NYSDOT contract D265833 bid tabulation
Curve Warning Sign Upgrades Various Highways and Roadways. Let by New York State DOT on August 27, 2026, Nassau, Suffolk, Region 10. 4 bids received; low bid $3,592,264 by United Fence and Guard Rail Corp.
- Owner
- New York State DOT
- Letting
- 27 AUG 2026
- Pay items
- 58
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | United Fence and Guard Rail Corp | $3,592,264 | Low |
| 2 | Westmoreland Construction Inc | $4,404,203 | +23% |
| 3 | Constar Inc | $4,881,080 | +36% |
| 4 | Road Safety Systems LLC | $5,459,729 | +52% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. United Fence and Guard Rail Corp | 2. Westmoreland Construction Inc | 3. Constar Inc | 4. Road Safety Systems LLC |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.07) | ACRE | 1 | $10,000 | $10,000 | $200,000 | $5,500.00 |
| 2 | Unclassified Excavation and Disposal (203.02) | CY | 73 | $25.00 | $125.00 | $100.00 | $180.00 |
| 3 | Test Pit Excavation (206.05) | EACH | 1 | $1,000.00 | $2,500.00 | $2,500.00 | $1,500.00 |
| 4 | (607.41010010) | 773 | $10.00 | $10.00 | $15.00 | $9.00 | |
| 5 | Mycorrhizal Fungi (610.0701) | LB | 136 | $27.00 | $30.00 | $30.00 | $72.00 |
| 6 | Moisture Retention Additive (610.08) | LB | 136 | $27.00 | $30.00 | $40.00 | $98.00 |
| 7 | Mulch for Planting Type A, B & D Wood Chips and Shredded Bark (610.1101) | CY | 20 | $80.00 | $95.00 | $150.00 | $150.00 |
| 8 | Topsoil - Roadside (610.1402) | CY | 73 | $150.00 | $160.00 | $140.00 | $70.00 |
| 9 | Turf Establishment - Roadside (610.1601) | SY | 217 | $10.00 | $15.00 | $15.00 | $6.50 |
| 10 | Watering Vegetation (610.19) | 1,000 GALLONS | 16 | $200.00 | $600.00 | $1,000.00 | $55.00 |
| 11 | (611.0111) | EACH | 10 | $1,000.00 | $1,000.00 | $1,100.00 | $1,450.00 |
| 12 | (611.0201) | EACH | 39 | $900.00 | $850.00 | $1,000.00 | $1,050.00 |
| 13 | (611.0311) | EACH | 49 | $800.00 | $800.00 | $800.00 | $1,450.00 |
| 14 | (611.0411) | EACH | 387 | $100.00 | $100.00 | $110.00 | $220.00 |
| 15 | Post-Planting Care (611.19) | EACH | 435 | $2.00 | $1.00 | $10.00 | $43.00 |
| 16 | (611.19010024) | 2 | $2.00 | $1.00 | $300.00 | $1,850.00 | |
| 17 | (611.19020024) | 8 | $2.00 | $1.00 | $400.00 | $1,000.00 | |
| 18 | (611.19030024) | 10 | $2.00 | $1.00 | $200.00 | $1,000.00 | |
| 19 | (611.19040024) | 78 | $2.00 | $1.00 | $60.00 | $100.00 | |
| 20 | (614.060102) | EACH | 97 | $600.00 | $700.00 | $600.00 | $2,250.00 |
| 21 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $250,000 | $400,000 | $900,000 | $890,000 |
| 22 | Type III Construction Barricades (619.04) | EACH | 200 | $5.00 | $150.00 | $20.00 | $25.00 |
| 23 | (619.111133) | EACH | 7 | $10,000 | $5,000.00 | $10,000 | $12,000 |
| 24 | Vehicle Arresting Barrier (619.23) | EACH | 10 | $25.00 | $5,000.00 | $100.00 | $3,975.00 |
| 25 | Nighttime Operations (Entire Project) (619.24) | LS | 1 | $500.00 | $300,000 | $50,000 | $105,000 |
| 26 | Traffic Control Supervisor (619.25) | MONTH | 24 | $25.00 | $10,000 | $100.00 | $525.00 |
| 27 | Survey Operations (625.01) | LS | 1 | $100.00 | $25,000 | $5,000.00 | $202,000 |
| 28 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $25.00 | $500.00 | $250.00 | $5,980.00 |
| 29 | Engineer’s Field Office – Type 1 (637.11) | MONTH | 24 | $5,250.00 | $7,500.00 | $5,000.00 | $21,000 |
| 30 | Office Technology and Supplies (637.34) | DOL | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 31 | Construction Testing supplies – Consumables (637.36) | DOL | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 32 | (637.41000115) | 24 | $100.00 | $150.00 | $250.00 | $210.00 | |
| 33 | (637.41000215) | 24 | $100.00 | $150.00 | $250.00 | $210.00 | |
| 34 | (637.41000315) | 24 | $100.00 | $150.00 | $250.00 | $210.00 | |
| 35 | (637.41000415) | 24 | $100.00 | $150.00 | $250.00 | $210.00 | |
| 36 | (637.41000515) | 24 | $100.00 | $150.00 | $250.00 | $210.00 | |
| 37 | (637.41000615) | 24 | $100.00 | $150.00 | $250.00 | $210.00 | |
| 38 | (637.41000715) | 24 | $100.00 | $150.00 | $250.00 | $210.00 | |
| 39 | (645.13070010) | 1 | $2,000.00 | $275.00 | $5,000.00 | $6,050.00 | |
| 40 | (645.13080010) | 100 | $10.00 | $50.00 | $100.00 | $52.00 | |
| 41 | (645.41010015) | 100 | $1.00 | $50.00 | $10.00 | $52.00 | |
| 42 | (645.51010110) | 6,854 | $75.00 | $70.00 | $65.00 | $54.00 | |
| 43 | Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102) | SF | 7,248 | $80.00 | $75.00 | $60.00 | $70.00 |
| 44 | Type A Sign Posts (645.81) | EACH | 1,915 | $250.00 | $300.00 | $350.00 | $272.00 |
| 45 | Soil Plate for Type A Sign Post (645.8105) | EACH | 533 | $25.00 | $75.00 | $100.00 | $317.00 |
| 46 | (645.81090003) | 2,409 | $100.00 | $50.00 | $100.00 | $43.00 | |
| 47 | Pole-Mounted Sign Support System (Band Mounting) (645.85) | EACH | 89 | $150.00 | $100.00 | $500.00 | $650.00 |
| 48 | Relocate Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.31) | EACH | 80 | $100.00 | $400.00 | $200.00 | $500.00 |
| 49 | Remove and Store Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.41) | EACH | 805 | $50.00 | $30.00 | $200.00 | $150.00 |
| 50 | Remove and Dispose Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.51) | EACH | 31 | $50.00 | $30.00 | $200.00 | $100.00 |
| 51 | Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61) | EACH | 483 | $100.00 | $120.00 | $200.00 | $128.67 |
| 52 | (657.16020010) | 929 | $125.00 | $150.00 | $100.00 | $204.00 | |
| 53 | (680.83200010) | LS | 1 | $50,000 | $30,000 | $100,000 | $13,500 |
| 54 | (691.04000020) | 126,000 | $1.00 | $1.00 | $1.00 | $1.00 | |
| 55 | Field Change Payment (FCP) (697.03) | DOL | 517,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 56 | Fuel Price Adjustment (698.05) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 |
| 57 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 |
| 58 | Mobilization (699.040001) | LS | 1 | $138,164 | $150,000 | $187,000 | $209,989 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of August 27, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.