NYSDOT contract D265446 bid tabulation

I88 RESURFACING AND JOINT REPAIRS. Let by New York State DOT on March 27, 2025, Schoharie, Region 09. 3 bids received; low bid $13,266,234 by Cobleskill Stone Products Inc..

Owner
New York State DOT
Letting
27 MAR 2025
Pay items
77
Data through
15 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Cobleskill Stone Products Inc.$13,266,234Low
2Heidelberg Materials Northeast-Ny LLC$14,489,851+9.0%
3Lancaster Development and Tully Construction Co LLC$16,451,125+24%
NYSDOT contract D265446: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Cobleskill Stone Products Inc.2. Heidelberg Materials Northeast-Ny LLC3. Lancaster Development and Tully Construction Co LLC
1Unclassified Excavation and Disposal (203.02)CY2,909$21.00$53.00$80.70
2 (203.24010017)5,835$29.75$34.00$10.00
3Conduit Excavation and Backfill including Surface Restoration (206.03)LF150$46.25$37.23$35.50
4 (304.00010018)67,345$0.45$0.41$0.92
5Subbase Course, Optional Type (304.15)CY247$67.45$63.00$85.40
6 (404.0001)TON2,349.39$90.00$90.00$90.00
7Pavement Density Quality Adjustment to Asphalt Items (404.0002)QUALITY UNIT1,784.93$90.00$90.00$90.00
8Longitudinal Joint Density Quality Adjustment to Asphalt Items (404.0003)QUALITY UNIT440$90.00$90.00$90.00
9 (404.0589)TON10,542$77.00$100.00$125.00
10 (404.1989)TON1,263$92.65$132.00$164.00
11 (404.2589)TON2,101$98.95$116.00$131.00
12 (406.1252)TON35,699$85.00$96.50$100.00
13 (407.01040009)61,217$4.30$2.95$1.00
14Asphalt Pavement Joint Adhesive (418.7603)LF330,488$0.55$0.30$0.01
15 (490.17011018)19,293$3.35$2.85$5.00
16Box Beam Guide Railing (606.10)LF21,118$43.30$40.25$48.50
17Box Beam Median Barrier (606.11)LF16,509$63.00$59.75$70.70
18Box Beam End Piece (606.120101)EACH9$755.00$700.00$846.00
19Box Beam Guide Railing End Assembly Type I (606.120102)EACH1$5,175.00$4,500.00$6,000.00
20Box Beam Guide Railing End Assembly Type I with 18 ft Extension (606.120103)EACH11$5,775.00$5,100.00$5,500.00
21Box Beam Median Barrier End Assembly, Type C (606.1403)EACH7$9,050.00$7,850.00$9,890.00
22Resetting Box Beam Median Barrier (New Posts) (606.5448)LF1,474$39.00$35.00$41.40
23Removing and Disposing Cable Guide Railing (606.70)LF20,813$2.90$2.75$3.25
24Removing and Disposing Box Beam Guide Railing (606.73)LF3,231$3.15$3.00$3.55
25Removing and Disposing Anchorage Units for Cable Guide railing or Median Barrier (606.79)EACH34$530.00$500.00$592.00
26Removing and Disposing Box Beam Guide Rail Turned-Down Terminal (606.7920)EACH23$158.00$150.00$178.00
27 (606.85020001)12$790.00$700.00$888.00
28Concrete Sidewalks and Driveways (608.0101)CY1$2,500.00$2,150.00$6,400.00
29Basic Work Zone Traffic Control (619.01)LS1$163,000$700,000$919,000
30 (619.0901)LF150,696$0.32$0.30$0.36
31Maintain Traffic Signal Equipment (Requirement C) Intersection (619.1613)MONTH24$158.00$200.00$178.00
32Survey Operations (625.01)LS1$10,500$30,000$169,996
33 (625.09010015)LS1$1,000.00$2,500.00$8,690.00
34Stress Relieving Pavement Repairs (633.16)SY30,000$103.50$104.50$126.00
35Concrete Cylinder Curing Equipment (637.04)EACH1$2,500.00$2,000.00$3,820.00
36Engineer’s Field Office – Type 2 (637.12)MONTH24$2,300.00$3,000.00$7,010.00
37Office Technology and Supplies (637.34)DOL2,000$1.00$1.00$1.00
38 (637.41000115)24$65.50$105.00$118.00
39 (637.41000215)24$65.50$105.00$118.00
40Ground-Mounted Sign Panels without Z-bars (645.5101)SF14$42.50$40.00$47.70
41Type A Sign Posts (645.81)EACH2$211.00$200.00$10,000
42 (645.830701)EACH2$8,675.00$8,220.00$538.00
43Reference Marker Panel (646.21)EACH108$46.50$43.75$52.10
44Large Delineator, Large Snowplowing Marker, Large Supplementary Snowplowing Marker Panel (646.23)EACH857$31.65$29.00$35.50
45Steel Post, 2.0 lb/ft (646.32)EACH725$81.50$74.25$91.50
46Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61)EACH2$26.50$25.00$29.60
47 (647.83001002)693$13.75$13.00$15.40
48Milled-In Audible Roadway Delineators (MIARDs) (649.01)LF116,704$0.29$0.15$0.46
49Pavement Ride Quality Adjustment to Asphalt Level 2 (653.1020)QUALITY UNIT848$90.00$90.00$90.00
50 (662.60010004)1,500$1.00$1.00$1.00
51Pole Excavation and Concrete Foundation (680.5001)CY1.20$3,535.00$2,508.00$3,970.00
52 (680.510501)EACH3$1,525.00$2,118.00$1,710.00
53 (680.520106)LF250$16.35$16.02$18.40
54 (680.520204)LF60$15.85$9.73$17.80
55Conduit Jacking or Boring (680.53)LF150$52.75$98.00$59.20
56 (680.70070010)1$1,690.00$5,838.00$1,890.00
57 (680.77000001)LS1$2,325.00$2,160.00$2,600.00
58Breakaway Transformer Base (680.8223)EACH1$910.00$1,122.00$1,020.00
59 (680.90920008)1$885.00$602.00$994.00
60Watertight Disconnect Box (680.9401)EACH2$425.00$1,331.00$474.00
61Ground Wire (680.9403)LF400$2.65$2.61$2.95
62 (680.950106)LF400$4.85$3.46$5.45
63 (680.95110009)1$1,575.00$578.00$1,760.00
64Performance Concrete Quality Adjustment (680.99)QUALITY UNIT1$11.56$11.56$11.56
65 (683.06010013)1$6,125.00$7,141.00$6,870.00
66 (683.17002211)1$7,285.00$12,272$8,170.00
67 (683.93090104)2$67,000$88,158$75,200
68 (685.16010014)137,573$1.25$1.19$1.40
69 (685.17010014)108,762$1.25$1.19$1.40
70White Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3104)LF20,968$3.15$2.99$3.55
71White Epoxy Reflectorized Pavement Letters - 20 mil Portable/Hand Application (685.3304)EACH8$79.15$75.00$88.80
72 (691.04000020)105,000$1.00$1.00$1.00
73Field Change Payment (FCP) (697.03)DOL720,000$1.00$1.00$1.00
74Asphalt Price Adjustment (698.04)DOL124,277.08$1.00$1.00$1.00
75Fuel Price Adjustment (698.05)DOL25,414$1.00$1.00$1.00
76Steel/Iron Price Adjustment (698.06)DOL100$1.00$1.00$1.00
77Mobilization (699.040001)LS1$475,270$550,000$631,214
NYSDOT contract D265446: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.

Every contract let that day: NYSDOT letting of March 27, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy