NYSDOT contract D265610 bid tabulation
BRIDGE REHABILITATION; 3 BINs on I-990, Town of Amherst. Let by New York State DOT on December 18, 2025, Erie, Region 05. 2 bids received; low bid $8,667,991 by Oakgrove Construction Inc.
- Owner
- New York State DOT
- Letting
- 18 DEC 2025
- Pay items
- 117
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Oakgrove Construction Inc | $8,667,991 | Low |
| 2 | Concrete Applied Technologies Corp/DBA:Catco | $10,843,873 | +25% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Oakgrove Construction Inc | 2. Concrete Applied Technologies Corp/DBA:Catco |
|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.06) | LS | 1 | $5,000.00 | $8,000.00 |
| 2 | Removal of Steel Supported Structural Slabs (with shear connectors) – Type B (202.2202) | SF | 27,845 | $12.00 | $22.00 |
| 3 | Unclassified Excavation and Disposal (203.02) | CY | 17,638 | $22.00 | $27.00 |
| 4 | Embankment In Place (203.03) | CY | 13,817 | $8.00 | $25.00 |
| 5 | Select Structural Fill (203.21) | CY | 82 | $100.00 | $105.00 |
| 6 | Structure Excavation (206.01) | CY | 249 | $50.00 | $100.00 |
| 7 | Trench and Culvert Excavation (206.0201) | CY | 15 | $85.00 | $70.00 |
| 8 | Seed and Mulch – Temporary (209.1003) | SY | 23,099 | $0.50 | $0.01 |
| 9 | (209.23010009) | 4,981 | $4.00 | $0.10 | |
| 10 | (304.15010005) | 2,654 | $60.00 | $70.00 | |
| 11 | (404.0001) | TON | 104 | $100.00 | $100.00 |
| 12 | (404.0982) | TON | 665 | $150.00 | $180.00 |
| 13 | (404.1989) | TON | 1,146 | $130.00 | $120.00 |
| 14 | (404.3789) | TON | 275 | $130.00 | $130.00 |
| 15 | Diluted Tack Coat (407.0102) | GAL | 520 | $12.00 | $10.00 |
| 16 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 260 | $1.00 | $2.00 |
| 17 | Miscellaneous Cold Milling of Bituminous Concrete (490.30) | SY | 1,683 | $12.00 | $15.00 |
| 18 | Concrete for Structures, Performance (555.0021) | CY | 100 | $2,000.00 | $3,600.00 |
| 19 | Performance Concrete Quality Adjustment – Concrete for Structures (555.9902) | QUALITY UNIT | 3 | $4.58 | $4.58 |
| 20 | Epoxy-Coated Bar Reinforcement for Structures (556.0202) | LB | 10,967 | $3.00 | $3.30 |
| 21 | Stud Shear Connectors for Bridges (556.03) | EACH | 17,637 | $6.00 | $4.80 |
| 22 | (557.1013) | SY | 119 | $500.00 | $6.50 |
| 23 | (557.1019) | SY | 618 | $450.00 | $550.00 |
| 24 | (557.1113) | SY | 1,362 | $600.00 | $730.00 |
| 25 | (557.1119) | SY | 1,740 | $425.00 | $625.00 |
| 26 | Winter Surface Treatment – Superstructure Slabs and Structural Approach Slabs (557.29) | SY | 3,840 | $0.01 | $0.01 |
| 27 | Performance Concrete Quality Adjustment – Superstructure and Approach Slab (557.9901) | QUALITY UNIT | 3 | $16.59 | $16.59 |
| 28 | Longitudinal Sawcut Grooving of Structural Slab Surface (558.02) | SY | 3,522 | $6.00 | $6.80 |
| 29 | Protective Sealing of Structural Concrete on New Bridge Decks and Bridge Deck Overlays (559.01) | SF | 31,704 | $1.00 | $1.30 |
| 30 | Protective Sealing of New Structural Concrete (559.02) | SF | 7,160 | $2.00 | $2.00 |
| 31 | Protective Sealing of Concrete with Coating Type Protective Sealer (559.04) | SQUAREFOOT | 7,788 | $2.50 | $3.50 |
| 32 | (564.11000010) | 1 | $3,000.00 | $2,900.00 | |
| 33 | (564.510002) | LB | 21,187 | $10.00 | $10.00 |
| 34 | (564.510003) | LB | 409 | $40.00 | $38.00 |
| 35 | Type M.R. Expansion Bearing (226 to 450 k) (565.1522) | EACH | 6 | $5,500.00 | $4,300.00 |
| 36 | Type M.R. Expansion Bearing (676 to 900 k) (565.1524) | EACH | 3 | $7,500.00 | $9,400.00 |
| 37 | Type M.R. Fixed Bearing (676 to 900 k) (565.1724) | EACH | 3 | $6,000.00 | $7,300.00 |
| 38 | Type E.B. Fixed Bearing (Over 225 k) (565.2025) | EACH | 11 | $3,000.00 | $3,100.00 |
| 39 | Type E.B. Expansion Bearing (Over 225 k) (565.2035) | EACH | 11 | $3,000.00 | $3,000.00 |
| 40 | Modular Expansion Joint System - Two Cell (566.02) | LF | 36 | $2,500.00 | $2,600.00 |
| 41 | Bridge Joint Header (567.62) | CF | 68 | $325.00 | $450.00 |
| 42 | Bridge Joint Seal (567.63) | LF | 132 | $70.00 | $70.00 |
| 43 | Performance Concrete Quality Adjustment (567.99) | QUALITY UNIT | 1 | $40.54 | $40.54 |
| 44 | Transition Bridge Railing (568.70) | LF | 480 | $200.00 | $210.00 |
| 45 | Single Slope (Half-Section) Concrete Bridge Barrier (569.04) | LF | 1,630 | $250.00 | $400.00 |
| 46 | Performance Concrete Quality Adjustment–Cast-In-Place Concrete Barrier (569.99) | QUALITY UNIT | 3 | $3.97 | $3.97 |
| 47 | (570.150001) | LS | 1 | $60,000 | $198,000 |
| 48 | (570.150002) | LS | 1 | $30,000 | $55,600 |
| 49 | (570.150003) | LS | 1 | $30,000 | $59,600 |
| 50 | Disposal of Non-Hazardous Industrial Solid Paint Removal Waste (571.04) | LB | 16,800 | $0.10 | $2.40 |
| 51 | (573.010001) | LS | 1 | $150,000 | $238,000 |
| 52 | (573.010002) | LS | 1 | $80,000 | $79,000 |
| 53 | (573.010003) | LS | 1 | $60,000 | $103,700 |
| 54 | (574.030001) | SF | 255 | $90.00 | $26.00 |
| 55 | Removal of Structural Concrete (580.01) | CY | 90 | $1,500.00 | $2,700.00 |
| 56 | Removal of Concrete Approach Slab (580.04) | SF | 5,609 | $4.00 | $9.00 |
| 57 | Removal and Replacement of Structural Concrete (582.0052) | SF | 398 | $250.00 | $250.00 |
| 58 | (585.01) | EACH | 34 | $5,000.00 | $6,100.00 |
| 59 | Drilling and Grouting Bolts or Reinforcing Bars (586.0201) | EACH | 862 | $50.00 | $45.00 |
| 60 | Field Drill Holes in Existing Structural Steel (586.10) | EACH | 640 | $25.00 | $25.00 |
| 61 | Bridge Railing Removal and Storage (587.02) | LF | 1,605 | $30.00 | $15.00 |
| 62 | (589.010002) | LB | 14,700 | $5.00 | $5.00 |
| 63 | (589.010003) | LB | 378 | $10.00 | $11.00 |
| 64 | (589.520001) | EACH | 12 | $700.00 | $770.00 |
| 65 | (589.520002) | EACH | 2,208 | $5.00 | $24.00 |
| 66 | (589.520003) | EACH | 12 | $700.00 | $770.00 |
| 67 | (589.520004) | EACH | 1,524 | $4.00 | $24.00 |
| 68 | (589.520005) | EACH | 10 | $700.00 | $770.00 |
| 69 | (589.520006) | EACH | 1,010 | $5.00 | $24.00 |
| 70 | (589.520007) | EACH | 3 | $1,000.00 | $550.00 |
| 71 | (603.85050015) | 1,700 | $40.00 | $45.00 | |
| 72 | Underdrain Filter, Type I (605.0901) | CY | 78 | $200.00 | $100.00 |
| 73 | (605.1501) | LF | 340 | $12.00 | $12.00 |
| 74 | (605.16020008) | 80 | $25.00 | $15.00 | |
| 75 | Box Beam Guide Railing (606.10) | LF | 244 | $55.00 | $54.00 |
| 76 | Box Beam End Piece (606.120101) | EACH | 5 | $625.00 | $680.00 |
| 77 | Resetting Box Beam Guide Railing (New Posts) (606.5348) | LF | 396 | $40.00 | $34.50 |
| 78 | Removing and Storing Box Beam Guide Railing (606.63) | LF | 1,072 | $6.00 | $12.00 |
| 79 | Removing and Storing Box Beam Guide Railing End Assembly (606.6920) | EACH | 5 | $600.00 | $1,160.00 |
| 80 | (607.06410016) | 650 | $65.00 | $68.00 | |
| 81 | Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102) | TON | 48 | $250.00 | $250.00 |
| 82 | Stone Curb – Bridge (Type A) (609.0301) | LF | 163 | $200.00 | $190.00 |
| 83 | Topsoil – Reuse On-Site Materials (610.1401) | CY | 2,891 | $15.00 | $20.00 |
| 84 | Topsoil - Roadside (610.1402) | CY | 74 | $100.00 | $85.00 |
| 85 | Turf Establishment - Roadside (610.1601) | SY | 18,010 | $1.00 | $1.25 |
| 86 | (617.11000024) | LS | 1 | $1,000.00 | $2,000.00 |
| 87 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $1,075,000 | $625,000 |
| 88 | Type III Construction Barricades (619.04) | EACH | 148 | $60.00 | $110.00 |
| 89 | Cover Existing Pavement Marking Stripes (Removable Tape) (619.0803) | LF | 39,250 | $2.00 | $0.01 |
| 90 | (619.100103) | LF | 44,854 | $3.00 | $4.30 |
| 91 | (619.110513) | EACH | 6 | $5,000.00 | $12,000 |
| 92 | Temporary Glare Screen (619.12) | LF | 3,400 | $5.00 | $17.00 |
| 93 | (619.17060005) | 15,950 | $1.00 | $0.01 | |
| 94 | Temporary Positive Barrier – Category 5 (Pinning Prohibited) (619.1715) | LF | 8,215 | $0.99 | $32.00 |
| 95 | Temporary Impact Attenuator - Redirective (Test Level 3) (619.1803) | EACH | 2 | $3,000.00 | $9,000.00 |
| 96 | Stone Filling (Light) (620.03) | CY | 158 | $125.00 | $130.00 |
| 97 | Bedding Material, Type 1 (620.0801) | CY | 167 | $125.00 | $110.00 |
| 98 | Survey Operations (625.01) | LS | 1 | $50,000 | $80,000 |
| 99 | (627.50140008) | 260 | $6.00 | $9.00 | |
| 100 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $2,000.00 | $3,800.00 |
| 101 | Engineer’s Field Office – Type 2 (637.12) | MONTH | 27 | $2,000.00 | $2,700.00 |
| 102 | Office Technology and Supplies (637.34) | DOL | 500 | $1.00 | $1.00 |
| 103 | Large Delineator, Large Snowplowing Marker, Large Supplementary Snowplowing Marker Panel (646.23) | EACH | 43 | $30.00 | $58.00 |
| 104 | Steel Post, 2.0 lb/ft (646.32) | EACH | 18 | $100.00 | $110.00 |
| 105 | Brackets for Barrier and Multidirectional Mounting (646.50) | EACH | 14 | $100.00 | $60.00 |
| 106 | Relocate Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.31) | EACH | 2 | $200.00 | $170.00 |
| 107 | Remove and Dispose Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.51) | EACH | 12 | $300.00 | $50.00 |
| 108 | Milled-In Audible Roadway Delineators (MIARDs) (649.01) | LF | 3,423 | $2.50 | $2.50 |
| 109 | White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102) | LF | 2,340 | $4.00 | $3.90 |
| 110 | Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202) | LF | 1,938 | $4.00 | $3.90 |
| 111 | (691.04000020) | 67,200 | $1.00 | $1.00 | |
| 112 | Field Change Payment (FCP) (697.03) | DOL | 598,000 | $1.00 | $1.00 |
| 113 | Asphalt Price Adjustment (698.04) | DOL | 100 | $1.00 | $1.00 |
| 114 | Fuel Price Adjustment (698.05) | DOL | 100 | $1.00 | $1.00 |
| 115 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 |
| 116 | (698.93000091) | LS | 1 | $42,000 | $42,000 |
| 117 | Mobilization (699.040001) | LS | 1 | $333,118 | $400,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of December 18, 2025. Compiled by Mirage Metrics.