NYSDOT contract D265744 bid tabulation
PAVEMENT MAINTENANCE - Various Locations. Let by New York State DOT on March 26, 2026, Otsego, Region 09. 2 bids received; low bid $14,995,417 by Cobleskill Stone Products Inc..
- Owner
- New York State DOT
- Letting
- 26 MAR 2026
- Pay items
- 98
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Cobleskill Stone Products Inc. | $14,995,417 | Low |
| 2 | Lancaster Development and Tully Construction Co LLC | $18,860,612 | +26% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Cobleskill Stone Products Inc. | 2. Lancaster Development and Tully Construction Co LLC |
|---|---|---|---|---|---|
| 1 | Unclassified Excavation and Disposal (203.02) | CY | 1,591 | $40.00 | $59.60 |
| 2 | Embankment In Place (203.03) | CY | 23 | $95.00 | $100.00 |
| 3 | (203.24010017) | 2,441 | $34.00 | $40.00 | |
| 4 | Conduit Excavation and Backfill including Surface Restoration (206.03) | LF | 320 | $61.35 | $38.10 |
| 5 | Silt Fence - Temporary (209.13) | LF | 300 | $5.00 | $9.75 |
| 6 | (304.00010018) | 50,160 | $0.60 | $0.83 | |
| 7 | Subbase Course, Optional Type (304.15) | CY | 2 | $400.00 | $800.00 |
| 8 | Pavement Density Quality Adjustment to Asphalt Items (404.0002) | QUALITY UNIT | 2,096.30 | $90.00 | $90.00 |
| 9 | Longitudinal Joint Density Quality Adjustment to Asphalt Items (404.0003) | QUALITY UNIT | 675 | $90.00 | $90.00 |
| 10 | (404.0589) | TON | 15,326 | $98.30 | $141.00 |
| 11 | (404.1989) | TON | 941 | $108.55 | $218.00 |
| 12 | (404.2589) | TON | 1,568 | $104.60 | $162.00 |
| 13 | (407.01040009) | 37,552 | $5.25 | $6.20 | |
| 14 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 193,884 | $0.25 | $0.25 |
| 15 | (421.09520109) | 33,009 | $116.60 | $160.00 | |
| 16 | (490.17011018) | 38,116 | $4.50 | $3.00 | |
| 17 | Miscellaneous Cold Milling of Bituminous Concrete (490.30) | SY | 5,573 | $11.45 | $4.00 |
| 18 | (602.3624) | LF | 261 | $230.00 | $234.00 |
| 19 | (602.3630) | LF | 422 | $240.00 | $283.00 |
| 20 | (602.3636) | LF | 120 | $400.00 | $438.00 |
| 21 | (602.3642) | LF | 141 | $480.00 | $478.00 |
| 22 | (603.171614) | EACH | 4 | $305.00 | $900.00 |
| 23 | (603.171814) | EACH | 4 | $455.00 | $1,000.00 |
| 24 | (603.171912) | EACH | 1 | $800.00 | $2,500.00 |
| 25 | (603.172012) | EACH | 1 | $2,000.00 | $3,000.00 |
| 26 | Box Beam Guide Railing (606.10) | LF | 18,183 | $47.60 | $50.90 |
| 27 | Box Beam Guide Railing (Shop Bent or Shop Mitered) (606.100002) | LF | 324 | $61.35 | $65.60 |
| 28 | Box Beam Median Barrier (606.11) | LF | 2,378 | $63.45 | $67.90 |
| 29 | Box Beam End Piece (606.120101) | EACH | 21 | $900.00 | $961.00 |
| 30 | Box Beam Guide Railing End Assembly Type I (606.120102) | EACH | 17 | $4,335.00 | $4,640.00 |
| 31 | Box Beam Guide Railing End Assembly Type I with 18 ft Extension (606.120103) | EACH | 1 | $5,140.00 | $5,500.00 |
| 32 | Box Beam Median Barrier End Assembly, Type C (606.1403) | EACH | 1 | $11,630 | $12,400 |
| 33 | Resetting Box Beam Guide Railing (606.53) | LF | 1,620 | $29.70 | $22.60 |
| 34 | Resetting Box Beam Guide Rail Turned-Down Terminal (606.5920) | EACH | 3 | $455.00 | $486.00 |
| 35 | Removing and Disposing Cable Guide Railing (606.70) | LF | 12,977 | $2.00 | $5.15 |
| 36 | Removing and Disposing Corrugated Beam Guide Railing (606.71) | LF | 1,525 | $4.00 | $7.05 |
| 37 | Removing and Disposing Box Beam Guide Railing (606.73) | LF | 4,026 | $5.00 | $6.65 |
| 38 | Removing and Disposing Anchorage Units for Cable Guide railing or Median Barrier (606.79) | EACH | 32 | $800.00 | $837.00 |
| 39 | Removing and Disposing Anchorage Units for Corrugated Beam Guide Railing and Median Barrier (606.7910) | EACH | 4 | $800.00 | $837.00 |
| 40 | Removing and Disposing Box Beam Guide Rail Turned-Down Terminal (606.7920) | EACH | 7 | $215.00 | $478.00 |
| 41 | (607.62000010) | 2,000 | $8.00 | $6.45 | |
| 42 | Concrete Sidewalks and Driveways (608.0101) | CY | 3 | $3,525.00 | $5,420.00 |
| 43 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $653,400 | $932,000 |
| 44 | (619.0901) | LF | 430,097 | $0.32 | $0.34 |
| 45 | (619.111112) | EACH | 4 | $9,000.00 | $26,600 |
| 46 | (621.05020004) | 11,280 | $3.85 | $3.00 | |
| 47 | (621.51970008) | 180 | $31.65 | $41.00 | |
| 48 | Survey Operations (625.01) | LS | 1 | $15,000 | $85,686 |
| 49 | Cleaning Existing Pavement and/or Shoulder (633.11) | SY | 235,631 | $0.09 | $0.12 |
| 50 | Stress Relieving Pavement Repairs (633.16) | SY | 27,881 | $113.15 | $140.00 |
| 51 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $2,650.00 | $3,640.00 |
| 52 | Engineer’s Field Office – Type 2 (637.12) | MONTH | 24 | $2,350.00 | $5,300.00 |
| 53 | Office Technology and Supplies (637.34) | DOL | 45,000 | $1.00 | $1.00 |
| 54 | (637.41000115) | 24 | $75.00 | $100.00 | |
| 55 | (637.41000215) | 24 | $75.00 | $100.00 | |
| 56 | Ground-Mounted Sign Panels without Z-bars (645.5101) | SF | 54 | $63.50 | $67.90 |
| 57 | Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102) | SF | 122 | $42.30 | $45.20 |
| 58 | Ground-Mounted Sign Panels greater than 32 SF with Z-bars (645.5103) | SF | 315 | $38.00 | $40.70 |
| 59 | Type A Sign Posts (645.81) | EACH | 55 | $227.00 | $243.00 |
| 60 | (645.830701) | EACH | 6 | $7,720.00 | $8,260.00 |
| 61 | Reference Marker Panel (646.21) | EACH | 90 | $33.85 | $36.20 |
| 62 | Large Delineator, Large Snowplowing Marker, Large Supplementary Snowplowing Marker Panel (646.23) | EACH | 654 | $18.00 | $19.20 |
| 63 | Steel Post, 2.0 lb/ft (646.32) | EACH | 666 | $69.80 | $74.60 |
| 64 | Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61) | EACH | 18 | $90.00 | $96.10 |
| 65 | Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size III (Over 100 Square Feet) (647.63) | EACH | 2 | $180.00 | $192.00 |
| 66 | (647.83001002) | 506 | $9.50 | $18.20 | |
| 67 | Milled-In Audible Roadway Delineators (MIARDs) (649.01) | LF | 95,934 | $0.46 | $0.26 |
| 68 | Pole Excavation and Concrete Foundation (680.5001) | CY | 2 | $1,900.00 | $11,200 |
| 69 | (680.510501) | EACH | 3 | $1,955.00 | $2,890.00 |
| 70 | (680.520106) | LF | 350 | $31.70 | $21.00 |
| 71 | (680.520204) | LF | 60 | $38.00 | $14.10 |
| 72 | Trenchless Installation Method for Conduit (680.5301) | LF | 220 | $110.00 | $121.00 |
| 73 | (680.70070010) | 1 | $6,660.00 | $4,800.00 | |
| 74 | (680.77000001) | LS | 1 | $3,500.00 | $1,530.00 |
| 75 | Breakaway Transformer Base (680.8223) | EACH | 1 | $1,140.00 | $1,800.00 |
| 76 | (680.90920008) | 1 | $900.00 | $2,160.00 | |
| 77 | Watertight Disconnect Box (680.9401) | EACH | 2 | $740.00 | $1,330.00 |
| 78 | Ground Wire (680.9403) | LF | 400 | $6.35 | $3.10 |
| 79 | (680.950106) | LF | 400 | $7.40 | $4.65 |
| 80 | (680.95110009) | 1 | $2,750.00 | $1,620.00 | |
| 81 | Performance Concrete Quality Adjustment (680.99) | QUALITY UNIT | 1 | $12.92 | $12.92 |
| 82 | (683.06010013) | 1 | $7,600.00 | $8,000.00 | |
| 83 | (683.17003011) | 1 | $7,500.00 | $15,400 | |
| 84 | (683.93090104) | 2 | $70,735 | $70,600 | |
| 85 | (685.07200910) | 33 | $52.00 | $56.60 | |
| 86 | White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102) | LF | 7,125 | $0.95 | $1.00 |
| 87 | Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202) | LF | 3,075 | $0.95 | $1.00 |
| 88 | (685.16010014) | 151,974 | $1.37 | $1.45 | |
| 89 | (685.17010014) | 99,502 | $1.37 | $1.45 | |
| 90 | White Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3104) | LF | 21,360 | $2.95 | $3.15 |
| 91 | White Epoxy Reflectorized Pavement Letters - 20 mil Portable/Hand Application (685.3304) | EACH | 8 | $79.30 | $84.80 |
| 92 | White Epoxy Reflectorized Pavement Symbols - 20 mil Portable/Hand Application (685.3404) | EACH | 14 | $240.00 | $254.00 |
| 93 | (691.04000020) | 110,000 | $1.00 | $1.00 | |
| 94 | Field Change Payment (FCP) (697.03) | DOL | 1,103,413 | $1.00 | $1.00 |
| 95 | Asphalt Price Adjustment (698.04) | DOL | 46,886.90 | $1.00 | $1.00 |
| 96 | Fuel Price Adjustment (698.05) | DOL | 3,825 | $1.00 | $1.00 |
| 97 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 |
| 98 | Mobilization (699.040001) | LS | 1 | $576,390 | $723,664 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of March 26, 2026. Compiled by Mirage Metrics.