NYSDOT contract D265712 bid tabulation
CORRIDOR PAVING RTE 304: ROCKLAND COUNTY. Let by New York State DOT on February 26, 2026, Rockland, Region 08. 6 bids received; low bid $18,877,285 by Yonkers Contracting Company Inc.
- Owner
- New York State DOT
- Letting
- 26 FEB 2026
- Pay items
- 69
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Yonkers Contracting Company Inc | $18,877,285 | Low |
| 2 | Grace Industries LLC | $19,787,583 | +5.0% |
| 3 | Elq Industries Inc | $23,777,841 | +26% |
| 4 | Crisdel Group Inc | $25,459,062 | +35% |
| 5 | Jrcruz Corp | $25,672,678 | +36% |
| 6 | Kyle Conti Construction LLC | $25,997,799 | +38% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Yonkers Contracting Company Inc | 2. Grace Industries LLC | 3. Elq Industries Inc | 4. Crisdel Group Inc | 5. Jrcruz Corp | 6. Kyle Conti Construction LLC |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Unclassified Excavation and Disposal (203.02) | CY | 7,010 | $75.00 | $130.00 | $138.00 | $285.32 | $80.00 | $106.00 |
| 2 | (203.24010017) | 190 | $200.00 | $123.00 | $135.00 | $192.49 | $100.00 | $435.00 | |
| 3 | (304.00010018) | 35,120 | $1.00 | $0.50 | $3.20 | $1.80 | $2.00 | $10.00 | |
| 4 | (304.11000008) | 4,670 | $90.00 | $150.00 | $176.00 | $272.49 | $80.00 | $106.00 | |
| 5 | Pavement Density Quality Adjustment to Asphalt Items (404.0002) | QUALITY UNIT | 1,298 | $140.00 | $140.00 | $140.00 | $140.00 | $140.00 | $140.00 |
| 6 | Longitudinal Joint Density Quality Adjustment to Asphalt Items (404.0003) | QUALITY UNIT | 164 | $140.00 | $140.00 | $140.00 | $140.00 | $140.00 | $140.00 |
| 7 | (404.0179) | TON | 940 | $155.00 | $184.00 | $150.00 | $164.85 | $200.00 | $102.00 |
| 8 | (404.1969) | TON | 5,670 | $180.00 | $200.00 | $179.00 | $230.76 | $350.00 | $170.00 |
| 9 | (406.1261) | TON | 22,810 | $155.00 | $184.00 | $149.00 | $149.63 | $215.00 | $185.00 |
| 10 | (407.01040009) | 13,920 | $10.00 | $4.50 | $7.00 | $4.68 | $8.00 | $10.00 | |
| 11 | (407.01120007) | 1,670 | $13.00 | $13.00 | $10.00 | $15.60 | $10.00 | $9.00 | |
| 12 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 144,688 | $1.15 | $0.15 | $0.85 | $0.60 | $1.00 | $0.45 |
| 13 | Production Cold-Mill Surface Planing of Bituminous Concrete (490.15) | SY | 166,150 | $7.50 | $8.50 | $7.00 | $7.92 | $6.00 | $5.00 |
| 14 | Miscellaneous Cold Milling of Bituminous Concrete (490.30) | SY | 9,690 | $18.00 | $26.00 | $22.00 | $49.51 | $50.00 | $21.50 |
| 15 | Production Grinding – Pavement Preservation with Slurry Removal (505.0402) | SY | 61,080 | $16.00 | $10.50 | $14.68 | $5.93 | $15.00 | $12.00 |
| 16 | (510.00210018) | 860 | $900.00 | $1,350.00 | $970.00 | $1,015.68 | $3,200.00 | $1,700.00 | |
| 17 | (510.01210018) | 130 | $950.00 | $1,520.00 | $1,125.00 | $1,331.41 | $3,200.00 | $1,850.00 | |
| 18 | (510.20000018) | 3,910 | $200.00 | $130.00 | $170.00 | $172.09 | $500.00 | $340.00 | |
| 19 | (510.81000018) | 5,380 | $15.00 | $12.31 | $122.00 | $49.27 | $45.00 | $77.50 | |
| 20 | (510.81100018) | 270 | $35.00 | $8.00 | $92.00 | $64.30 | $50.00 | $110.00 | |
| 21 | (510.90010018) | 9,630 | $14.00 | $11.00 | $13.00 | $5.25 | $8.00 | $3.85 | |
| 22 | (510.91000018) | 460 | $55.00 | $27.00 | $22.00 | $20.80 | $50.00 | $9.35 | |
| 23 | (511.50000018) | 4,070 | $200.00 | $280.00 | $267.00 | $284.41 | $250.00 | $302.00 | |
| 24 | (604.070801) | EACH | 10 | $3,500.00 | $2,200.00 | $4,500.00 | $2,565.96 | $2,303.80 | $3,100.00 |
| 25 | (604.07290010) | 300 | $150.00 | $120.00 | $96.00 | $257.89 | $150.00 | $62.00 | |
| 26 | (604.07600008) | 60 | $4,500.00 | $2,200.00 | $8,700.00 | $4,913.06 | $6,000.00 | $2,800.00 | |
| 27 | (604.07610008) | 50 | $5,500.00 | $3,300.00 | $8,700.00 | $6,316.88 | $7,200.00 | $3,100.00 | |
| 28 | Concrete Sidewalks and Driveways (608.0101) | CY | 60 | $1,600.00 | $2,700.00 | $3,100.00 | $1,758.88 | $1,500.00 | $935.00 |
| 29 | (608.02010015) | 140 | $435.00 | $335.00 | $330.00 | $297.68 | $100.00 | $270.00 | |
| 30 | (608.02020015) | 50 | $40.00 | $235.00 | $640.00 | $200.73 | $100.00 | $57.50 | |
| 31 | (608.21000003) | 18 | $300.00 | $305.00 | $260.00 | $832.00 | $250.00 | $250.00 | |
| 32 | (609.0401) | LF | 990 | $125.00 | $110.00 | $170.00 | $262.36 | $125.00 | $105.00 |
| 33 | Topsoil - Roadside (610.1402) | CY | 40 | $110.00 | $125.00 | $170.00 | $104.00 | $100.00 | $165.00 |
| 34 | Turf Establishment - Roadside (610.1601) | SY | 330 | $5.00 | $18.00 | $6.00 | $26.00 | $10.00 | $1.20 |
| 35 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $1,481,001 | $1,137,000 | $3,792,000 | $3,800,000 | $2,500,000 | $3,750,000 |
| 36 | (619.0901) | LF | 185,000 | $0.38 | $0.45 | $0.42 | $0.40 | $0.60 | $0.40 |
| 37 | (619.110511) | EACH | 8 | $12,500 | $22,000 | $29,000 | $14,643 | $10,000 | $20,000 |
| 38 | Maintain Traffic Signal Equipment (Requirement B) Intersection (619.1612) | MONTH | 15 | $360.00 | $300.00 | $387.00 | $494.00 | $470.00 | $450.00 |
| 39 | Nighttime Operations (Entire Project) (619.24) | LS | 1 | $100,000 | $600,000 | $1,430,000 | $2,411,850 | $250,000 | $2,600,000 |
| 40 | Traffic Control Supervisor (619.25) | MONTH | 10 | $25,000 | $25,000 | $42,000 | $36,543 | $15,000 | $65,000 |
| 41 | Pavement Patching (Force Acount) (619.2601) | DOL | 20,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 42 | Cleaning Closed Drainage Systems (621.03) | LF | 4,900 | $15.00 | $14.40 | $16.00 | $12.48 | $12.00 | $13.00 |
| 43 | Cleaning Drainage Structures (621.04) | EACH | 162 | $1,200.00 | $800.00 | $430.00 | $624.00 | $750.00 | $650.00 |
| 44 | Clean, Grade and Shape Existing Roadside Section (621.05) | LF | 14,850 | $9.00 | $9.00 | $7.00 | $6.08 | $2.00 | $8.25 |
| 45 | Survey Operations (625.01) | LS | 1 | $88,000 | $60,000 | $71,000 | $26,641 | $140,000 | $150,024 |
| 46 | (627.50140008) | 4,220 | $13.00 | $6.40 | $4.50 | $3.90 | $5.00 | $7.00 | |
| 47 | (633.05040008) | LS | 1 | $1,100,000 | $300,000 | $175,000 | $58,560 | $50,000 | $250,000 |
| 48 | (635.13010011) | 277,190 | $0.50 | $0.60 | $0.54 | $0.51 | $0.85 | $0.50 | |
| 49 | Engineer’s Field Office – Type 4 (637.14) | MONTH | 15 | $10,000 | $6,000.00 | $7,500.00 | $9,432.74 | $8,500.00 | $25,000 |
| 50 | Office Technology and Supplies (637.34) | DOL | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 51 | Milled-In Audible Roadway Delineators (MIARDs) (649.01) | LF | 50,080 | $1.00 | $0.45 | $0.22 | $0.51 | $0.75 | $0.50 |
| 52 | (649.31000008) | 45,140 | $1.00 | $1.20 | $0.30 | $0.51 | $1.00 | $0.55 | |
| 53 | (655.30010010) | 15 | $3,645.00 | $2,000.00 | $3,700.00 | $2,149.68 | $5,000.00 | $2,150.00 | |
| 54 | Adjust Existing Valve Box Elevation (663.33) | EACH | 14 | $1,900.00 | $100.00 | $980.00 | $285.74 | $1,250.00 | $170.00 |
| 55 | (680.05010007) | 15 | $27,000 | $32,000 | $29,000 | $31,382 | $36,000 | $35,000 | |
| 56 | (680.05020007) | 15 | $3,700.00 | $5,500.00 | $4,000.00 | $4,602.00 | $5,000.00 | $5,000.00 | |
| 57 | (680.51200208) | 38 | $75.00 | $1,650.00 | $655.00 | $1,560.00 | $1,600.00 | $2,000.00 | |
| 58 | (685.16010009) | 39,240 | $1.60 | $1.60 | $0.54 | $0.51 | $2.00 | $1.00 | |
| 59 | (685.16010014) | 109,790 | $1.60 | $1.60 | $1.30 | $1.23 | $2.00 | $1.60 | |
| 60 | (685.17010014) | 34,790 | $1.00 | $1.60 | $1.30 | $1.23 | $2.00 | $1.60 | |
| 61 | White Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3104) | LF | 24,890 | $1.95 | $3.00 | $3.25 | $3.07 | $2.75 | $1.95 |
| 62 | Yellow Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3204) | LF | 42,210 | $1.95 | $3.40 | $3.25 | $3.07 | $2.75 | $1.95 |
| 63 | White Epoxy Reflectorized Pavement Letters - 20 mil Portable/Hand Application (685.3304) | EACH | 212 | $125.00 | $180.00 | $86.00 | $81.12 | $170.00 | $125.00 |
| 64 | White Epoxy Reflectorized Pavement Symbols - 20 mil Portable/Hand Application (685.3404) | EACH | 105 | $150.00 | $200.00 | $215.00 | $202.80 | $210.00 | $150.00 |
| 65 | Field Change Payment (FCP) (697.03) | DOL | 750,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 66 | Asphalt Price Adjustment (698.04) | DOL | 27,904 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 67 | Fuel Price Adjustment (698.05) | DOL | 34,701 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 68 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 69 | Mobilization (699.040001) | LS | 1 | $700,000 | $750,000 | $900,000 | $915,000 | $987,411 | $999,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of February 26, 2026. Compiled by Mirage Metrics.