NYSDOT contract D265825 bid tabulation

Guide Rail Replacement SFY26. Let by New York State DOT on August 27, 2026, Washington, Region 01. 3 bids received; low bid $2,598,783 by Emi Guide Rail LLC.

Owner
New York State DOT
Letting
27 AUG 2026
Pay items
34
Data through
15 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Emi Guide Rail LLC$2,598,783Low
2Elderlee Inc$2,915,655+12%
3Road Safety Systems LLC$3,308,265+27%
NYSDOT contract D265825: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Emi Guide Rail LLC2. Elderlee Inc3. Road Safety Systems LLC
1Embankment In Place (203.03)CY1$95.00$185.00$872.00
2Select Granular Fill (203.07)CY5$100.00$48.00$191.00
3 (203.24010017)538$125.00$75.00$110.00
4Trench and Culvert Excavation (206.0201)CY5$45.00$35.00$1,470.00
5 (568.70020002)128$158.50$190.00$235.00
6 (603.171116)EACH1$245.00$110.00$2,500.00
7Concrete Collars (603.77)EACH1$2,250.00$2,840.00$3,000.00
8 (603.9812)LF14$105.00$75.00$163.00
9Box Beam Guide Railing (606.10)LF24,452$43.50$50.00$59.00
10Box Beam Guide Railing (Shop Bent or Shop Mitered) (606.100002)LF1,061$48.00$60.00$65.00
11Box Beam Guide Railing With Extra Long Posts (606.1001)LF4,985$48.25$53.00$66.00
12Box Beam Guide Railing End Assembly Type I (606.120102)EACH38$4,150.00$4,600.00$4,500.00
13Box Beam Guide Railing End Assembly Type I with 18 ft Extension (606.120103)EACH1$5,300.00$5,500.00$5,800.00
14Box Beam Guide Railing End Assembly Type IIA (606.120201)EACH122$2,025.00$2,400.00$2,600.00
15Box Beam End Assembly Type III (606.1203)EACH4$6,350.00$6,200.00$6,800.00
16Removing and Disposing Cable Guide Railing (606.70)LF8,361$2.25$2.00$3.00
17Removing and Disposing Corrugated Beam Guide Railing (606.71)LF19,315$3.00$2.00$4.00
18Removing and Disposing Box Beam Guide Railing (606.73)LF2,322$4.50$4.00$5.00
19Removing and Disposing Anchorage Units for Cable Guide railing or Median Barrier (606.79)EACH46$400.00$250.00$375.00
20Removing and Disposing Anchorage Units for Corrugated Beam Guide Railing and Median Barrier (606.7910)EACH110$400.00$250.00$375.00
21Removing and Disposing Box Beam Guide Rail Turned-Down Terminal (606.7920)EACH14$150.00$85.00$100.00
22Turf Establishment – Performance (610.1605)SY8,154$6.00$10.00$9.00
23Basic Work Zone Traffic Control (619.01)LS1$185,000$242,000$225,000
24 (619.111213)WEEK20$675.00$1,700.00$700.00
25Mailboxes (619.27)EACH19$205.00$215.00$475.00
26Engineer’s Field Office – Type 2 (637.12)MONTH14$2,625.00$3,200.00$3,600.00
27Office Technology and Supplies (637.34)DOL2,000$1.00$1.00$1.00
28Large Delineator, Large Snowplowing Marker, Large Supplementary Snowplowing Marker Panel (646.23)EACH229$18.50$20.00$32.00
29Steel Post, 2.0 lb/ft (646.32)EACH229$73.50$65.00$87.50
30Field Change Payment (FCP) (697.03)DOL153,000$1.00$1.00$1.00
31Asphalt Price Adjustment (698.04)DOL100$1.00$1.00$1.00
32Fuel Price Adjustment (698.05)DOL100$1.00$1.00$1.00
33Steel/Iron Price Adjustment (698.06)DOL100$1.00$1.00$1.00
34Mobilization (699.040001)LS1$99,750$112,000$111,873
NYSDOT contract D265825: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.

Every contract let that day: NYSDOT letting of August 27, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy