NYSDOT contract D265800 bid tabulation
Sign Structures Replacement. Let by New York State DOT on October 1, 2026, Bronx, Queens, Region 11. 5 bids received; low bid $21,414,264 by Westmoreland Construction Inc.
- Owner
- New York State DOT
- Letting
- 01 OCT 2026
- Pay items
- 199
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Westmoreland Construction Inc | $21,414,264 | Low |
| 2 | Es II Enterprises LLC /DBA El Sol Enterprises | $22,928,321 | +7.0% |
| 3 | Paul J Scariano Inc | $26,750,000 | +25% |
| 4 | H & L Contracting LLC | $27,264,903 | +27% |
| 5 | Tully Construction Company Inc | $33,912,838 | +58% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Westmoreland Construction Inc | 2. Es II Enterprises LLC /DBA El Sol Enterprises | 3. Paul J Scariano Inc | 4. H & L Contracting LLC | 5. Tully Construction Company Inc |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.06) | LS | 1 | $10,000 | $40,000 | $55,192 | $100,000 | $30,000 |
| 2 | Removal of Steel Supported Structural Slabs (with shear connectors) – Type A (202.2201) | SF | 168 | $400.00 | $241.04 | $200.00 | $200.00 | $1,110.00 |
| 3 | Unclassified Excavation and Disposal (203.02) | CY | 122 | $250.00 | $250.00 | $600.00 | $420.00 | $830.00 |
| 4 | Embankment In Place (203.03) | CY | 70 | $250.00 | $250.00 | $250.00 | $150.00 | $215.00 |
| 5 | Select Structural Fill (203.21) | CY | 66 | $200.00 | $350.00 | $650.00 | $1,056.24 | $250.00 |
| 6 | Structure Excavation (206.01) | CY | 100 | $2,000.00 | $420.00 | $340.00 | $300.00 | $1,780.00 |
| 7 | Conduit Excavation and Backfill including Surface Restoration (206.03) | LF | 273 | $165.00 | $300.00 | $200.00 | $330.00 | $440.00 |
| 8 | (206.03120010) | 630 | $150.00 | $90.00 | $120.00 | $130.00 | $160.00 | |
| 9 | Test Pit Excavation (206.05) | EACH | 30 | $3,500.00 | $2,500.00 | $4,250.00 | $3,400.00 | $4,000.00 |
| 10 | Silt Fence - Temporary (209.13) | LF | 66 | $10.00 | $45.00 | $45.00 | $95.00 | $135.00 |
| 11 | Drainage Structure Inlet Protection, Catch Basin Inserts Oil and Hydrocarbon Absorbent Pouches – Temporary (209.1708) | EACH | 28 | $450.00 | $800.00 | $450.00 | $600.00 | $300.00 |
| 12 | Subbase Course, Type 1 (304.11) | CY | 136 | $120.00 | $300.00 | $260.00 | $450.00 | $500.00 |
| 13 | (404.0189) | TON | 89 | $500.00 | $200.00 | $640.00 | $350.00 | $1,600.00 |
| 14 | (404.0972) | TON | 4 | $500.00 | $950.00 | $4,000.00 | $380.00 | $510.00 |
| 15 | (404.0989) | TON | 36 | $500.00 | $350.00 | $640.00 | $380.00 | $445.00 |
| 16 | (404.1989) | TON | 19 | $500.00 | $450.00 | $640.00 | $380.00 | $530.00 |
| 17 | (404.3789) | TON | 72 | $500.00 | $250.00 | $640.00 | $380.00 | $530.00 |
| 18 | Diluted Tack Coat (407.0102) | GAL | 12 | $1.00 | $70.00 | $300.00 | $25.00 | $570.00 |
| 19 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 383 | $20.00 | $45.00 | $35.00 | $20.00 | $1.00 |
| 20 | (502.0021) | 6 | $3,000.00 | $1,800.00 | $1,100.00 | $10,000 | $3,100.00 | |
| 21 | Performance Concrete Quality Adjustment - PCC Pavement (502.99) | QUALITY UNIT | 1 | $3.12 | $3.12 | $3.12 | $3.12 | $3.12 |
| 22 | PCC Foundation for Pavement, PEM Concrete (503.1013) | CY | 187 | $500.00 | $650.00 | $480.00 | $500.00 | $1,400.00 |
| 23 | (510.81000018) | 87 | $40.00 | $80.00 | $300.00 | $155.00 | $130.00 | |
| 24 | (520.09000010) | 103 | $15.00 | $50.00 | $40.00 | $70.00 | $215.00 | |
| 25 | (520.50000004) | 410 | $45.00 | $25.00 | $60.00 | $58.54 | $78.00 | |
| 26 | Temporary Steel Sheeting (552.13) | SF | 4,240 | $20.00 | $25.00 | $20.00 | $65.00 | $115.00 |
| 27 | Concrete for Structures, Performance (555.0021) | CY | 259 | $6,000.00 | $4,250.00 | $3,000.00 | $3,800.00 | $2,850.00 |
| 28 | (555.72000016) | 20 | $750.00 | $350.00 | $1,000.00 | $940.00 | $180.00 | |
| 29 | Performance Concrete Quality Adjustment – Concrete for Structures (555.9902) | QUALITY UNIT | 1 | $25.00 | $25.00 | $25.00 | $25.00 | $25.00 |
| 30 | Epoxy-Coated Bar Reinforcement for Structures (556.0202) | LB | 40,508 | $8.00 | $5.00 | $3.00 | $9.00 | $3.75 |
| 31 | (557.1111) | SY | 12 | $5,000.00 | $5,500.00 | $6,000.00 | $5,600.00 | $10,800 |
| 32 | Performance Concrete Quality Adjustment – Superstructure and Approach Slab (557.9901) | QUALITY UNIT | 1 | $15.16 | $15.16 | $15.16 | $15.16 | $15.16 |
| 33 | (560.10040010) | 120 | $35.00 | $70.00 | $60.00 | $65.00 | $100.00 | |
| 34 | (560.70000008) | 309 | $30.00 | $170.00 | $300.00 | $225.00 | $100.00 | |
| 35 | (560.80010011) | 819 | $15.00 | $30.00 | $45.00 | $35.00 | $50.00 | |
| 36 | (564.510001) | LB | 21,276 | $50.00 | $35.00 | $60.00 | $25.00 | $115.00 |
| 37 | Transition Bridge Railing (568.70) | LF | 71 | $700.00 | $500.00 | $500.00 | $340.00 | $90.00 |
| 38 | Vertical Faced Concrete Parapet (569.03) | LF | 49 | $1,750.00 | $800.00 | $1,500.00 | $1,700.00 | $1,500.00 |
| 39 | Performance Concrete Quality Adjustment–Cast-In-Place Concrete Barrier (569.99) | QUALITY UNIT | 1 | $26.14 | $26.14 | $26.14 | $26.14 | $26.14 |
| 40 | Lead-Exposure Control Plan (570.01) | LS | 1 | $7,500.00 | $5,000.00 | $5,000.00 | $10,000 | $30,000 |
| 41 | Medical Testing (570.02) | DOL | 11,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 42 | (570.160001) | LS | 1 | $7,500.00 | $10,000 | $6,000.00 | $10,000 | $22,000 |
| 43 | Disposal of Hazardous Paint Removal Waste Containing Lead (571.03) | LB | 189 | $15.00 | $50.00 | $15.00 | $1.00 | $6.00 |
| 44 | (572.010001) | SF | 1,780 | $85.00 | $20.00 | $25.00 | $15.00 | $25.00 |
| 45 | (574.030001) | SF | 360 | $130.00 | $100.00 | $150.00 | $250.00 | $350.00 |
| 46 | Removal of Structural Concrete (580.01) | CY | 86 | $3,000.00 | $2,250.00 | $4,000.00 | $4,500.00 | $1,600.00 |
| 47 | (580.01010010) | 11 | $500.00 | $400.00 | $240.00 | $800.00 | $1,400.00 | |
| 48 | Removal of Bituminous Concrete Overlay (Bridge) (581.01) | SF | 20 | $125.00 | $5.00 | $180.00 | $380.00 | $550.00 |
| 49 | Drilling and Grouting Bolts or Reinforcing Bars (586.0201) | EACH | 319 | $40.00 | $120.00 | $250.00 | $145.00 | $125.00 |
| 50 | Field Drill Holes in Existing Structural Steel (586.10) | EACH | 76 | $70.00 | $90.00 | $120.00 | $150.00 | $605.00 |
| 51 | (589.010001) | LB | 1,941 | $20.00 | $25.00 | $30.00 | $15.50 | $37.00 |
| 52 | (589.010002) | LB | 1,403 | $20.00 | $25.00 | $30.00 | $15.50 | $37.00 |
| 53 | Box Beam Guide Railing (606.10) | LF | 121 | $100.00 | $140.00 | $200.00 | $117.60 | $37.00 |
| 54 | Anchorage Units for Corrugated Beam Guide Railing (606.22) | EACH | 3 | $5,000.00 | $5,250.00 | $7,500.00 | $4,410.00 | $850.00 |
| 55 | Anchorage Units for Corrugated Beam Guide Railing Buried In Back Slope (606.2201) | EACH | 2 | $10,000 | $6,500.00 | $9,100.00 | $5,460.00 | $850.00 |
| 56 | HPBO (Mod.) Corrugated Beam Guide Railing End Terminal (Energy-Absorbing) (606.27) | EACH | 7 | $11,000 | $6,400.00 | $9,000.00 | $8,500.00 | $4,300.00 |
| 57 | HPBO (Mod.) Corrugated Beam Guide Railing (606.2701) | LF | 4,882 | $70.00 | $50.00 | $70.00 | $55.00 | $50.00 |
| 58 | Anchorage Units for HPBO (Mod.) Corrugated Beam Guide Railing (606.2703) | EACH | 8 | $6,500.00 | $6,000.00 | $7,000.00 | $7,500.00 | $4,000.00 |
| 59 | HPBO (Mod.) Corrugated Beam Median Barrier (606.2801) | LF | 714 | $90.00 | $80.00 | $100.00 | $75.00 | $60.00 |
| 60 | Concrete Barrier Type A (Optional) (606.3001) | LF | 147 | $300.00 | $600.00 | $300.00 | $250.00 | $950.00 |
| 61 | Single-Slope Concrete Median Barrier (Optional) (606.3041) | LF | 71 | $800.00 | $650.00 | $330.00 | $300.00 | $1,300.00 |
| 62 | (606.34030008) | 2 | $6,500.00 | $6,250.00 | $7,500.00 | $7,500.00 | $3,300.00 | |
| 63 | (606.36050010) | 10 | $4,000.00 | $8,900.00 | $4,855.00 | $7,500.00 | $3,300.00 | |
| 64 | Removing and Disposing Corrugated Beam Guide Railing (606.71) | LF | 438 | $7.00 | $13.00 | $15.00 | $15.00 | $17.00 |
| 65 | Removing and Disposing HPBO (Mod.) Corrugated Beam Guide Railing (606.7101) | LF | 4,572 | $4.00 | $13.00 | $15.00 | $12.00 | $12.00 |
| 66 | Removing and Disposing HPBO (Mod.) Corrugated Beam Median Barrier (606.7201) | LF | 678 | $7.00 | $19.00 | $25.00 | $18.00 | $17.00 |
| 67 | Removing and Disposing Box Beam Guide Railing (606.73) | LF | 588 | $7.00 | $19.00 | $25.00 | $18.00 | $17.00 |
| 68 | Removing and Disposing Concrete Barrier (606.75) | LF | 273 | $120.00 | $120.00 | $70.00 | $145.00 | $370.00 |
| 69 | Removing and Disposing Box Beam Guide Rail Turned-Down Terminal (606.7920) | EACH | 2 | $1,250.00 | $250.00 | $300.00 | $2,500.00 | $365.00 |
| 70 | Removing and Disposing Anchorage Units for HPBO(Mod) Corrugated Beam Guide Railing (606.7941) | EACH | 23 | $1,500.00 | $375.00 | $500.00 | $2,500.00 | $485.00 |
| 71 | (606.90000011) | 21 | $10,000 | $3,200.00 | $1,800.00 | $2,400.00 | $1,450.00 | |
| 72 | (607.41010010) | 410 | $8.00 | $20.00 | $40.00 | $20.00 | $27.00 | |
| 73 | (607.95010007) | 138 | $100.00 | $134.00 | $175.00 | $115.00 | $150.00 | |
| 74 | (608.01020011) | 55 | $700.00 | $500.00 | $400.00 | $285.00 | $530.00 | |
| 75 | (609.06000008) | 174 | $15.00 | $120.00 | $135.00 | $5.00 | $105.00 | |
| 76 | (609.26020111) | 173 | $150.00 | $245.00 | $300.00 | $175.00 | $175.00 | |
| 77 | Mycorrhizal Fungi (610.0701) | LB | 402 | $25.00 | $40.00 | $25.00 | $40.00 | $48.00 |
| 78 | Mycorrhizal Fungi (610.0702) | GAL | 1 | $25.00 | $600.00 | $5,000.00 | $600.00 | $725.00 |
| 79 | Compost (610.10) | CY | 1,145 | $90.00 | $105.00 | $100.00 | $50.00 | $125.00 |
| 80 | Mulch for Planting Type A, B & D Wood Chips and Shredded Bark (610.1101) | CY | 1,149 | $25.00 | $100.00 | $30.00 | $50.00 | $120.00 |
| 81 | Mulch for Planting Type C – USDA-APHIS Protocol Wood Chips (610.1102) | CY | 1,149 | $25.00 | $98.00 | $30.00 | $50.00 | $120.00 |
| 82 | Topsoil - Roadside (610.1402) | CY | 200 | $200.00 | $120.00 | $200.00 | $50.00 | $145.00 |
| 83 | Topsoil - Lawns (610.1403) | CY | 2,040 | $105.00 | $125.00 | $150.00 | $50.00 | $150.00 |
| 84 | Preparation of Subsoil for Turf Establishment (610.15) | SY | 1,000 | $6.00 | $10.50 | $15.00 | $10.00 | $125.00 |
| 85 | Turf Establishment -Lawns (610.1602) | SY | 12,611 | $4.50 | $8.00 | $6.00 | $4.00 | $8.00 |
| 86 | Watering Vegetation (610.19) | 1,000 GALLONS | 100 | $300.00 | $300.00 | $350.00 | $300.00 | $300.00 |
| 87 | Mowing Limits Markers (610.22) | EACH | 51 | $50.00 | $950.00 | $60.00 | $950.00 | $950.00 |
| 88 | Care of Trees up to 12” Diam. at Breast Height – Pruning (614.0411) | EACH | 1 | $550.00 | $600.00 | $750.00 | $600.00 | $600.00 |
| 89 | Care of Trees Over 12” to 24” Diam. at Breast Height - Pruning (614.0421) | EACH | 3 | $900.00 | $900.00 | $1,000.00 | $900.00 | $950.00 |
| 90 | Care of Trees Over 24” to 36” Diam. at Breast Height - Pruning (614.0431) | EACH | 1 | $1,000.00 | $1,500.00 | $1,100.00 | $1,500.00 | $1,500.00 |
| 91 | Care of Trees Over 36” to 48” Diam. at Breast Height – Pruning (614.0441) | EACH | 1 | $1,000.00 | $2,000.00 | $1,200.00 | $2,000.00 | $2,000.00 |
| 92 | Tree Root Zone Treatment (Vertical Mulching/Aeration) (614.08) | SY | 105 | $25.00 | $200.00 | $35.00 | $200.00 | $200.00 |
| 93 | (614.08210009) | 6 | $300.00 | $900.00 | $225.00 | $900.00 | $1,000.00 | |
| 94 | Tree Root Pruning (614.09) | LF | 1 | $100.00 | $100.00 | $5,000.00 | $2,500.00 | $200.00 |
| 95 | (615.33010011) | 32 | $500.00 | $732.00 | $1,000.00 | $800.00 | $1,900.00 | |
| 96 | (615.43000011) | 1 | $1,000.00 | $300.00 | $5,000.00 | $500.00 | $125.00 | |
| 97 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $1,000,000 | $2,275,000 | $2,400,000 | $3,250,000 | $8,000,000 |
| 98 | (619.02970001) | 527 | $400.00 | $65.00 | $100.00 | $150.00 | $70.00 | |
| 99 | Type III Construction Barricades (619.04) | EACH | 12 | $100.00 | $220.00 | $250.00 | $250.00 | $450.00 |
| 100 | (619.080101) | LF | 6,442 | $2.00 | $2.00 | $2.00 | $2.02 | $2.30 |
| 101 | Cover Existing Pavement Marking Stripes (Removable Tape) (619.0803) | LF | 1 | $20.00 | $6.00 | $5,000.00 | $5.83 | $7.00 |
| 102 | (619.100101) | LF | 19,714 | $3.00 | $1.00 | $1.00 | $0.98 | $0.80 |
| 103 | (619.100201) | EACH | 14 | $500.00 | $120.00 | $125.00 | $121.97 | $140.00 |
| 104 | (619.10050020) | 837 | $10.00 | $36.00 | $45.00 | $11.00 | $25.00 | |
| 105 | (619.110511) | EACH | 3 | $7,500.00 | $25,000 | $30,000 | $75,000 | $70,000 |
| 106 | Maintain Traffic Signal Equipment (Requirement A) Intersection (619.1611) | MONTH | 27 | $100.00 | $500.00 | $6,000.00 | $4,809.00 | $5,000.00 |
| 107 | Temporary Positive Barrier – Category 1 (Pinning Prohibited) (619.1711) | LF | 3,251 | $90.00 | $50.00 | $90.00 | $112.00 | $90.00 |
| 108 | Temporary Positive Barrier – Category 5 (Pinning Prohibited) (619.1715) | LF | 8,948 | $90.00 | $50.00 | $90.00 | $115.00 | $145.00 |
| 109 | Warning Lights on Temporary Positive Barriers (619.1719) | EACH | 260 | $25.00 | $30.00 | $90.00 | $157.00 | $115.00 |
| 110 | Temporary Impact Attenuator - Redirective (Test Level 2) (619.1802) | EACH | 10 | $15,000 | $10,000 | $15,000 | $12,000 | $35,000 |
| 111 | Temporary Impact Attenuator - Redirective (Test Level 3) (619.1803) | EACH | 10 | $20,000 | $10,000 | $15,000 | $28,000 | $35,000 |
| 112 | Temporary Sand Barrel Module (619.21) | EACH | 15 | $1,200.00 | $1,200.00 | $1,500.00 | $4,200.00 | $3,300.00 |
| 113 | Nighttime Operations (Entire Project) (619.24) | LS | 1 | $500,000 | $500,000 | $350,000 | $1,950,000 | $2,220,000 |
| 114 | (619.67020010) | LS | 1 | $25,000 | $40,000 | $30,000 | $21,720 | $26,000 |
| 115 | Survey Operations (625.01) | LS | 1 | $100,000 | $450,000 | $350,000 | $400,000 | $480,000 |
| 116 | (627.50140008) | 1 | $10.00 | $10.00 | $5,000.00 | $5,500.00 | $110.00 | |
| 117 | Cleaning, Sealing and/or Filling Joints (633.13) | LF | 44 | $25.00 | $150.00 | $250.00 | $15.15 | $200.00 |
| 118 | (634.90040011) | 27 | $1,750.00 | $1,500.00 | $750.00 | $1,500.00 | $970.00 | |
| 119 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $1,000.00 | $5,000.00 | $6,000.00 | $9,357.22 | $3,600.00 |
| 120 | Engineer’s Field Office – Type 3 (637.13) | MONTH | 27 | $7,500.00 | $6,500.00 | $25,000 | $12,500 | $12,000 |
| 121 | (637.31020020) | 27 | $1,000.00 | $950.00 | $1,000.00 | $1,000.00 | $1,000.00 | |
| 122 | Office Technology and Supplies (637.34) | DOL | 6,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 123 | Partnering Workshop (637.35) | DOL | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 124 | (639.10210011) | LS | 1 | $75,000 | $80,000 | $75,000 | $75,000 | $75,000 |
| 125 | White Paint Reflectorized Pavement Stripes – 20 mils (640.20) | LF | 11,350 | $3.00 | $1.00 | $0.60 | $0.62 | $0.70 |
| 126 | Yellow Paint Reflectorized Pavement Stripes - 20 mils (640.21) | LF | 5,475 | $3.00 | $1.00 | $0.60 | $0.62 | $0.70 |
| 127 | Anchor Bolts (644.11) | LB | 15,440 | $15.00 | $25.00 | $17.50 | $28.00 | $11.00 |
| 128 | Drilled Shaft for Overhead Sign Structures (644.20) | CY | 343 | $6,200.00 | $9,250.00 | $12,500 | $7,500.00 | $6,100.00 |
| 129 | Rectangular Footing for Overhead Sign Structures (644.30) | CY | 19 | $7,000.00 | $4,000.00 | $7,500.00 | $7,500.00 | $6,100.00 |
| 130 | (644.420915) | EACH | 1 | $120,000 | $100,000 | $120,000 | $125,000 | $110,000 |
| 131 | (644.420930) | EACH | 2 | $165,000 | $150,000 | $180,000 | $175,000 | $110,000 |
| 132 | (644.421035) | EACH | 1 | $160,000 | $150,000 | $190,000 | $175,000 | $110,000 |
| 133 | (644.421125) | EACH | 3 | $175,000 | $150,000 | $175,000 | $175,000 | $110,000 |
| 134 | (644.421420) | EACH | 1 | $180,000 | $130,000 | $165,000 | $175,000 | $110,000 |
| 135 | (644.432060) | EACH | 1 | $200,000 | $180,000 | $220,000 | $225,000 | $180,000 |
| 136 | (644.432560) | EACH | 3 | $200,000 | $200,000 | $235,000 | $225,000 | $180,000 |
| 137 | (644.432590) | EACH | 1 | $200,000 | $190,000 | $220,000 | $225,000 | $180,000 |
| 138 | (644.433090) | EACH | 2 | $200,000 | $220,000 | $250,000 | $265,000 | $220,000 |
| 139 | (644.434590) | EACH | 1 | $300,000 | $340,000 | $435,000 | $425,000 | $295,000 |
| 140 | (644.4401) | EACH | 3 | $200,000 | $180,000 | $215,000 | $250,000 | $250,000 |
| 141 | (644.4402) | EACH | 1 | $425,000 | $325,000 | $410,000 | $425,000 | $250,000 |
| 142 | (644.4403) | EACH | 1 | $220,000 | $200,000 | $235,000 | $250,000 | $250,000 |
| 143 | (644.4404) | EACH | 1 | $220,000 | $200,000 | $245,000 | $275,000 | $250,000 |
| 144 | Performance Concrete Quality Adjustment (644.99) | QUALITY UNIT | 1 | $25.00 | $25.00 | $25.00 | $25.00 | $25.00 |
| 145 | Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102) | SF | 1 | $100.00 | $51.00 | $51.00 | $55.00 | $215.00 |
| 146 | Ground-Mounted Sign Panels greater than 32 SF with Z-bars (645.5103) | SF | 181 | $50.00 | $60.00 | $70.00 | $65.00 | $85.00 |
| 147 | Overhead Sign Panels (645.61) | SF | 9,304 | $50.00 | $70.00 | $80.00 | $75.00 | $60.00 |
| 148 | Type A Sign Posts (645.81) | EACH | 1 | $1,500.00 | $350.00 | $345.00 | $1,500.00 | $515.00 |
| 149 | High-Capacity Type A Sign Posts with Soil Plates Only (645.8106) | EACH | 1 | $2,500.00 | $1,600.00 | $2,000.00 | $6,500.00 | $1,000.00 |
| 150 | (645.830203) | EACH | 4 | $3,500.00 | $5,000.00 | $6,000.00 | $6,500.00 | $3,500.00 |
| 151 | (645.830402) | EACH | 2 | $5,000.00 | $5,000.00 | $6,000.00 | $6,500.00 | $4,200.00 |
| 152 | Pole-Mounted Sign Support System (Band Mounting) (645.85) | EACH | 7 | $300.00 | $350.00 | $400.00 | $500.00 | $160.00 |
| 153 | Removal of Cantilever Overhead Sign Panel(s), Structure, and Foundations (647.20) | EACH | 3 | $12,500 | $50,000 | $27,000 | $25,000 | $19,500 |
| 154 | Removal of Single Span Overhead Sign Panel(s), Structure, and Foundations (647.21) | EACH | 15 | $20,000 | $70,000 | $40,000 | $35,000 | $35,000 |
| 155 | Removal of Multi-Span Overhead Sign Panel(s), Structure, and Foundations (647.22) | EACH | 2 | $30,000 | $70,000 | $45,000 | $35,000 | $43,000 |
| 156 | Relocate Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.31) | EACH | 3 | $1,000.00 | $400.00 | $500.00 | $500.00 | $700.00 |
| 157 | Relocate Sign Panel, Sign Panel Assembly Size III (Over 100 Square Feet) (647.33) | EACH | 1 | $15,000 | $1,300.00 | $1,700.00 | $1,600.00 | $1,400.00 |
| 158 | (654.0101) | EACH | 1 | $650.00 | $2,000.00 | $3,200.00 | $1,600.00 | $5,000.00 |
| 159 | (654.0102) | EACH | 1 | $800.00 | $2,000.00 | $3,400.00 | $1,600.00 | $5,000.00 |
| 160 | (654.0103) | EACH | 2 | $900.00 | $2,000.00 | $3,700.00 | $1,600.00 | $5,000.00 |
| 161 | (654.0104) | EACH | 4 | $1,100.00 | $2,000.00 | $4,400.00 | $1,600.00 | $5,000.00 |
| 162 | Concrete Foundation for Impact Attenuators (654.05) | CY | 4 | $4,500.00 | $3,500.00 | $4,500.00 | $12,000 | $4,100.00 |
| 163 | Remove and Dispose Impact Attenuator Systems (654.0701) | EACH | 10 | $2,500.00 | $2,000.00 | $1,000.00 | $1,200.00 | $2,700.00 |
| 164 | Expendable Impact Attenuator , TL 2, ≤ 2 ft Obstruction Width (654.5020) | EACH | 1 | $35,000 | $27,000 | $50,000 | $44,000 | $36,000 |
| 165 | Expendable Impact Attenuator , TL 2, > 2 ft up to 5 ft Obstruction Width (654.5022) | EACH | 1 | $45,000 | $27,000 | $55,000 | $56,000 | $36,000 |
| 166 | (654.51320015) | 1 | $45,000 | $35,000 | $50,000 | $58,000 | $40,000 | |
| 167 | (654.51350015) | 1 | $50,000 | $40,000 | $55,000 | $68,000 | $40,000 | |
| 168 | (670.2306) | LF | 641 | $100.00 | $80.00 | $200.00 | $90.00 | $110.00 |
| 169 | (670.7004) | LF | 37 | $11.00 | $10.00 | $10.00 | $10.40 | $12.50 |
| 170 | Ground Wire No. 6 AWG. (670.7501) | LF | 173 | $7.00 | $6.00 | $9.00 | $6.00 | $7.00 |
| 171 | (670.75060011) | 16 | $14.00 | $12.00 | $9.00 | $13.70 | $16.00 | |
| 172 | (680.51050010) | 1 | $5,000.00 | $3,500.00 | $5,500.00 | $3,560.00 | $7,500.00 | |
| 173 | (680.520108) | LF | 231 | $110.00 | $90.00 | $180.00 | $100.00 | $120.00 |
| 174 | (680.520205) | LF | 120 | $100.00 | $80.00 | $75.00 | $90.00 | $110.00 |
| 175 | (680.520406) | LF | 30 | $130.00 | $120.00 | $150.00 | $130.00 | $150.00 |
| 176 | (680.53000111) | 2 | $5,000.00 | $2,500.00 | $7,500.00 | $3,280.00 | $4,000.00 | |
| 177 | (680.83200010) | LS | 1 | $30,000 | $25,000 | $30,000 | $22,308 | $60,000 |
| 178 | (680.96460011) | 1 | $10,000 | $8,000.00 | $17,500 | $8,660.00 | $10,000 | |
| 179 | (680.97165011) | 1 | $22,500 | $25,000 | $30,000 | $22,480 | $27,000 | |
| 180 | (680.98124811) | 1 | $6,000.00 | $5,000.00 | $3,250.00 | $5,310.00 | $6,400.00 | |
| 181 | (680.99910011) | LS | 1 | $100,000 | $30,000 | $75,000 | $79,110 | $95,000 |
| 182 | (683.07100010) | 95 | $45.00 | $50.00 | $25.00 | $44.30 | $54.00 | |
| 183 | (683.09150011) | 1 | $26,000 | $25,000 | $40,000 | $25,350 | $30,000 | |
| 184 | (683.09150111) | 9 | $30,000 | $14,000 | $40,000 | $27,240 | $33,000 | |
| 185 | (683.09230208) | 1 | $15,000 | $15,000 | $20,000 | $12,300 | $15,000 | |
| 186 | (683.10110008) | 1 | $30,000 | $25,000 | $60,000 | $26,750 | $32,000 | |
| 187 | (683.80800208) | 1 | $5,000.00 | $5,000.00 | $4,000.00 | $2,974.00 | $3,500.00 | |
| 188 | (683.85020011) | 1 | $7,500.00 | $5,860.00 | $20,000 | $6,190.00 | $7,500.00 | |
| 189 | (683.91150011) | 2 | $40,000 | $30,000 | $45,000 | $35,210 | $42,000 | |
| 190 | White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102) | LF | 4,184 | $4.00 | $1.50 | $1.25 | $1.02 | $1.00 |
| 191 | Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202) | LF | 1,382 | $5.00 | $1.50 | $1.25 | $1.02 | $1.00 |
| 192 | (685.16010014) | 1,944 | $6.00 | $2.50 | $1.95 | $2.07 | $2.00 | |
| 193 | (685.17010014) | 3,495 | $6.00 | $2.50 | $1.95 | $2.07 | $2.00 | |
| 194 | (691.04000020) | 252,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | |
| 195 | Field Change Payment (FCP) (697.03) | DOL | 1,290,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 196 | Asphalt Price Adjustment (698.04) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 197 | Fuel Price Adjustment (698.05) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 198 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 199 | Mobilization (699.040001) | LS | 1 | $750,000 | $850,138 | $1,000,000 | $1,048,000 | $1,240,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of October 1, 2026. Compiled by Mirage Metrics.