $2,500.00 | $5,500.00 | $8,200.00 | $3,000.00 | $6,500.00 | $5,000.00 |
| 70 | Engineer’s Field Office – Type 3 (637.13) | MONTH | 12 | $4,000.00 | $2,000.00 | $7,200.00 | $11,000 | $12,000 | $5,000.00 |
| 71 | Office Technology and Supplies (637.34) | DOL | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 72 | Partnering Workshop (637.35) | DOL | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 73 | Construction Testing supplies – Consumables (637.36) | DOL | 1,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 74 | (639.21010011) | LS | 1 | $27,000 | $25,000 | $30,000 | $25,000 | $25,000 | $75,000 |
| 75 | (659.18160008) | 325 | $25.00 | $25.00 | $25.00 | $25.00 | $25.00 | $25.00 | |
| 76 | (660.09020011) | 1 | $3,655.00 | $6,500.00 | $4,200.00 | $3,837.75 | $3,655.00 | $3,700.00 | |
| 77 | (660.65000101) | 1 | $6,200.00 | $750.00 | $1,100.00 | $4,377.74 | $10,180 | $500.00 | |
| 78 | (661.24110011) | 2 | $750.00 | $2,500.00 | $852.00 | $787.50 | $750.00 | $750.00 | |
| 79 | (662.17100108) | LS | 1 | $25,000 | $25,000 | $25,000 | $25,000 | $25,000 | $25,000 |
| 80 | (662.18100108) | LS | 1 | $45,000 | $45,000 | $45,000 | $45,000 | $45,000 | $45,000 |
| 81 | (662.60030008) | 1 | $4,200.00 | $750.00 | $550.00 | $10,500 | $1,360.00 | $600.00 | |
| 82 | (670.11250611) | 4 | $7,800.00 | $10,000 | $8,600.00 | $8,000.00 | $7,585.00 | $7,600.00 | |
| 83 | (670.1208) | EACH | 2 | $950.00 | $2,500.00 | $1,100.00 | $1,000.00 | $950.00 | $950.00 |
| 84 | (670.14480010) | 1 | $4,000.00 | $750.00 | $1,100.00 | $4,000.00 | $1,360.00 | $500.00 | |
| 85 | (670.2003) | LF | 1,587 | $42.00 | $35.00 | $48.00 | $44.00 | $41.50 | $42.00 |
| 86 | Cast Iron Junction Boxes (670.40) | EACH | 2 | $7,750.00 | $10,000 | $8,800.00 | $8,500.00 | $7,750.00 | $7,750.00 |
| 87 | (670.50040104) | 6 | $985.00 | $1,000.00 | $1,200.00 | $1,100.00 | $985.00 | $985.00 | |
| 88 | (670.60010011) | 6 | $75.00 | $110.00 | $86.00 | $80.00 | $75.00 | $75.00 | |
| 89 | (670.60020011) | 6 | $150.00 | $125.00 | $170.00 | $158.00 | $150.00 | $150.00 | |
| 90 | (670.7005) | LF | 6,395 | $3.00 | $5.00 | $3.25 | $3.00 | $2.85 | $3.00 |
| 91 | (670.7006) | LF | 525 | $2.50 | $5.00 | $2.70 | $3.00 | $2.35 | $3.00 |
| 92 | (670.75070011) | 1,862 | $2.25 | $5.00 | $2.50 | $3.00 | $2.20 | $3.00 | |
| 93 | (670.81200010) | 10 | $600.00 | $500.00 | $690.00 | $630.00 | $600.00 | $600.00 | |
| 94 | (670.91000008) | 2 | $650.00 | $1,100.00 | $740.00 | $685.00 | $650.00 | $650.00 | |
| 95 | (670.94110010) | LS | 1 | $3,692.04 | $12,000 | $4,000.00 | $3,675.00 | $3,500.00 | $3,500.00 |
| 96 | (680.520406) | LF | 63 | $79.00 | $100.00 | $90.00 | $85.00 | $78.75 | $80.00 |
| 97 | Yellow Epoxy Reflectorized Pavement Stripes - 15 mil (685.0201) | LF | 1,012 | $2.00 | $2.00 | $2.10 | $2.00 | $2.27 | $2.00 |
| 98 | White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102) | LF | 5,063 | $1.00 | $0.75 | $0.90 | $1.00 | $0.91 | $2.00 |
| 99 | Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202) | LF | 3,750 | $1.00 | $0.75 | $0.90 | $1.00 | $0.91 | $2.00 |
| 100 | (691.04000020) | 63,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | |
| 101 | Field Change Payment (FCP) (697.03) | DOL | 347,750 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 102 | Asphalt Price Adjustment (698.04) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 103 | Fuel Price Adjustment (698.05) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 104 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 105 | Mobilization (699.040001) | LS | 1 | $275,000 | $320,000 | $340,000 | $360,000 | $365,000 | $364,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of January 9, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way