NYSDOT contract D265426 bid tabulation
BRIDGE DECK REHAB/PAINTING - NY Rt. 951A. Let by New York State DOT on March 27, 2025, Niagara, Region 05. 2 bids received; low bid $13,159,250 by Cold Spring Construction Company.
- Owner
- New York State DOT
- Letting
- 27 MAR 2025
- Pay items
- 112
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Cold Spring Construction Company | $13,159,250 | Low |
| 2 | Oakgrove Construction Inc | $13,796,578 | +5.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Cold Spring Construction Company | 2. Oakgrove Construction Inc |
|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.06) | LS | 1 | $2,500.00 | $5,000.00 |
| 2 | Removal of Steel Supported Structural Slabs (with shear connectors) – Type B (202.2202) | SF | 55,696 | $12.00 | $13.00 |
| 3 | Unclassified Excavation and Disposal (203.02) | CY | 437 | $45.00 | $30.00 |
| 4 | Embankment In Place (203.03) | CY | 5 | $90.00 | $100.00 |
| 5 | (203.24010017) | 65 | $60.00 | $100.00 | |
| 6 | Seed and Mulch – Temporary (209.1003) | SY | 461 | $0.50 | $1.00 |
| 7 | Removal and Disposal of Bond Breaker/Filler ACM (BV14) (210.3312) | SF | 288 | $40.00 | $70.00 |
| 8 | Subbase Course, Optional Type (304.15) | CY | 110 | $150.00 | $100.00 |
| 9 | (404.0189) | TON | 225.74 | $150.00 | $150.00 |
| 10 | (404.0982) | TON | 451.49 | $150.00 | $125.00 |
| 11 | Diluted Tack Coat (407.0102) | GAL | 669 | $10.00 | $6.00 |
| 12 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 5,020 | $1.00 | $0.25 |
| 13 | Miscellaneous Cold Milling of Bituminous Concrete (490.30) | SY | 5,578 | $4.00 | $5.00 |
| 14 | Concrete for Structures, Performance (555.0021) | CY | 70.30 | $3,000.00 | $3,500.00 |
| 15 | (555.80010001) | 185 | $175.00 | $150.00 | |
| 16 | Performance Concrete Quality Adjustment – Concrete for Structures (555.9902) | QUALITY UNIT | 1 | $14.00 | $14.00 |
| 17 | Epoxy-Coated Bar Reinforcement for Structures (556.0202) | LB | 15,568 | $4.00 | $3.00 |
| 18 | Stainless Steel Bar Reinforcement for Structures (556.0205) | LB | 440 | $8.00 | $10.00 |
| 19 | Stud Shear Connectors for Bridges (556.03) | EACH | 20,356 | $5.50 | $8.00 |
| 20 | (557.1012) | SY | 793 | $350.00 | $350.00 |
| 21 | (557.1112) | SY | 4,856 | $600.00 | $650.00 |
| 22 | Winter Surface Treatment – Superstructure Slabs and Structural Approach Slabs (557.29) | SY | 5,607.50 | $0.01 | $0.01 |
| 23 | Performance Concrete Quality Adjustment – Superstructure and Approach Slab (557.9901) | QUALITY UNIT | 1 | $12.72 | $12.72 |
| 24 | Longitudinal Sawcut Grooving of Structural Slab Surface (558.02) | SY | 5,247.50 | $6.00 | $5.00 |
| 25 | Protective Sealing of Structural Concrete on New Bridge Decks and Bridge Deck Overlays (559.01) | SF | 56,572 | $0.50 | $1.00 |
| 26 | Protective Sealing of Concrete with Coating Type Protective Sealer (559.04) | SQUAREFOOT | 19,185 | $2.50 | $5.00 |
| 27 | (564.11000010) | 200 | $550.00 | $1.00 | |
| 28 | (564.510001) | LB | 4,895 | $24.00 | $23.00 |
| 29 | (564.510002) | LB | 4,895 | $24.00 | $23.00 |
| 30 | (564.510003) | LB | 4,124 | $15.00 | $13.00 |
| 31 | (564.510004) | LB | 17,218 | $7.00 | $6.00 |
| 32 | (564.510005) | LB | 35,290 | $8.00 | $7.00 |
| 33 | Type E.B. Fixed Bearing (112 to 168 k) (565.2023) | EACH | 14 | $2,500.00 | $2,500.00 |
| 34 | Type E.B. Fixed Bearing (Over 225 k) (565.2025) | EACH | 14 | $3,500.00 | $3,000.00 |
| 35 | (565.20310003) | 14 | $7,000.00 | $7,000.00 | |
| 36 | Type E.B. Expansion Bearing (112 to 168 k) (565.2033) | EACH | 28 | $2,500.00 | $2,500.00 |
| 37 | Type E.B. Expansion Bearing (Over 225 k) (565.2035) | EACH | 14 | $3,500.00 | $3,000.00 |
| 38 | Modular Expansion Joint System - Two Cell (566.02) | LF | 128 | $1,850.00 | $2,200.00 |
| 39 | Armorless Bridge Joint (567.60) | LF | 256 | $220.00 | $175.00 |
| 40 | Single Slope (Half-Section) Concrete Bridge Barrier (569.04) | LF | 2,086 | $270.00 | $250.00 |
| 41 | Performance Concrete Quality Adjustment–Cast-In-Place Concrete Barrier (569.99) | QUALITY UNIT | 1 | $12.40 | $12.40 |
| 42 | Lead-Exposure Control Plan (570.01) | LS | 1 | $2,500.00 | $2,500.00 |
| 43 | Medical Testing (570.02) | DOL | 1,950 | $1.00 | $1.00 |
| 44 | Personal-Exposure-Monitoring Sample Analysis (570.03) | DOL | 6,750 | $1.00 | $1.00 |
| 45 | Decontamination Facilities (570.04) | CALENDAR WEEK | 20 | $25.00 | $25.00 |
| 46 | (570.150001) | LS | 1 | $500,000 | $200,000 |
| 47 | Disposal of Hazardous Paint Removal Waste Containing Lead (571.03) | LB | 61,555 | $0.75 | $0.75 |
| 48 | (573.010001) | LS | 1 | $2,175,000 | $2,100,000 |
| 49 | Scuppers (Type A) (576.01) | EACH | 8 | $3,000.00 | $3,000.00 |
| 50 | Downspout System (PVC) (576.21) | LF | 496 | $160.00 | $100.00 |
| 51 | Removal of Structural Concrete (580.01) | CY | 50 | $3,500.00 | $3,600.00 |
| 52 | Removal of Concrete Approach Slab (580.04) | SF | 10,400 | $7.00 | $5.00 |
| 53 | Removal and Replacement of Structural Concrete (582.0051) | CY | 1 | $12,000 | $15,000 |
| 54 | (582.99) | 1 | $100.00 | $100.00 | |
| 55 | (582.99000016) | 331 | $35.00 | $29.99 | |
| 56 | Removal of Structural Concrete - Replacement with Shotcrete, No Reinforcement Bar Encasement (583.02) | SF | 538 | $250.00 | $200.00 |
| 57 | Removal of Structural Concrete - Replacement with Shotcrete, with Reinforcement Bar Encasement (583.03) | SF | 137 | $250.00 | $250.00 |
| 58 | (585.01) | EACH | 28 | $5,000.00 | $3,000.00 |
| 59 | (585.02) | EACH | 56 | $5,000.00 | $3,000.00 |
| 60 | Drilling and Grouting Bolts or Reinforcing Bars (586.0201) | EACH | 1,179 | $75.00 | $50.00 |
| 61 | Drilling and Grouting Bolts or Reinforcing Bars with Pullout Test (586.0301) | EACH | 280 | $100.00 | $70.00 |
| 62 | Field Drill Holes in Existing Structural Steel (586.10) | EACH | 10,456 | $30.00 | $30.00 |
| 63 | Bridge Railing Removal and Disposal (587.01) | LF | 1,415 | $25.00 | $25.00 |
| 64 | (589.010001) | LB | 44,100 | $1.00 | $1.00 |
| 65 | (589.010002) | LB | 576,842 | $0.05 | $0.10 |
| 66 | (589.010003) | LB | 14,758 | $1.00 | $0.75 |
| 67 | (589.010004) | LB | 5,926 | $7.00 | $6.00 |
| 68 | (589.010005) | LB | 3,864 | $7.00 | $6.00 |
| 69 | Box Beam Guide Railing (606.10) | LF | 509 | $55.00 | $55.00 |
| 70 | Box Beam Guide Railing (Shop Bent or Shop Mitered) (606.100002) | LF | 173 | $55.00 | $55.00 |
| 71 | Box Beam Guide Railing End Assembly Type IIA (606.120201) | EACH | 2 | $3,000.00 | $2,500.00 |
| 72 | Removing and Storing Precast Concrete Barrier (606.65) | LF | 943 | $20.00 | $10.00 |
| 73 | Removing and Disposing Box Beam Guide Railing (606.73) | LF | 780 | $10.00 | $5.00 |
| 74 | Transition from Box Beam Guide Rail to Full-Section Single-Slope Concrete Barrier (One- or Two-Way Operation) (606.8806) | EACH | 8 | $8,000.00 | $10,000 |
| 75 | (607.0512) | LF | 25 | $90.00 | $100.00 |
| 76 | (607.06410016) | 320 | $100.00 | $100.00 | |
| 77 | Stone Curb – Bridge (Type F1) (609.0302) | LF | 480 | $80.00 | $50.00 |
| 78 | (609.06000008) | 2,003 | $6.00 | $4.00 | |
| 79 | Topsoil - Roadside (610.1402) | CY | 51 | $75.00 | $75.00 |
| 80 | Turf Establishment - Roadside (610.1601) | SY | 461 | $2.50 | $4.00 |
| 81 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $350,000 | $1,495,000 |
| 82 | Type III Construction Barricades (619.04) | EACH | 33 | $100.00 | $125.00 |
| 83 | Cover Existing Pavement Marking Stripes (Removable Tape) (619.0803) | LF | 400 | $8.00 | $8.00 |
| 84 | (619.100103) | LF | 100 | $10.00 | $10.00 |
| 85 | (619.111113) | EACH | 8 | $8,000.00 | $7,500.00 |
| 86 | (619.1301) | EACH | 1 | $60,000 | $45,000 |
| 87 | Temporary Positive Barrier – Category 3 (Pinning Prohibited) (619.1713) | LF | 96 | $50.00 | $25.00 |
| 88 | Stone Filling (Light) (620.03) | CY | 24 | $150.00 | $200.00 |
| 89 | Bedding Material, Type 2 (620.0802) | CY | 25 | $125.00 | $150.00 |
| 90 | Concrete Block Slope Paving (620.09) | SY | 348 | $500.00 | $300.00 |
| 91 | (620.09000005) | 33 | $200.00 | $300.00 | |
| 92 | Survey Operations (625.01) | LS | 1 | $50,000 | $50,000 |
| 93 | (625.09010015) | LS | 1 | $500.00 | $1,000.00 |
| 94 | (627.50140008) | 308 | $5.00 | $6.00 | |
| 95 | Removal and Repair of Loose, Broken, or Spalled PCC Pavement (633.15) | SY | 10 | $300.00 | $150.00 |
| 96 | Concrete Cylinder Curing Equipment (637.04) | EACH | 2 | $150.00 | $2,000.00 |
| 97 | Engineer’s Field Office – Type 2 (637.12) | MONTH | 20 | $3,000.00 | $2,000.00 |
| 98 | Office Technology and Supplies (637.34) | DOL | 500 | $1.00 | $1.00 |
| 99 | Partnering Workshop (637.35) | DOL | 5,000 | $1.00 | $1.00 |
| 100 | Construction Testing supplies – Consumables (637.36) | DOL | 100 | $1.00 | $1.00 |
| 101 | Remove and Store Impact Attenuator (654.0702) | EACH | 2 | $2,000.00 | $1,500.00 |
| 102 | (680.77020010) | LS | 1 | $10,500 | $1,000.00 |
| 103 | White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102) | LF | 4,591 | $1.00 | $2.00 |
| 104 | Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202) | LF | 2,047 | $1.00 | $2.00 |
| 105 | White Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3104) | LF | 220 | $3.00 | $10.00 |
| 106 | (691.04000020) | 60,000 | $1.00 | $1.00 | |
| 107 | Field Change Payment (FCP) (697.03) | DOL | 630,622.11 | $1.00 | $1.00 |
| 108 | Asphalt Price Adjustment (698.04) | DOL | 100 | $1.00 | $1.00 |
| 109 | Fuel Price Adjustment (698.05) | DOL | 208 | $1.00 | $1.00 |
| 110 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 |
| 111 | (698.93940008) | LS | 1 | $60,000 | $60,000 |
| 112 | Mobilization (699.040001) | LS | 1 | $504,136 | $530,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of March 27, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.