NYSDOT contract D265811 bid tabulation
BRIDGE PAINTING & MINOR STEEL REPAIRS ROBERT MOSES CAUSEWAY. Let by New York State DOT on September 17, 2026, Suffolk, Region 10. 5 bids received; low bid $53,355,050 by Ahern Painting Contractors Inc.
- Owner
- New York State DOT
- Letting
- 17 SEP 2026
- Pay items
- 45
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Ahern Painting Contractors Inc | $53,355,050 | Low |
| 2 | Liberty Maintenance Inc | $53,499,261 | 0.0% |
| 3 | Cac Industries-Nuco Painting, JV | $54,753,000 | +3.0% |
| 4 | Atlas Painting & Sheeting Corporation | $62,899,000 | +18% |
| 5 | Champion Painting Specialty Services Corp | $98,540,969 | +85% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Ahern Painting Contractors Inc | 2. Liberty Maintenance Inc | 3. Cac Industries-Nuco Painting, JV | 4. Atlas Painting & Sheeting Corporation | 5. Champion Painting Specialty Services Corp |
|---|---|---|---|---|---|---|---|---|
| 1 | (564.100001) | LB | 12,670 | $67.00 | $32.89 | $59.40 | $60.00 | $68.30 |
| 2 | (564.21010011) | 700 | $50.00 | $234.44 | $99.00 | $100.00 | $250.00 | |
| 3 | (564.510001) | LB | 850 | $50.00 | $27.27 | $54.00 | $100.00 | $67.00 |
| 4 | (564.510002) | LB | 13,900 | $29.00 | $14.83 | $36.00 | $60.00 | $48.10 |
| 5 | (564.75000001) | 23 | $4,200.00 | $1,958.65 | $5,850.00 | $500.00 | $7,464.00 | |
| 6 | Lead-Exposure Control Plan (570.01) | LS | 1 | $20,000 | $11,741 | $4,950.00 | $75,000 | $15,000 |
| 7 | Medical Testing (570.02) | DOL | 144,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 8 | Personal-Exposure-Monitoring Sample Analysis (570.03) | DOL | 119,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 9 | Decontamination Facilities (570.04) | CALENDAR WEEK | 164 | $100.00 | $360.83 | $693.00 | $30.00 | $2,500.00 |
| 10 | (570.100001) | LS | 1 | $500,000 | $17,612 | $3,420,000 | $25,000 | $11,674,471 |
| 11 | (570.100002) | LS | 1 | $500,000 | $17,612 | $10,114,146 | $25,000 | $20,754,615 |
| 12 | (570.150001) | LS | 1 | $8,000,000 | $7,063,051 | $2,412,000 | $8,000,000 | $6,994,683 |
| 13 | (570.150002) | LS | 1 | $13,650,000 | $16,037,882 | $4,770,000 | $11,464,880 | $12,442,769 |
| 14 | (570.160001) | LS | 1 | $50,000 | $56,861 | $180,000 | $200,000 | $10,000 |
| 15 | (570.160002) | LS | 1 | $10,000 | $56,861 | $4,500.00 | $50,000 | $10,000 |
| 16 | Disposal of Hazardous Paint Removal Waste Containing Lead (571.03) | LB | 425,000 | $0.10 | $0.38 | $1.35 | $0.05 | $0.45 |
| 17 | Disposal of Non-Hazardous Industrial Solid Paint Removal Waste (571.04) | LB | 425,000 | $0.10 | $0.38 | $0.45 | $0.05 | $0.27 |
| 18 | (573.010001) | LS | 1 | $8,000,000 | $8,776,337 | $9,603,000 | $13,900,000 | $10,507,024 |
| 19 | (573.010002) | LS | 1 | $13,560,000 | $13,909,172 | $13,410,000 | $20,000,000 | $18,679,154 |
| 20 | (574.030001) | SF | 1,240 | $60.00 | $177.72 | $567.00 | $225.00 | $300.00 |
| 21 | (574.030002) | SF | 30 | $60.00 | $177.74 | $2,043.00 | $300.00 | $500.00 |
| 22 | Removal of Rivets-Replacement with High Strength Bolts (586.05) | EACH | 260 | $150.00 | $455.30 | $108.00 | $250.00 | $139.15 |
| 23 | Field Drill Holes in Existing Structural Steel (586.10) | EACH | 2,790 | $80.00 | $176.43 | $63.00 | $50.00 | $76.00 |
| 24 | (589.010001) | LB | 12,690 | $28.00 | $28.91 | $21.60 | $20.00 | $27.83 |
| 25 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $1,650,000 | $514,273 | $1,053,000 | $1,900,800 | $2,372,800 |
| 26 | (619.10050020) | 2,640 | $5.00 | $35.22 | $18.00 | $5.00 | $20.00 | |
| 27 | (619.110543) | EACH | 4 | $15,000 | $23,483 | $36,000 | $10,000 | $35,000 |
| 28 | Nighttime Operations (Entire Project) (619.24) | LS | 1 | $50,000 | $58,707 | $207,000 | $50,000 | $485,815 |
| 29 | Survey Operations (625.01) | LS | 1 | $10,000 | $17,612 | $18,000 | $5,000.00 | $75,000 |
| 30 | (634.97100011) | 80,900 | $10.00 | $0.01 | $13.50 | $3.00 | $28.00 | |
| 31 | (634.98010011) | 80,900 | $0.60 | $0.01 | $3.60 | $1.00 | $21.00 | |
| 32 | Engineer’s Field Office – Type 4 (637.14) | MONTH | 33 | $10,000 | $5,577.14 | $18,000 | $3,000.00 | $17,825 |
| 33 | Inspection Boat - Type B (637.33) | MONTH | 22 | $25,000 | $33,623 | $9,000.00 | $20,000 | $47,564 |
| 34 | Office Technology and Supplies (637.34) | DOL | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 35 | Partnering Workshop (637.35) | DOL | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 36 | Construction Testing supplies – Consumables (637.36) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 37 | (637.41000115) | 33 | $300.00 | $410.95 | $90.00 | $300.00 | $150.00 | |
| 38 | (639.21010011) | LS | 1 | $75,000 | $75,000 | $75,600 | $75,000 | $90,000 |
| 39 | (691.04000020) | 184,800 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | |
| 40 | (695.33110105) | LS | 1 | $50,000 | $59,947 | $234,000 | $20,000 | $10,000 |
| 41 | Field Change Payment (FCP) (697.03) | DOL | 770,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 42 | Asphalt Price Adjustment (698.04) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 43 | Fuel Price Adjustment (698.05) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 44 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 45 | Mobilization (699.040001) | LS | 1 | $1,960,000 | $2,031,996 | $2,025,000 | $2,400,000 | $3,753,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of September 17, 2026. Compiled by Mirage Metrics.