NYSDOT contract D265624 bid tabulation
Parkway Guide Sign and Sign Structure Replacement. Let by New York State DOT on March 26, 2026, Westchester, Region 08. 2 bids received; low bid $16,294,724 by Tully Construction Company Inc.
- Owner
- New York State DOT
- Letting
- 26 MAR 2026
- Pay items
- 180
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Tully Construction Company Inc | $16,294,724 | Low |
| 2 | Westmoreland Construction Inc | $20,222,222 | +24% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Tully Construction Company Inc | 2. Westmoreland Construction Inc |
|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.06) | LS | 1 | $36,000 | $99,592 |
| 2 | Unclassified Excavation and Disposal (203.02) | CY | 15 | $1,000.00 | $300.00 |
| 3 | Structure Excavation (206.01) | CY | 175 | $300.00 | $750.00 |
| 4 | Conduit Excavation and Backfill including Surface Restoration (206.03) | LF | 850 | $50.00 | $150.00 |
| 5 | (206.03050005) | 24 | $750.00 | $400.00 | |
| 6 | (206.03120010) | 320 | $55.00 | $100.00 | |
| 7 | (304.11000008) | 4 | $275.00 | $250.00 | |
| 8 | (502.94000018) | 151 | $25.00 | $50.00 | |
| 9 | Footing Concrete, Performance (555.0011) | CY | 17 | $2,110.00 | $7,500.00 |
| 10 | Concrete for Structures, Performance (555.0021) | CY | 210 | $1,170.00 | $5,000.00 |
| 11 | Performance Concrete Quality Adjustment – Footing Concrete (555.9901) | QUALITY UNIT | 1 | $15.00 | $15.00 |
| 12 | Performance Concrete Quality Adjustment – Concrete for Structures (555.9902) | QUALITY UNIT | 1 | $15.00 | $15.00 |
| 13 | Uncoated Bar Reinforcement for Concrete Structures (556.0201) | LB | 556 | $5.00 | $20.00 |
| 14 | Epoxy-Coated Bar Reinforcement for Structures (556.0202) | LB | 25,845 | $5.00 | $15.00 |
| 15 | Protective Sealing of New Structural Concrete (559.02) | SF | 1,396 | $7.00 | $3.00 |
| 16 | (560.70000008) | 13 | $200.00 | $1,000.00 | |
| 17 | (560.80010011) | 216 | $55.00 | $50.00 | |
| 18 | (564.700001) | EACH | 1 | $72,000 | $100,000 |
| 19 | (564.700002) | EACH | 1 | $21,000 | $150,000 |
| 20 | (564.700003) | EACH | 3 | $12,000 | $75,000 |
| 21 | Type E.B. Expansion Bearing (112 to 168 k) (565.2033) | EACH | 1 | $31,000 | $50,000 |
| 22 | (570.090001) | LS | 1 | $12,500 | $10,000 |
| 23 | (570.090002) | LS | 1 | $12,500 | $10,000 |
| 24 | (570.090003) | LS | 1 | $12,500 | $10,000 |
| 25 | (570.090004) | LS | 1 | $15,700 | $10,000 |
| 26 | (570.090005) | LS | 1 | $15,700 | $10,000 |
| 27 | (570.160001) | LS | 1 | $22,900 | $10,000 |
| 28 | (570.160002) | LS | 1 | $22,550 | $10,000 |
| 29 | (570.160003) | LS | 1 | $14,500 | $10,000 |
| 30 | Disposal of Hazardous Paint Removal Waste Containing Lead (571.03) | LB | 2,380 | $5.00 | $5.00 |
| 31 | (572.010001) | SF | 396 | $115.00 | $30.00 |
| 32 | (572.010002) | SF | 300 | $115.00 | $30.00 |
| 33 | (572.010003) | SF | 80 | $115.00 | $30.00 |
| 34 | (574.030001) | SF | 250 | $200.00 | $250.00 |
| 35 | (574.030002) | SF | 235 | $200.00 | $250.00 |
| 36 | (574.030003) | SF | 100 | $300.00 | $250.00 |
| 37 | Removal and Replacement of Structural Concrete (582.0051) | CY | 1 | $9,000.00 | $25,000 |
| 38 | (585.01) | EACH | 1 | $60,000 | $350,000 |
| 39 | Drilling and Grouting Bolts or Reinforcing Bars (586.0201) | EACH | 330 | $80.00 | $50.00 |
| 40 | Drilling and Grouting Bolts or Reinforcing Bars (with Non-Destructive Investigation) (586.0202) | EACH | 319 | $80.00 | $50.00 |
| 41 | Drilling and Grouting Bolts or Reinforcing Bars with Pullout Test (586.0301) | EACH | 118 | $80.00 | $600.00 |
| 42 | Drilling and Grouting Bolts or Reinforcing Bars with Pullout Test (with Non- Destructive Investigation) (586.0302) | EACH | 165 | $80.00 | $100.00 |
| 43 | Field Drill Holes in Existing Structural Steel (586.10) | EACH | 896 | $350.00 | $65.00 |
| 44 | (589.520001) | EACH | 2 | $20,600 | $10,000 |
| 45 | (589.520002) | EACH | 2 | $9,350.00 | $10,000 |
| 46 | (589.520003) | EACH | 2 | $13,350 | $10,000 |
| 47 | (589.520004) | EACH | 1 | $20,800 | $10,000 |
| 48 | (589.520005) | EACH | 1 | $20,800 | $10,000 |
| 49 | (589.520006) | EACH | 1 | $20,800 | $10,000 |
| 50 | (589.520007) | EACH | 1 | $20,800 | $10,000 |
| 51 | (589.520008) | EACH | 1 | $20,800 | $10,000 |
| 52 | (589.520009) | EACH | 1 | $20,800 | $10,000 |
| 53 | (589.520010) | EACH | 1 | $20,800 | $10,000 |
| 54 | (589.520011) | EACH | 1 | $20,800 | $10,000 |
| 55 | (589.520012) | EACH | 1 | $20,800 | $10,000 |
| 56 | (589.520013) | EACH | 1 | $20,800 | $10,000 |
| 57 | (589.520014) | EACH | 1 | $20,800 | $10,000 |
| 58 | (589.520015) | EACH | 1 | $20,800 | $10,000 |
| 59 | Box Beam Guide Railing (606.10) | LF | 328 | $75.00 | $150.00 |
| 60 | Box Beam End Piece (606.120101) | EACH | 1 | $1,000.00 | $7,500.00 |
| 61 | Box Beam Guide Railing End Assembly Type IIA (606.120201) | EACH | 2 | $2,500.00 | $10,000 |
| 62 | Single-Slope Concrete Median Barrier (Precast) (606.3042) | LF | 90 | $460.00 | $750.00 |
| 63 | Single-Slope Concrete Half Section Barrier (Precast) (606.3062) | LF | 420 | $385.00 | $650.00 |
| 64 | Resetting Box Beam Guide Railing (606.53) | LF | 996 | $50.00 | $150.00 |
| 65 | Resetting Box Beam Guide Rail Turned-Down Terminal (606.5920) | EACH | 5 | $420.00 | $2,500.00 |
| 66 | Removing and Disposing Box Beam Guide Railing (606.73) | LF | 502 | $16.25 | $15.00 |
| 67 | Removing and Disposing Box Beam Median Barrier (606.74) | LF | 206 | $16.25 | $30.00 |
| 68 | Removing and Disposing Concrete Barrier-Half Section (606.7510) | LF | 100 | $610.00 | $250.00 |
| 69 | Transition Between Box Beam Guide Rail and Single Slope Half Section Concrete Barrier (One or Two Way Operation) (606.8803) | EACH | 3 | $17,000 | $25,000 |
| 70 | Transition Between Single Slope Half Section Concrete Barrier and Box Beam Guide Rail (One Way - Trailing End of Barrier) (606.8804) | EACH | 3 | $18,500 | $25,000 |
| 71 | Transition Between Box Beam Median Barrier and Single Slope Concrete Median Barrier (606.8805) | EACH | 1 | $28,000 | $25,000 |
| 72 | Transition between Half-Section and Full-Section Single Slope Concrete Barrier (Left Pocket) (606.9003) | EACH | 1 | $12,500 | $25,000 |
| 73 | Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.000013) | QUALITY UNIT | 1 | $120.00 | $120.00 |
| 74 | Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102) | TON | 20 | $700.00 | $500.00 |
| 75 | Topsoil - Roadside (610.1402) | CY | 70 | $110.00 | $100.00 |
| 76 | Turf Establishment - Roadside (610.1601) | SY | 570 | $8.00 | $10.00 |
| 77 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $2,600,000 | $2,000,000 |
| 78 | Type III Construction Barricades (619.04) | EACH | 54 | $200.00 | $250.00 |
| 79 | (619.110513) | EACH | 18 | $5,000.00 | $7,500.00 |
| 80 | Nighttime Operations (Entire Project) (619.24) | LS | 1 | $490,000 | $350,000 |
| 81 | Traffic Control Supervisor (619.25) | MONTH | 20 | $14,000 | $15,000 |
| 82 | Crushed Gravel (In-Place Measure) (623.11) | CY | 22 | $300.00 | $250.00 |
| 83 | Survey Operations (625.01) | LS | 1 | $200,000 | $250,000 |
| 84 | (627.50140008) | 50 | $94.00 | $100.00 | |
| 85 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $5,000.00 | $2,500.00 |
| 86 | Engineer’s Field Office – Type 2 (637.12) | MONTH | 20 | $13,500 | $7,500.00 |
| 87 | Office Technology and Supplies (637.34) | DOL | 5,000 | $1.00 | $1.00 |
| 88 | Partnering Workshop (637.35) | DOL | 5,000 | $1.00 | $1.00 |
| 89 | (644.03120103) | 1 | $8,000.00 | $10,000 | |
| 90 | (644.03120203) | 1 | $8,000.00 | $10,000 | |
| 91 | (644.03120303) | 1 | $8,000.00 | $10,000 | |
| 92 | (644.03120403) | 1 | $8,000.00 | $10,000 | |
| 93 | Anchor Bolts (644.11) | LB | 16,847 | $8.00 | $20.00 |
| 94 | Drilled Shaft for Overhead Sign Structures (644.20) | CY | 344 | $6,200.00 | $9,225.00 |
| 95 | (644.410503) | EACH | 1 | $50,000 | $75,000 |
| 96 | (644.410605) | EACH | 1 | $48,000 | $75,000 |
| 97 | (644.420610) | EACH | 2 | $63,000 | $100,000 |
| 98 | (644.420715) | EACH | 1 | $78,000 | $125,000 |
| 99 | (644.420820) | EACH | 2 | $74,000 | $125,000 |
| 100 | (644.420830) | EACH | 2 | $100,000 | $135,000 |
| 101 | (644.420930) | EACH | 2 | $107,000 | $140,000 |
| 102 | (644.432560) | EACH | 1 | $225,000 | $190,000 |
| 103 | (644.433060) | EACH | 3 | $180,000 | $200,000 |
| 104 | (644.433090) | EACH | 3 | $200,000 | $200,000 |
| 105 | (644.433590) | EACH | 1 | $180,000 | $250,000 |
| 106 | (644.435090) | EACH | 1 | $350,000 | $350,000 |
| 107 | (644.4401) | EACH | 1 | $120,000 | $150,000 |
| 108 | (644.60000111) | 1 | $24,000 | $100,000 | |
| 109 | (644.60000211) | 1 | $28,900 | $100,000 | |
| 110 | (644.60000311) | 1 | $37,500 | $100,000 | |
| 111 | (644.60000411) | 1 | $28,900 | $100,000 | |
| 112 | (644.60000511) | 1 | $48,500 | $100,000 | |
| 113 | (644.60000611) | 1 | $49,000 | $100,000 | |
| 114 | (644.60000711) | 1 | $49,500 | $100,000 | |
| 115 | (644.60000811) | 1 | $30,000 | $100,000 | |
| 116 | (644.60000911) | 1 | $49,000 | $100,000 | |
| 117 | (644.60001011) | 1 | $24,000 | $100,000 | |
| 118 | (644.60001111) | 1 | $29,000 | $100,000 | |
| 119 | (644.60001211) | 1 | $29,000 | $100,000 | |
| 120 | (644.60001311) | 1 | $29,000 | $100,000 | |
| 121 | (644.60001411) | 1 | $49,000 | $100,000 | |
| 122 | (644.60001511) | 1 | $29,000 | $100,000 | |
| 123 | Performance Concrete Quality Adjustment (644.99) | QUALITY UNIT | 1 | $21.25 | $21.25 |
| 124 | (645.34010104) | 1 | $115,000 | $200,000 | |
| 125 | (645.34010204) | 1 | $116,000 | $200,000 | |
| 126 | (645.34010304) | 1 | $295,000 | $200,000 | |
| 127 | (645.52020110) | 578 | $83.00 | $75.00 | |
| 128 | (645.52030110) | 2,497 | $85.00 | $75.00 | |
| 129 | (645.62000110) | 10,491 | $70.00 | $60.00 | |
| 130 | Type A Sign Posts (645.81) | EACH | 4 | $275.00 | $1,500.00 |
| 131 | (645.81000111) | 10 | $2,550.00 | $2,500.00 | |
| 132 | (645.830202) | EACH | 38 | $4,000.00 | $2,500.00 |
| 133 | (645.830302) | EACH | 2 | $4,300.00 | $3,500.00 |
| 134 | (645.830402) | EACH | 4 | $4,800.00 | $4,500.00 |
| 135 | (645.830502) | EACH | 8 | $5,300.00 | $4,500.00 |
| 136 | (645.830702) | EACH | 2 | $6,100.00 | $5,000.00 |
| 137 | Pole-Mounted Sign Support System (Band Mounting) (645.85) | EACH | 7 | $160.00 | $150.00 |
| 138 | Removal of Cantilever Overhead Sign Panel(s), Structure, and Foundations (647.20) | EACH | 15 | $19,000 | $15,000 |
| 139 | Removal of Single Span Overhead Sign Panel(s), Structure, and Foundations (647.21) | EACH | 9 | $30,000 | $20,000 |
| 140 | Remove and Dispose Overhead Sign Panel, Sign Panel Assembly (647.25) | EACH | 20 | $500.00 | $3,000.00 |
| 141 | (647.25000004) | 14 | $630.00 | $2,500.00 | |
| 142 | Remove and Store Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.41) | EACH | 2 | $190.00 | $1,000.00 |
| 143 | Remove and Dispose Sign Panel, Sign Panel Assembly Size II (30-100 Square Feet) (647.52) | EACH | 8 | $375.00 | $1,000.00 |
| 144 | Remove and Dispose Sign Panel, Sign Panel Assembly Size III (Over 100 Square Feet) (647.53) | EACH | 7 | $375.00 | $3,000.00 |
| 145 | Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61) | EACH | 4 | $190.00 | $500.00 |
| 146 | Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size II (30-100 Square Feet) (647.62) | EACH | 2 | $190.00 | $500.00 |
| 147 | Remove and Dispose Type B Ground Mounted Sign Support and Foundation (647.65) | EACH | 34 | $400.00 | $1,500.00 |
| 148 | (670.03070008) | 3 | $2,450.00 | $2,000.00 | |
| 149 | (670.2002) | LF | 130 | $50.00 | $60.00 |
| 150 | (670.2003) | LF | 90 | $58.00 | $70.00 |
| 151 | (670.2004) | LF | 930 | $78.00 | $120.00 |
| 152 | Pullboxes over 7 1/2 to 10 cubic feet, inside volume (Lighting) (670.3010) | EACH | 14 | $5,000.00 | $3,000.00 |
| 153 | (670.7002) | LF | 1,700 | $12.85 | $12.00 |
| 154 | (670.7003) | LF | 140 | $10.25 | $10.00 |
| 155 | (670.7004) | LF | 470 | $9.00 | $10.00 |
| 156 | Ground Wire No. 6 AWG. (670.7501) | LF | 70 | $9.00 | $10.00 |
| 157 | (670.75060011) | 750 | $7.50 | $10.00 | |
| 158 | (675.99000023) | 25,000 | $1.00 | $1.00 | |
| 159 | Concrete Base for Controller Cabinet (680.5002) | EACH | 2 | $5,300.00 | $7,500.00 |
| 160 | Concrete Work Pad (5 feet x 5 feet x 4 inches) (680.5003) | EACH | 4 | $7,000.00 | $2,500.00 |
| 161 | (680.510501) | EACH | 1 | $7,900.00 | $4,000.00 |
| 162 | (680.51100010) | 11 | $1,400.00 | $500.00 | |
| 163 | (680.53000111) | 3 | $5,500.00 | $4,000.00 | |
| 164 | (680.93550011) | 1 | $3,700.00 | $3,500.00 | |
| 165 | (683.09150011) | 1 | $20,200 | $30,000 | |
| 166 | (683.09150111) | 3 | $18,750 | $17,500 | |
| 167 | (683.30220508) | 2 | $17,000 | $20,000 | |
| 168 | (683.30241508) | 5,000 | $1.00 | $1.00 | |
| 169 | (683.30241708) | 3,000 | $1.00 | $1.00 | |
| 170 | (683.80338108) | 2 | $26,500 | $40,000 | |
| 171 | (683.84600108) | 510 | $14.00 | $15.00 | |
| 172 | (683.91150208) | 2 | $22,700 | $22,500 | |
| 173 | (683.93510010) | 2 | $12,500 | $8,500.00 | |
| 174 | (683.96100305) | 2 | $11,750 | $7,500.00 | |
| 175 | (691.04000020) | 72,800 | $1.00 | $1.00 | |
| 176 | Field Change Payment (FCP) (697.03) | DOL | 502,500 | $1.00 | $1.00 |
| 177 | Asphalt Price Adjustment (698.04) | DOL | 100 | $1.00 | $1.00 |
| 178 | Fuel Price Adjustment (698.05) | DOL | 821 | $1.00 | $1.00 |
| 179 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 |
| 180 | Mobilization (699.040001) | LS | 1 | $620,000 | $760,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of March 26, 2026. Compiled by Mirage Metrics.