NYSDOT contract D265624 bid tabulation

Parkway Guide Sign and Sign Structure Replacement. Let by New York State DOT on March 26, 2026, Westchester, Region 08. 2 bids received; low bid $16,294,724 by Tully Construction Company Inc.

Owner
New York State DOT
Letting
26 MAR 2026
Pay items
180
Data through
15 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Tully Construction Company Inc$16,294,724Low
2Westmoreland Construction Inc$20,222,222+24%
NYSDOT contract D265624: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Tully Construction Company Inc2. Westmoreland Construction Inc
1Clearing and Grubbing (201.06)LS1$36,000$99,592
2Unclassified Excavation and Disposal (203.02)CY15$1,000.00$300.00
3Structure Excavation (206.01)CY175$300.00$750.00
4Conduit Excavation and Backfill including Surface Restoration (206.03)LF850$50.00$150.00
5 (206.03050005)24$750.00$400.00
6 (206.03120010)320$55.00$100.00
7 (304.11000008)4$275.00$250.00
8 (502.94000018)151$25.00$50.00
9Footing Concrete, Performance (555.0011)CY17$2,110.00$7,500.00
10Concrete for Structures, Performance (555.0021)CY210$1,170.00$5,000.00
11Performance Concrete Quality Adjustment – Footing Concrete (555.9901)QUALITY UNIT1$15.00$15.00
12Performance Concrete Quality Adjustment – Concrete for Structures (555.9902)QUALITY UNIT1$15.00$15.00
13Uncoated Bar Reinforcement for Concrete Structures (556.0201)LB556$5.00$20.00
14Epoxy-Coated Bar Reinforcement for Structures (556.0202)LB25,845$5.00$15.00
15Protective Sealing of New Structural Concrete (559.02)SF1,396$7.00$3.00
16 (560.70000008)13$200.00$1,000.00
17 (560.80010011)216$55.00$50.00
18 (564.700001)EACH1$72,000$100,000
19 (564.700002)EACH1$21,000$150,000
20 (564.700003)EACH3$12,000$75,000
21Type E.B. Expansion Bearing (112 to 168 k) (565.2033)EACH1$31,000$50,000
22 (570.090001)LS1$12,500$10,000
23 (570.090002)LS1$12,500$10,000
24 (570.090003)LS1$12,500$10,000
25 (570.090004)LS1$15,700$10,000
26 (570.090005)LS1$15,700$10,000
27 (570.160001)LS1$22,900$10,000
28 (570.160002)LS1$22,550$10,000
29 (570.160003)LS1$14,500$10,000
30Disposal of Hazardous Paint Removal Waste Containing Lead (571.03)LB2,380$5.00$5.00
31 (572.010001)SF396$115.00$30.00
32 (572.010002)SF300$115.00$30.00
33 (572.010003)SF80$115.00$30.00
34 (574.030001)SF250$200.00$250.00
35 (574.030002)SF235$200.00$250.00
36 (574.030003)SF100$300.00$250.00
37Removal and Replacement of Structural Concrete (582.0051)CY1$9,000.00$25,000
38 (585.01)EACH1$60,000$350,000
39Drilling and Grouting Bolts or Reinforcing Bars (586.0201)EACH330$80.00$50.00
40Drilling and Grouting Bolts or Reinforcing Bars (with Non-Destructive Investigation) (586.0202)EACH319$80.00$50.00
41Drilling and Grouting Bolts or Reinforcing Bars with Pullout Test (586.0301)EACH118$80.00$600.00
42Drilling and Grouting Bolts or Reinforcing Bars with Pullout Test (with Non- Destructive Investigation) (586.0302)EACH165$80.00$100.00
43Field Drill Holes in Existing Structural Steel (586.10)EACH896$350.00$65.00
44 (589.520001)EACH2$20,600$10,000
45 (589.520002)EACH2$9,350.00$10,000
46 (589.520003)EACH2$13,350$10,000
47 (589.520004)EACH1$20,800$10,000
48 (589.520005)EACH1$20,800$10,000
49 (589.520006)EACH1$20,800$10,000
50 (589.520007)EACH1$20,800$10,000
51 (589.520008)EACH1$20,800$10,000
52 (589.520009)EACH1$20,800$10,000
53 (589.520010)EACH1$20,800$10,000
54 (589.520011)EACH1$20,800$10,000
55 (589.520012)EACH1$20,800$10,000
56 (589.520013)EACH1$20,800$10,000
57 (589.520014)EACH1$20,800$10,000
58 (589.520015)EACH1$20,800$10,000
59Box Beam Guide Railing (606.10)LF328$75.00$150.00
60Box Beam End Piece (606.120101)EACH1$1,000.00$7,500.00
61Box Beam Guide Railing End Assembly Type IIA (606.120201)EACH2$2,500.00$10,000
62Single-Slope Concrete Median Barrier (Precast) (606.3042)LF90$460.00$750.00
63Single-Slope Concrete Half Section Barrier (Precast) (606.3062)LF420$385.00$650.00
64Resetting Box Beam Guide Railing (606.53)LF996$50.00$150.00
65Resetting Box Beam Guide Rail Turned-Down Terminal (606.5920)EACH5$420.00$2,500.00
66Removing and Disposing Box Beam Guide Railing (606.73)LF502$16.25$15.00
67Removing and Disposing Box Beam Median Barrier (606.74)LF206$16.25$30.00
68Removing and Disposing Concrete Barrier-Half Section (606.7510)LF100$610.00$250.00
69Transition Between Box Beam Guide Rail and Single Slope Half Section Concrete Barrier (One or Two Way Operation) (606.8803)EACH3$17,000$25,000
70Transition Between Single Slope Half Section Concrete Barrier and Box Beam Guide Rail (One Way - Trailing End of Barrier) (606.8804)EACH3$18,500$25,000
71Transition Between Box Beam Median Barrier and Single Slope Concrete Median Barrier (606.8805)EACH1$28,000$25,000
72Transition between Half-Section and Full-Section Single Slope Concrete Barrier (Left Pocket) (606.9003)EACH1$12,500$25,000
73Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.000013)QUALITY UNIT1$120.00$120.00
74Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102)TON20$700.00$500.00
75Topsoil - Roadside (610.1402)CY70$110.00$100.00
76Turf Establishment - Roadside (610.1601)SY570$8.00$10.00
77Basic Work Zone Traffic Control (619.01)LS1$2,600,000$2,000,000
78Type III Construction Barricades (619.04)EACH54$200.00$250.00
79 (619.110513)EACH18$5,000.00$7,500.00
80Nighttime Operations (Entire Project) (619.24)LS1$490,000$350,000
81Traffic Control Supervisor (619.25)MONTH20$14,000$15,000
82Crushed Gravel (In-Place Measure) (623.11)CY22$300.00$250.00
83Survey Operations (625.01)LS1$200,000$250,000
84 (627.50140008)50$94.00$100.00
85Concrete Cylinder Curing Equipment (637.04)EACH1$5,000.00$2,500.00
86Engineer’s Field Office – Type 2 (637.12)MONTH20$13,500$7,500.00
87Office Technology and Supplies (637.34)DOL5,000$1.00$1.00
88Partnering Workshop (637.35)DOL5,000$1.00$1.00
89 (644.03120103)1$8,000.00$10,000
90 (644.03120203)1$8,000.00$10,000
91 (644.03120303)1$8,000.00$10,000
92 (644.03120403)1$8,000.00$10,000
93Anchor Bolts (644.11)LB16,847$8.00$20.00
94Drilled Shaft for Overhead Sign Structures (644.20)CY344$6,200.00$9,225.00
95 (644.410503)EACH1$50,000$75,000
96 (644.410605)EACH1$48,000$75,000
97 (644.420610)EACH2$63,000$100,000
98 (644.420715)EACH1$78,000$125,000
99 (644.420820)EACH2$74,000$125,000
100 (644.420830)EACH2$100,000$135,000
101 (644.420930)EACH2$107,000$140,000
102 (644.432560)EACH1$225,000$190,000
103 (644.433060)EACH3$180,000$200,000
104 (644.433090)EACH3$200,000$200,000
105 (644.433590)EACH1$180,000$250,000
106 (644.435090)EACH1$350,000$350,000
107 (644.4401)EACH1$120,000$150,000
108 (644.60000111)1$24,000$100,000
109 (644.60000211)1$28,900$100,000
110 (644.60000311)1$37,500$100,000
111 (644.60000411)1$28,900$100,000
112 (644.60000511)1$48,500$100,000
113 (644.60000611)1$49,000$100,000
114 (644.60000711)1$49,500$100,000
115 (644.60000811)1$30,000$100,000
116 (644.60000911)1$49,000$100,000
117 (644.60001011)1$24,000$100,000
118 (644.60001111)1$29,000$100,000
119 (644.60001211)1$29,000$100,000
120 (644.60001311)1$29,000$100,000
121 (644.60001411)1$49,000$100,000
122 (644.60001511)1$29,000$100,000
123Performance Concrete Quality Adjustment (644.99)QUALITY UNIT1$21.25$21.25
124 (645.34010104)1$115,000$200,000
125 (645.34010204)1$116,000$200,000
126 (645.34010304)1$295,000$200,000
127 (645.52020110)578$83.00$75.00
128 (645.52030110)2,497$85.00$75.00
129 (645.62000110)10,491$70.00$60.00
130Type A Sign Posts (645.81)EACH4$275.00$1,500.00
131 (645.81000111)10$2,550.00$2,500.00
132 (645.830202)EACH38$4,000.00$2,500.00
133 (645.830302)EACH2$4,300.00$3,500.00
134 (645.830402)EACH4$4,800.00$4,500.00
135 (645.830502)EACH8$5,300.00$4,500.00
136 (645.830702)EACH2$6,100.00$5,000.00
137Pole-Mounted Sign Support System (Band Mounting) (645.85)EACH7$160.00$150.00
138Removal of Cantilever Overhead Sign Panel(s), Structure, and Foundations (647.20)EACH15$19,000$15,000
139Removal of Single Span Overhead Sign Panel(s), Structure, and Foundations (647.21)EACH9$30,000$20,000
140Remove and Dispose Overhead Sign Panel, Sign Panel Assembly (647.25)EACH20$500.00$3,000.00
141 (647.25000004)14$630.00$2,500.00
142Remove and Store Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.41)EACH2$190.00$1,000.00
143Remove and Dispose Sign Panel, Sign Panel Assembly Size II (30-100 Square Feet) (647.52)EACH8$375.00$1,000.00
144Remove and Dispose Sign Panel, Sign Panel Assembly Size III (Over 100 Square Feet) (647.53)EACH7$375.00$3,000.00
145Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61)EACH4$190.00$500.00
146Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size II (30-100 Square Feet) (647.62)EACH2$190.00$500.00
147Remove and Dispose Type B Ground Mounted Sign Support and Foundation (647.65)EACH34$400.00$1,500.00
148 (670.03070008)3$2,450.00$2,000.00
149 (670.2002)LF130$50.00$60.00
150 (670.2003)LF90$58.00$70.00
151 (670.2004)LF930$78.00$120.00
152Pullboxes over 7 1/2 to 10 cubic feet, inside volume (Lighting) (670.3010)EACH14$5,000.00$3,000.00
153 (670.7002)LF1,700$12.85$12.00
154 (670.7003)LF140$10.25$10.00
155 (670.7004)LF470$9.00$10.00
156Ground Wire No. 6 AWG. (670.7501)LF70$9.00$10.00
157 (670.75060011)750$7.50$10.00
158 (675.99000023)25,000$1.00$1.00
159Concrete Base for Controller Cabinet (680.5002)EACH2$5,300.00$7,500.00
160Concrete Work Pad (5 feet x 5 feet x 4 inches) (680.5003)EACH4$7,000.00$2,500.00
161 (680.510501)EACH1$7,900.00$4,000.00
162 (680.51100010)11$1,400.00$500.00
163 (680.53000111)3$5,500.00$4,000.00
164 (680.93550011)1$3,700.00$3,500.00
165 (683.09150011)1$20,200$30,000
166 (683.09150111)3$18,750$17,500
167 (683.30220508)2$17,000$20,000
168 (683.30241508)5,000$1.00$1.00
169 (683.30241708)3,000$1.00$1.00
170 (683.80338108)2$26,500$40,000
171 (683.84600108)510$14.00$15.00
172 (683.91150208)2$22,700$22,500
173 (683.93510010)2$12,500$8,500.00
174 (683.96100305)2$11,750$7,500.00
175 (691.04000020)72,800$1.00$1.00
176Field Change Payment (FCP) (697.03)DOL502,500$1.00$1.00
177Asphalt Price Adjustment (698.04)DOL100$1.00$1.00
178Fuel Price Adjustment (698.05)DOL821$1.00$1.00
179Steel/Iron Price Adjustment (698.06)DOL100$1.00$1.00
180Mobilization (699.040001)LS1$620,000$760,000
NYSDOT contract D265624: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.

Every contract let that day: NYSDOT letting of March 26, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way