Cobleskill Stone Products Inc.: NYSDOT bid record

Cobleskill Stone Products Inc. submitted 21 bids on New York State DOT contracts in the data, from 06 JAN 2022 to 25 JUN 2026, and was the low bidder on 11 of them (52%). When it was not low, its total sat a median +27% above the low bid.

Owner
New York State DOT
Low bid volume
$66,207,422
Latest bid
25 JUN 2026
Data through
15 OCT 2026
21Bids
11Low bids
52Win rate, percent
+27%Median gap to the low bid when not low, 10 bids

By year

YearBidsLow bidsWin rate
20228450%
2023200%
20243267%
20253133%
20265480%
Cobleskill Stone Products Inc., NYSDOT: bids and low bids by year of letting

By region

RegionBidsLow bidsWin rate
Region 09141179%
Region 02700%
Cobleskill Stone Products Inc., NYSDOT: bids and low bids by region

Pay items where it is most often lowest

Pay itemCodeUnitLines bidLowest on the lineIts median priceAll bidders' median
Field Change Payment (FCP)697.03DOL1515 (100%)$1.00$1.00
Fuel Price Adjustment698.05DOL1515 (100%)$1.00$1.00
Steel/Iron Price Adjustment698.06DOL1515 (100%)$1.00$1.00
Asphalt Price Adjustment698.04DOL1515 (100%)$1.00$1.00
Office Technology and Supplies637.34DOL1414 (100%)$1.00$1.00
Engineer’s Field Office – Type 2637.12MONTH106 (60%)$2,600.00$2,500.00
Stone Filling (Light)620.03CY96 (67%)$90.00$163.00
691.0400002066 (100%)$1.00$1.00
Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips608.000013QUALITY UNIT66 (100%)$77.50$90.00
Asphalt Pavement Joint Adhesive418.7603LF155 (33%)$0.55$1.00
404.0001TON55 (100%)$90.00$95.00
Unclassified Excavation and Disposal203.02CY144 (29%)$33.00$71.00
Cobleskill Stone Products Inc., NYSDOT: pay items where its unit price was the lowest on the line

A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.

Who it meets most

FirmContracts in commonThat firm ranked ahead
Lancaster Development and Tully Construction Co LLC82 of 8
Bothar Construction LLC64 of 6
Heidelberg Materials Northeast-Ny LLC42 of 4
Cci Companies Inc21 of 2
Rifenburg Construction Inc21 of 2
Callanan Industries Inc21 of 2
Hanson Aggregates New York LLC22 of 2
Dolomite Products Co Inc/DBA A L Blades21 of 2
Maple Ridge Organics LLC20 of 2
Marcy Excavation Services LLC11 of 1
Cobleskill Stone Products Inc., NYSDOT: the firms on the same contracts most often

Latest bids

LetContractRegionProjectRankIts bidAgainst the low bid
25 JUN 2026D265805Region 02ROUTE 5S & 30A MONTGOMERY COUNTY PAVING REHABILITATION3 of 4$5,437,579+9.0%
26 MAR 2026D265744Region 09PAVEMENT MAINTENANCE - Various Locations.1 of 2$14,995,417Low, 26% under the second
05 FEB 2026D265667Region 09JOC Highway/Drainage Combined, Chenango and Otsego Counties1 of 3$852,238Low, 26% under the second
05 FEB 2026D265668Region 09JOC Highway/Drainage Combined, Delaware and Schoharie.1 of 2$852,652Low, 38% under the second
05 FEB 2026D265670Region 09JOC Highway/Drainage Combined, Sullivan County1 of 1$463,994Low
18 DEC 2025D265618Region 02RESURFACING PAVEMENT PROJECT - Rte 5, TOWN OF PALATINE2 of 2$1,692,473+20%
27 MAR 2025D265446Region 09I88 RESURFACING AND JOINT REPAIRS1 of 3$13,266,234Low, 9.0% under the second
27 FEB 2025D265417Region 02PAVEMENT REHABILITATION - Rt 67: Rt. 5 to Rt. 102 of 2$6,053,465+22%
08 AUG 2024D265289Region 09I88 - REST AREA TRUCK PARKING EXPANSION1 of 3$2,311,619Low, 5.0% under the second
23 MAY 2024D265260Region 02ROUTES 5S AND 920T PAVEMENT REHABILITATION PROJECT3 of 3$1,498,247+51%
08 FEB 2024D265154Region 09I-88 Crack and Seat, Exit 18 to 19, Otsego County1 of 3$21,767,702Low, 13% under the second
30 NOV 2023D265131Region 02CULVERT REPAIR/REPLACEMENT PROJECT HERKIMER COUNTY7 of 9$1,242,839+27%
19 JAN 2023D264940Region 02Route 5S Corridor Improvements4 of 4$7,868,601+28%
15 DEC 2022D264811Region 099ADA20 - ADA ACCESSIBILITY PROJECT2 of 3$3,088,489+27%
20 OCT 2022D264868Region 09RT 97 SLOPE STABILIZATION4 of 4$5,562,384+69%
19 MAY 2022D264780Region 09JOC- FOR HIGHWAY & DRAINAGE WORK IN PART OF NYSDOT REGION 91 of 1$909,640Low
21 APR 2022D264783Region 09Sullivan, JOC - HIGHWAY/DRAINAGE COMBINED, Various Locations1 of 1$475,135Low
07 APR 2022D264777Region 09JOC - HIGHWAY/DRAINAGE COMBINED1 of 1$790,991Low
24 MAR 2022D264744Region 02ROUTE 162 PAVEMENT REHABILATION:2 of 4$10,999,644+4.0%
03 FEB 2022D264718Region 09MILLING AND RESURFACING I-88, Near exit 231 of 3$9,521,801Low, 14% under the second
06 JAN 2022D264693Region 09ROUTE 28, SHOULDER WIDENING And Safety Improvements5 of 5$3,263,442+37%
Cobleskill Stone Products Inc.: latest NYSDOT bids in the data

How this record was read

NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.

  • Every bid counted here matched its published total to within one dollar; NYSDOT's rank decides who was low.
  • The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
  • A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.

A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy