NYSDOT contract D265685 bid tabulation
Crack Sealing & Joint Overlay Repairs- I-495 Exit 48 to 64. Let by New York State DOT on February 5, 2026, Suffolk, Region 10. 4 bids received; low bid $3,644,572 by Constar Inc.
- Owner
- New York State DOT
- Letting
- 05 FEB 2026
- Pay items
- 40
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Constar Inc | $3,644,572 | Low |
| 2 | GGG Construction Corp | $4,112,815 | +13% |
| 3 | Quintal Contracting Corp | $5,781,018 | +59% |
| 4 | Rosemar Contracting Inc | $9,622,811 | +164% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Constar Inc | 2. GGG Construction Corp | 3. Quintal Contracting Corp | 4. Rosemar Contracting Inc |
|---|---|---|---|---|---|---|---|
| 1 | (404.0971) | TON | 945 | $125.00 | $300.00 | $595.00 | $1,200.00 |
| 2 | (404.1979) | TON | 1,447 | $125.00 | $290.00 | $585.00 | $1,200.00 |
| 3 | Diluted Tack Coat (407.0102) | GAL | 402 | $3.00 | $25.00 | $18.00 | $10.00 |
| 4 | (412.76020010) | 400 | $6.00 | $15.00 | $13.00 | $200.00 | |
| 5 | (412.76030008) | 325 | $4,700.00 | $4,200.00 | $4,450.00 | $4,800.00 | |
| 6 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 60,260 | $0.50 | $1.00 | $2.00 | $1.00 |
| 7 | Miscellaneous Cold Milling of Bituminous Concrete (490.30) | SY | 8,035 | $5.00 | $30.00 | $21.00 | $125.00 |
| 8 | (520.09000010) | 60,260 | $1.00 | $6.00 | $5.00 | $5.00 | |
| 9 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $500,000 | $212,550 | $650,000 | $1,820,000 |
| 10 | Type III Construction Barricades (619.04) | EACH | 600 | $10.00 | $100.00 | $10.00 | $125.00 |
| 11 | (619.10050020) | 1,496 | $10.00 | $5.00 | $10.00 | $65.00 | |
| 12 | (619.110743) | EACH | 12 | $1,000.00 | $2,500.00 | $5,000.00 | $5,000.00 |
| 13 | (619.110943) | EACH | 6 | $1,000.00 | $2,500.00 | $5,000.00 | $5,000.00 |
| 14 | (619.111133) | EACH | 6 | $1,000.00 | $2,500.00 | $5,000.00 | $5,000.00 |
| 15 | Vehicle Arresting Barrier (619.23) | EACH | 5 | $500.00 | $1,000.00 | $1,000.00 | $15,000 |
| 16 | Nighttime Operations (Entire Project) (619.24) | LS | 1 | $250,000 | $125,000 | $275,000 | $200,000 |
| 17 | Traffic Control Supervisor (619.25) | MONTH | 20 | $100.00 | $1,000.00 | $400.00 | $100.00 |
| 18 | Pavement Patching (Force Acount) (619.2601) | DOL | 100,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 19 | Survey Operations (625.01) | LS | 1 | $1,000.00 | $2,500.00 | $5,000.00 | $50,000 |
| 20 | Cleaning, Sealing and/or Filling Joints (633.13) | LF | 60,260 | $0.50 | $0.50 | $3.50 | $3.00 |
| 21 | Removal and Repair of Loose, Broken, or Spalled PCC Pavement (633.15) | SY | 804 | $15.00 | $20.00 | $10.00 | $65.00 |
| 22 | Engineer’s Field Office – Type 3 (637.13) | MONTH | 24 | $4,000.00 | $4,000.00 | $5,000.00 | $5,000.00 |
| 23 | Office Technology and Supplies (637.34) | DOL | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 24 | Construction Testing supplies – Consumables (637.36) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 |
| 25 | (645.03030015) | 26 | $2,100.00 | $600.00 | $3,000.00 | $3,200.00 | |
| 26 | (645.03040015) | 8 | $2,900.00 | $900.00 | $5,000.00 | $4,600.00 | |
| 27 | (680.83200010) | LS | 1 | $100.00 | $1,000.00 | $2,000.00 | $10,000 |
| 28 | (685.02000010) | 26 | $100.00 | $100.00 | $200.00 | $100.00 | |
| 29 | (685.03130018) | 26 | $150.00 | $280.00 | $312.50 | $250.00 | |
| 30 | (685.07200110) | 9,031 | $2.00 | $3.30 | $3.70 | $2.95 | |
| 31 | (685.07200310) | 4 | $200.00 | $336.00 | $375.00 | $300.00 | |
| 32 | (685.07200410) | 500 | $2.00 | $5.00 | $5.65 | $5.00 | |
| 33 | (685.07200510) | 500 | $2.00 | $5.00 | $5.65 | $5.00 | |
| 34 | (685.07200610) | 1,307 | $2.00 | $3.30 | $3.70 | $5.00 | |
| 35 | (685.07200710) | 500 | $2.00 | $5.00 | $5.65 | $5.00 | |
| 36 | Field Change Payment (FCP) (697.03) | DOL | 379,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 37 | Asphalt Price Adjustment (698.04) | DOL | 10,200 | $1.00 | $1.00 | $1.00 | $1.00 |
| 38 | Fuel Price Adjustment (698.05) | DOL | 1,800 | $1.00 | $1.00 | $1.00 | $1.00 |
| 39 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 |
| 40 | Mobilization (699.040001) | LS | 1 | $140,175 | $158,185 | $222,346 | $273,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of February 5, 2026. Compiled by Mirage Metrics.