NYSDOT contract D265679 bid tabulation
PAVEMENT RESURFACING - Routes 133 & 100B. Let by New York State DOT on January 22, 2026, Westchester, Region 08. 6 bids received; low bid $7,722,105 by Morano Brothers Corp.
- Owner
- New York State DOT
- Letting
- 22 JAN 2026
- Pay items
- 83
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Morano Brothers Corp | $7,722,105 | Low |
| 2 | Petrillo Contracting Inc | $7,893,824 | +2.0% |
| 3 | Yonkers Contracting Company Inc | $8,311,556 | +8.0% |
| 4 | Grace Industries LLC | $8,338,500 | +8.0% |
| 5 | Elq Industries Inc | $9,297,303 | +20% |
| 6 | Montesano Bros Inc | $9,515,002 | +23% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Morano Brothers Corp | 2. Petrillo Contracting Inc | 3. Yonkers Contracting Company Inc | 4. Grace Industries LLC | 5. Elq Industries Inc | 6. Montesano Bros Inc |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.06) | LS | 1 | $22,000 | $48,000 | $15,000 | $42,100 | $20,000 | $225,000 |
| 2 | Unclassified Excavation and Disposal (203.02) | CY | 110 | $260.00 | $1,010.00 | $350.00 | $180.00 | $271.00 | $280.00 |
| 3 | Conduit Excavation and Backfill including Surface Restoration (206.03) | LF | 300 | $100.00 | $116.00 | $35.00 | $110.00 | $119.00 | $175.00 |
| 4 | Test Pit Excavation (206.05) | EACH | 4 | $1,500.00 | $3,000.00 | $1,500.00 | $2,200.00 | $3,175.00 | $2,000.00 |
| 5 | (304.11000008) | 1,100 | $170.00 | $100.00 | $55.00 | $240.00 | $228.00 | $160.00 | |
| 6 | Pavement Density Quality Adjustment to Asphalt Items (404.0002) | QUALITY UNIT | 1 | $140.00 | $140.00 | $140.00 | $140.00 | $140.00 | $140.00 |
| 7 | Longitudinal Joint Density Quality Adjustment to Asphalt Items (404.0003) | QUALITY UNIT | 650 | $140.00 | $140.00 | $140.00 | $140.00 | $140.00 | $140.00 |
| 8 | (406.0179) | TON | 390 | $200.00 | $220.00 | $160.00 | $230.00 | $190.00 | $125.00 |
| 9 | (406.1261) | TON | 10,000 | $170.00 | $206.00 | $160.00 | $210.00 | $183.30 | $167.00 |
| 10 | (406.2569) | TON | 2,600 | $175.00 | $220.00 | $160.00 | $210.00 | $196.00 | $175.00 |
| 11 | Straight Tack Coat (407.0103) | GAL | 4,300 | $13.00 | $15.00 | $9.00 | $5.50 | $13.10 | $12.50 |
| 12 | (407.01120007) | 190 | $13.00 | $24.00 | $50.00 | $5.50 | $14.90 | $7.50 | |
| 13 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 52,250 | $1.55 | $2.00 | $1.00 | $0.25 | $1.05 | $3.35 |
| 14 | Production Cold-Mill Surface Planing of Bituminous Concrete (490.15) | SY | 76,970 | $8.65 | $11.00 | $10.00 | $9.50 | $9.80 | $10.90 |
| 15 | PCC Foundation for Pavement, PEM Concrete (503.1013) | CY | 40 | $1,000.00 | $1,200.00 | $300.00 | $1,270.00 | $483.00 | $385.00 |
| 16 | (604.070801) | EACH | 15 | $1,800.00 | $3,000.00 | $8,000.00 | $2,170.00 | $3,000.00 | $2,200.00 |
| 17 | (604.07290010) | 1,060 | $57.00 | $30.00 | $125.00 | $100.00 | $75.00 | $105.00 | |
| 18 | (608.01050405) | 2,750 | $46.00 | $36.00 | $65.00 | $38.00 | $39.00 | $25.00 | |
| 19 | (608.02010015) | 150 | $156.00 | $200.00 | $500.00 | $180.00 | $340.00 | $280.00 | |
| 20 | (608.02020015) | 65 | $180.00 | $134.00 | $75.00 | $230.00 | $447.00 | $190.00 | |
| 21 | (608.21000003) | 6 | $430.00 | $700.00 | $600.00 | $1,260.00 | $342.00 | $250.00 | |
| 22 | (609.0401) | LF | 1,300 | $88.00 | $94.00 | $65.00 | $120.00 | $57.00 | $117.00 |
| 23 | Turf Establishment – Performance (610.1605) | SY | 1,700 | $3.00 | $20.00 | $12.00 | $19.00 | $20.00 | $19.00 |
| 24 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $590,000 | $500,000 | $804,001 | $514,199 | $1,808,244 | $1,775,000 |
| 25 | (619.0901) | LF | 77,000 | $0.50 | $1.00 | $0.40 | $0.50 | $0.42 | $0.43 |
| 26 | (619.110513) | EACH | 4 | $20,000 | $20,000 | $10,000 | $12,400 | $21,900 | $25,600 |
| 27 | Maintain Traffic Signal Equipment (Requirement B) Intersection (619.1612) | MONTH | 3 | $270.00 | $300.00 | $250.00 | $310.00 | $272.00 | $275.00 |
| 28 | Nighttime Operations (Entire Project) (619.24) | LS | 1 | $455,000 | $300,000 | $100,000 | $189,000 | $358,000 | $325,000 |
| 29 | Traffic Control Supervisor (619.25) | MONTH | 8 | $32,000 | $15,000 | $30,000 | $28,400 | $30,000 | $48,000 |
| 30 | Stone Filling (Light) (620.03) | CY | 35 | $230.00 | $250.00 | $575.00 | $270.00 | $194.00 | $375.00 |
| 31 | Cleaning Culverts with Span of 50 in. or Less (621.01) | LF | 1,100 | $20.00 | $20.00 | $30.00 | $19.00 | $23.40 | $27.00 |
| 32 | Cleaning Closed Drainage Systems (621.03) | LF | 560 | $23.00 | $30.00 | $10.00 | $23.00 | $25.00 | $29.00 |
| 33 | Cleaning Drainage Structures (621.04) | EACH | 120 | $790.00 | $700.00 | $600.00 | $820.00 | $892.00 | $1,150.00 |
| 34 | Clean, Grade and Shape Existing Roadside Section (621.05) | LF | 2,250 | $4.20 | $10.00 | $12.00 | $10.00 | $7.10 | $15.45 |
| 35 | Asphalt Gutter (624.020101) | TON | 1,500 | $453.00 | $260.00 | $475.00 | $650.00 | $448.00 | $525.00 |
| 36 | Plant Production Quality Adjustment to 624.020101 (624.020110) | QUALITY UNIT | 75 | $140.00 | $140.00 | $140.00 | $140.00 | $140.00 | $140.00 |
| 37 | Survey Operations (625.01) | LS | 1 | $45,000 | $108,000 | $40,000 | $25,000 | $100,000 | $60,000 |
| 38 | (627.50140008) | 16,050 | $5.00 | $6.00 | $9.00 | $6.00 | $6.00 | $4.50 | |
| 39 | (633.05040008) | LS | 1 | $130,000 | $40,000 | $752,000 | $124,000 | $130,000 | $280,000 |
| 40 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $8,300.00 | $5,000.00 | $3,000.00 | $3,470.00 | $7,000.00 | $5,400.00 |
| 41 | Engineer’s Field Office – Type 3 (637.13) | MONTH | 8 | $6,100.00 | $10,000 | $19,000 | $6,380.00 | $5,572.00 | $4,500.00 |
| 42 | Office Technology and Supplies (637.34) | DOL | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 43 | (637.41000115) | 8 | $450.00 | $1,500.00 | $200.00 | $700.00 | $185.00 | $378.00 | |
| 44 | Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102) | SF | 250 | $190.00 | $80.00 | $55.00 | $76.00 | $56.00 | $55.00 |
| 45 | Type A Sign Posts (645.81) | EACH | 50 | $280.00 | $200.00 | $355.00 | $440.00 | $382.00 | $375.00 |
| 46 | Reference Marker Panel (646.21) | EACH | 40 | $65.00 | $70.00 | $57.00 | $120.00 | $62.00 | $60.00 |
| 47 | Steel Post, 2.0 lb/ft (646.32) | EACH | 40 | $65.00 | $70.00 | $152.00 | $190.00 | $165.00 | $160.00 |
| 48 | Remove and Store Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.41) | EACH | 1 | $55.00 | $60.00 | $155.00 | $640.00 | $169.00 | $165.00 |
| 49 | Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61) | EACH | 45 | $55.00 | $60.00 | $73.00 | $250.00 | $79.00 | $70.00 |
| 50 | (647.83001002) | 33 | $55.00 | $60.00 | $33.00 | $64.00 | $36.00 | $30.00 | |
| 51 | Cast Frame F3, UnMountable Curb Box CU3 & Reticuline Grate G3 (655.0706) | EACH | 10 | $3,500.00 | $1,500.00 | $3,600.00 | $1,920.00 | $3,043.00 | $1,900.00 |
| 52 | Welded Frame & Reticuline Grate 22 (655.1122) | EACH | 8 | $3,500.00 | $1,000.00 | $3,200.00 | $1,000.00 | $2,615.00 | $1,290.00 |
| 53 | (660.65000101) | 15 | $2,000.00 | $1,200.00 | $3,500.00 | $2,170.00 | $1,816.00 | $570.00 | |
| 54 | (662.60030008) | 10 | $320.00 | $500.00 | $275.00 | $95.00 | $566.00 | $18.00 | |
| 55 | Adjust Existing Valve Box Elevation (663.33) | EACH | 15 | $110.00 | $500.00 | $200.00 | $95.00 | $570.00 | $113.00 |
| 56 | (670.31031011) | 3 | $610.00 | $1,000.00 | $550.00 | $950.00 | $2,100.00 | $130.00 | |
| 57 | (680.05010007) | 1 | $30,000 | $27,000 | $26,400 | $33,400 | $28,655 | $29,000 | |
| 58 | (680.05020007) | 1 | $5,000.00 | $4,500.00 | $4,500.00 | $5,690.00 | $4,884.00 | $4,975.00 | |
| 59 | Pole Excavation and Concrete Foundation (680.5001) | CY | 6 | $4,400.00 | $9,000.00 | $3,950.00 | $5,000.00 | $4,287.00 | $4,367.00 |
| 60 | (680.510501) | EACH | 4 | $2,400.00 | $6,000.00 | $2,150.00 | $2,730.00 | $2,334.00 | $2,375.00 |
| 61 | (680.520106) | LF | 50 | $45.00 | $40.00 | $40.00 | $51.00 | $43.40 | $45.00 |
| 62 | (680.520108) | LF | 250 | $72.00 | $65.00 | $65.00 | $83.00 | $70.50 | $71.00 |
| 63 | (680.6808) | EACH | 4 | $2,200.00 | $2,000.00 | $2,000.00 | $2,530.00 | $2,170.00 | $2,200.00 |
| 64 | (680.730214) | LF | 660 | $6.00 | $6.00 | $5.50 | $7.00 | $6.00 | $6.00 |
| 65 | (680.730514) | LF | 660 | $7.00 | $7.14 | $6.25 | $7.50 | $7.00 | $6.90 |
| 66 | (680.77030008) | 1 | $2,200.00 | $2,000.00 | $1,975.00 | $2,500.00 | $2,144.00 | $2,180.00 | |
| 67 | Pedestrian Signal Section - Aluminum Type I, 12 inch (680.813103) | EACH | 8 | $510.00 | $500.00 | $460.00 | $590.00 | $499.00 | $500.00 |
| 68 | Pedestrian Signal Module - 12-inch, Bi-Modal Hand/Man Symbols, LED (680.813105) | EACH | 4 | $490.00 | $500.00 | $440.00 | $560.00 | $477.00 | $485.00 |
| 69 | Pedestrian Signal Bracket Mount Assembly (680.8141) | EACH | 4 | $610.00 | $600.00 | $550.00 | $710.00 | $597.00 | $600.00 |
| 70 | Pedestrian Signal Module - 12-inch Countdown Timer, LED (680.815001) | EACH | 4 | $490.00 | $500.00 | $440.00 | $560.00 | $477.00 | $580.00 |
| 71 | (680.8151) | EACH | 4 | $2,200.00 | $2,000.00 | $1,985.00 | $2,510.00 | $2,154.00 | $2,190.00 |
| 72 | Breakaway Transformer Base (680.8223) | EACH | 4 | $1,200.00 | $6,000.00 | $1,050.00 | $1,330.00 | $1,140.00 | $1,160.00 |
| 73 | Performance Concrete Quality Adjustment (680.99) | QUALITY UNIT | 1 | $17.50 | $17.50 | $17.50 | $17.50 | $17.50 | $17.50 |
| 74 | White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102) | LF | 9,000 | $2.60 | $3.00 | $2.35 | $3.00 | $2.55 | $2.57 |
| 75 | (685.16010014) | 38,000 | $1.30 | $1.50 | $1.20 | $1.50 | $1.30 | $1.33 | |
| 76 | (685.17010014) | 40,000 | $1.30 | $1.50 | $1.20 | $1.50 | $1.30 | $1.33 | |
| 77 | White Epoxy Reflectorized Pavement Letters - 20 mil Portable/Hand Application (685.3304) | EACH | 8 | $150.00 | $160.00 | $135.00 | $170.00 | $146.00 | $149.00 |
| 78 | White Epoxy Reflectorized Pavement Symbols - 20 mil Portable/Hand Application (685.3404) | EACH | 7 | $170.00 | $180.00 | $155.00 | $190.00 | $168.00 | $170.00 |
| 79 | Field Change Payment (FCP) (697.03) | DOL | 600,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 80 | Asphalt Price Adjustment (698.04) | DOL | 9,562 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 81 | Fuel Price Adjustment (698.05) | DOL | 2,212 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 82 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 83 | Mobilization (699.040001) | LS | 1 | $285,000 | $303,000 | $300,000 | $320,000 | $351,500 | $148,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of January 22, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.