NYSDOT contract D265488 bid tabulation
Standby Where & When General Repairs on Highways and Bridges. Let by New York State DOT on July 24, 2025, Bronx, Kings, New York, Queens,, Region 11. 7 bids received; low bid $18,510,478 by Westmoreland Construction Inc.
- Owner
- New York State DOT
- Letting
- 24 JUL 2025
- Pay items
- 8
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Westmoreland Construction Inc | $18,510,478 | Low |
| 2 | Jrcruz Corp | $20,976,301 | +13% |
| 3 | Bove Industries Inc | $21,585,000 | +17% |
| 4 | Triumph Construction Corp | $22,890,540 | +24% |
| 5 | Constar Inc | $24,183,558 | +31% |
| 6 | Defoe Corporation | $24,245,530 | +31% |
| 7 | Paul J Scariano Inc | $29,698,913 | +60% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Westmoreland Construction Inc | 2. Jrcruz Corp | 3. Bove Industries Inc | 4. Triumph Construction Corp | 5. Constar Inc | 6. Defoe Corporation |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Standby Readiness (636.01) | LS | 1 | $800,000 | $800,000 | $700,091 | $800,000 | $800,000 | $800,000 |
| 2 | Response Work (636.02) | DOLLAR-CENTS | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 3 | Labor with Cost Factor (636.03) | PERCENT | 12,257,310 | $1.08 | $1.20 | $1.30 | $1.16 | $1.50 | $1.48 |
| 4 | Materials with Cost Factor (636.04) | PERCENT | 2,828,610 | $1.04 | $1.05 | $1.05 | $1.00 | $1.10 | $1.10 |
| 5 | Equipment with Cost Factor (636.05) | PERCENT | 3,771,480 | $0.29 | $0.60 | $0.45 | $1.25 | $0.42 | $0.50 |
| 6 | Engineer’s Field Office – Type 5 (637.15) | MONTH | 27 | $15,000 | $7,500.00 | $9,500.00 | $11,000 | $10,000 | $10,200 |
| 7 | (637.31020020) | 27 | $1,000.00 | $1,000.00 | $800.00 | $1,000.00 | $1,000.00 | $1,000.00 | |
| 8 | Office Technology and Supplies (637.34) | DOL | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of July 24, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.