NYSDOT contract D265495 bid tabulation

BRIDGE MAINTENANCE & REHAB - Rts I-87, 907C, 907M & 909C. Let by New York State DOT on October 23, 2025, Bronx, Kings, Queens, Richmond, Region 11. 8 bids received; low bid $26,484,000 by El Sol Contracting / Es II Enterprises JV.

Owner
New York State DOT
Letting
23 OCT 2025
Pay items
120
Data through
15 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1El Sol Contracting / Es II Enterprises JV$26,484,000Low
2Bove Industries - Gccom Construction JV 1$31,948,000+21%
3Tully Construction Company Inc$32,202,417+22%
4Triumph Construction Corp$33,101,393+25%
5H & L Contracting LLC$33,103,920+25%
6Paul J Scariano Inc$35,321,000+33%
7C.A.C. Industries Inc$38,692,980+46%
8Restani Construction Corp$41,972,921+58%
NYSDOT contract D265495: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. El Sol Contracting / Es II Enterprises JV2. Bove Industries - Gccom Construction JV 13. Tully Construction Company Inc4. Triumph Construction Corp5. H & L Contracting LLC6. Paul J Scariano Inc
1Clearing and Grubbing (201.06)LS1$10,000$100,000$20,000$8,610.00$10,000$38,000
2Removal and Disposal of Bond Breaker/Filler ACM (BV14) (210.3312)SF555$145.00$100.00$145.00$216.00$145.00$225.00
3Removal and Disposal of Caulking ACM (BV14) (210.3411)LF2,081$68.00$50.00$70.00$112.00$75.00$160.00
4 (210.481201)SF12,427$53.00$10.00$30.00$73.00$43.00$50.00
5 (210.481202)SF482$175.00$125.00$175.00$260.00$175.00$255.00
6 (210.481203)SF20$275.00$150.00$280.00$409.00$275.00$410.00
7 (210.481204)SF965$38.00$40.00$40.00$57.00$38.00$60.00
8 (210.481301)LS1$6,500.00$6,500.00$6,500.00$9,674.00$6,500.00$5,000.00
9 (402.90710118)191$680.00$800.00$800.00$421.00$700.00$2,200.00
10 (404.0971)TON238$455.00$900.00$300.00$454.00$500.00$1,500.00
11 (404.1281)TON12$650.00$650.00$1,000.00$2,128.00$3,400.00$3,800.00
12Diluted Tack Coat (407.0102)GAL227$5.00$10.00$60.00$32.00$6.62$100.00
13Production Cold Milling of Bituminous Concrete (490.10)SY3,107$31.00$85.00$25.00$23.00$32.00$75.00
14Production Cold Milling of Portland Cement Concrete (490.20)SY2,028$38.50$40.00$26.00$26.00$39.00$190.00
15Concrete for Structures, Performance (555.0021)CY88$6,000.00$6,500.00$1,350.00$2,530.00$4,300.00$5,750.00
16 (555.80010001)2,427$40.00$125.00$90.00$176.00$175.00$250.00
17 (555.81980011)4,963$40.00$145.00$95.00$167.00$90.00$325.00
18Performance Concrete Quality Adjustment – Concrete for Structures (555.9902)QUALITY UNIT1$32.23$32.23$32.23$32.23$32.23$32.23
19Epoxy-Coated Bar Reinforcement for Structures (556.0202)LB10,334$20.00$3.00$3.50$4.00$2.75$32.00
20Sidewalks and Safety Walks (557.30)SY45$700.00$400.00$330.00$144.00$800.00$1,750.00
21 (557.67010311)803$600.00$425.00$630.00$753.00$565.00$600.00
22Performance Concrete Quality Adjustment – Sidewalks and Safety Walks (557.9902)QUALITY UNIT1$15.01$15.01$15.01$15.01$15.01$15.01
23 (559.19010011)161$50.00$65.00$72.00$81.00$20.00$235.00
24 (560.72010011)262$150.00$125.00$78.00$254.00$225.00$650.00
25 (564.510001)LB7,367$80.00$100.00$60.00$69.00$40.00$70.00
26 (564.510002)LB2$2,500.00$21,000$1,200.00$1,297.00$1,800.00$17.00
27 (564.510003)LB2,254$80.00$150.00$72.00$84.00$55.00$72.00
28 (564.510004)LB6,966$80.00$75.00$60.00$61.00$38.00$63.00
29 (564.510005)LB6,231$80.00$70.00$72.00$78.00$40.00$59.00
30 (564.510006)LB11,570$80.00$100.00$60.00$71.00$29.00$90.00
31 (564.510007)LB585$80.00$600.00$120.00$77.00$135.00$170.00
32Type M.R. Expansion Bearing (226 to 450 k) (565.1522)EACH22$7,000.00$16,500$16,500$12,642$6,500.00$16,500
33Type M.R. Expansion Bearing (451 to 675 k) (565.1523)EACH6$7,000.00$30,000$17,700$16,367$6,500.00$25,500
34Type M.R. Fixed Bearing (451 to 675 k) (565.1723)EACH5$7,000.00$20,000$16,800$16,912$6,500.00$2,000.00
35Type M.R. Fixed Bearing (676 to 900 k) (565.1724)EACH5$7,000.00$35,000$16,800$16,176$6,500.00$23,250
36 (565.43020015)79$8,000.00$10,000$24,000$14,948$4,500.00$7,500.00
37Bridge Joint Header (567.62)CF934$250.00$300.00$250.00$517.00$300.00$400.00
38Bridge Joint Seal (567.63)LF1,999$120.00$200.00$80.00$252.00$235.00$250.00
39Performance Concrete Quality Adjustment (567.99)QUALITY UNIT1$40.54$40.54$40.54$40.54$40.54$40.54
40Lead-Exposure Control Plan (570.01)LS1$7,500.00$9,500.00$17,500$6,893.00$10,000$12,000
41Medical Testing (570.02)DOL10,440$1.00$1.00$1.00$1.00$1.00$1.00
42Personal-Exposure-Monitoring Sample Analysis (570.03)DOL12,008$1.00$1.00$1.00$1.00$1.00$1.00
43Decontamination Facilities (570.04)CALENDAR WEEK32$1,500.00$94.00$300.00$689.00$200.00$100.00
44 (570.10)LS1$1,100,000$9,500.00$15,000$15,992$350,000$150,000
45 (570.160001)LS1$400,000$4,700.00$5,800.00$17,922$400,000$6,500.00
46 (570.160002)LS1$400,000$4,700.00$5,800.00$4,412.00$250,000$6,500.00
47 (570.160003)LS1$250,000$4,700.00$5,800.00$2,206.00$150,000$6,500.00
48 (570.160004)LS1$250,000$4,700.00$5,800.00$3,171.00$375,000$6,500.00
49 (570.160005)LS1$250,000$4,700.00$5,800.00$3,447.00$450,000$6,500.00
50 (570.160006)LS1$350,000$4,700.00$5,800.00$4,687.00$550,000$6,500.00
51 (570.160007)LS1$350,000$4,700.00$5,800.00$3,860.00$180,000$6,500.00
52 (570.160008)LS1$750,000$4,700.00$5,800.00$16,544$150,000$6,500.00
53Disposal of Hazardous Paint Removal Waste Containing Lead (571.03)LB16,086$1.00$1.50$1.70$2.00$2.00$2.00
54 (574.030001)SF7,530$80.00$80.00$100.00$240.00$51.00$118.00
55 (574.030002)SF3,297$80.00$100.00$128.00$135.00$61.00$120.00
56 (574.030003)SF1,600$80.00$100.00$132.00$159.00$47.00$120.00
57 (574.030004)SF2,289$80.00$100.00$124.00$137.00$131.00$125.00
58 (574.030005)SF2,536$80.00$100.00$125.00$132.00$138.00$120.00
59 (574.030006)SF3,677$80.00$210.00$260.00$125.00$122.00$285.00
60 (574.030007)SF1,874$100.00$200.00$250.00$199.00$48.00$300.00
61 (574.030008)SF9,522$80.00$125.00$140.00$166.00$50.00$160.00
62 (576.03210011)11$700.00$650.00$560.00$409.00$4,500.00$900.00
63Downspout System (Ductile Iron) (576.2001)LF63$1,000.00$1,450.00$300.00$853.00$600.00$300.00
64Removal of Structural Concrete (580.01)CY135$4,000.00$8,000.00$2,200.00$2,465.00$9,000.00$5,000.00
65Removal and Replacement of Structural Concrete (582.0051)CY241$3,500.00$9,500.00$5,540.00$8,349.00$15,850$9,500.00
66Removal of Structural Concrete- Replacement with Vertical and Overhead Patching Material (582.0061)SF976$230.00$300.00$175.00$728.00$460.00$675.00
67 (582.20130111)155$800.00$1,100.00$405.00$3,002.00$475.00$3,200.00
68 (582.99)1$10.00$10.00$10.00$10.00$10.00$10.00
69 (585.01)EACH3$20,000$150,000$120,000$24,906$90,000$12,000
70 (585.02)EACH12$20,000$70,000$61,800$26,352$70,000$23,000
71 (585.03)EACH8$20,000$90,000$30,300$14,381$75,000$20,000
72 (585.04)EACH25$20,000$85,000$61,000$29,088$75,000$22,000
73 (585.05)EACH10$20,000$65,000$30,000$15,561$65,000$19,000
74 (585.06)EACH27$20,000$35,000$60,000$37,168$45,000$26,000
75 (585.07)EACH29$20,000$65,000$24,200$14,913$45,000$16,500
76Drilling and Grouting Bolts or Reinforcing Bars (with Non-Destructive Investigation) (586.0202)EACH1,260$100.00$80.00$48.00$395.00$650.00$205.00
77Removal of Rivets-Replacement with High Strength Bolts (586.05)EACH1,152$100.00$50.00$145.00$207.00$90.00$110.00
78Field Drill Holes in Existing Structural Steel (586.10)EACH3,727$70.00$43.00$120.00$78.00$110.00$110.00
79 (589.010001)LB622$30.00$50.00$240.00$14.00$30.00$24.00
80 (589.010002)LB5,792$30.00$10.00$95.00$16.00$20.00$24.00
81 (589.010003)LB4,148$30.00$10.00$95.00$13.00$20.00$24.00
82 (589.010004)LB1,373$30.00$30.00$95.00$16.00$27.00$24.00
83 (589.010005)LB563$30.00$30.00$240.00$16.00$66.00$24.00
84 (589.520001)EACH3$2,500.00$3,500.00$10,400$10,115$3,500.00$3,500.00
85 (589.520002)EACH35$2,500.00$5,500.00$10,400$9,856.00$3,500.00$3,500.00
86HPBO (Mod.) Corrugated Beam Guide Railing (606.2701)LF34$250.00$208.00$120.00$65.00$208.00$208.00
87Anchorage Units for HPBO (Mod.) Corrugated Beam Guide Railing (606.2703)EACH6$5,580.00$5,580.00$7,500.00$5,187.00$5,580.00$7,950.00
88HPBO (Mod.) Corrugated Beam Median Barrier End Terminal (Energy-Absorbing) (606.28)EACH6$11,500$11,500$9,500.00$18,155$11,500$12,500
89HPBO (Mod.) Corrugated Beam Median Barrier (606.2801)LF27$300.00$300.00$150.00$78.00$300.00$325.00
90Removing and Disposing HPBO (Mod.) Corrugated Beam Guide Railing (606.7101)LF34$153.00$153.00$25.00$78.00$153.00$160.00
91Removing and Disposing HPBO (Mod.) Corrugated Beam Median Barrier (606.7201)LF27$76.00$76.00$30.00$78.00$76.00$100.00
92 (607.0512)LF32$246.00$246.00$200.00$78.00$246.00$300.00
93Basic Work Zone Traffic Control (619.01)LS1$3,354,280$1,340,788$4,570,000$3,455,000$2,483,705$2,000,000
94Type III Construction Barricades (619.04)EACH140$50.00$75.00$5.00$93.00$205.83$175.00
95 (619.10050020)810$40.00$50.00$100.00$58.00$22.00$75.00
96 (619.110511)EACH32$2,500.00$15,000$600.00$12,500$8,800.00$3,500.00
97Nighttime Operations (Entire Project) (619.24)LS1$550,000$350,000$600,000$850,600$775,000$500,000
98 (619.70030011)6,256$35.00$50.00$155.00$194.00$65.00$205.00
99 (619.70040011)12,463$10.00$50.00$22.00$61.00$25.00$225.00
100Survey Operations (625.01)LS1$500,000$100,000$140,000$198,085$65,000$363,713
101Concrete Cylinder Curing Equipment (637.04)EACH1$10,000$8,500.00$4,000.00$8,716.00$7,015.26$7,500.00
102Engineer’s Field Office – Type 3 (637.13)MONTH27$7,500.00$12,000$12,000$13,500$15,000$18,500
103 (637.31010020)27$900.00$1,000.00$1,000.00$1,000.00$1,000.00$1,000.00
104Office Technology and Supplies (637.34)DOL13,500$1.00$1.00$1.00$1.00$1.00$1.00
105Partnering Workshop (637.35)DOL5,000$1.00$1.00$1.00$1.00$1.00$1.00
106 (639.10210011)LS1$100,000$75,000$75,000$75,000$75,000$75,000
107Remove and Dispose Impact Attenuator Systems (654.0701)EACH1$5,000.00$6,500.00$1,500.00$754.00$9,500.00$18,500
108Expendable Impact Attenuator , TL 3, ≤ 2 ft Obstruction Width (654.5030)EACH1$25,000$45,000$30,000$36,398$55,000$65,000
109 (665.98000001)LS1$20,000$350,000$242,000$263,248$340,000$275,000
110 (675.99000023)100,000$1.00$1.00$1.00$1.00$1.00$1.00
111White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102)LF3,418$2.25$1.50$1.60$2.00$1.57$3.75
112Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202)LF2,713$2.00$1.50$1.60$2.00$1.57$3.75
113White Epoxy Reflectorized Pavement Letters - 20 mil Portable/Hand Application (685.3304)EACH28$250.00$150.00$145.00$190.00$146.31$305.00
114White Epoxy Reflectorized Pavement Symbols - 20 mil Portable/Hand Application (685.3404)EACH11$250.00$165.00$175.00$211.00$162.57$325.00
115 (691.04000020)115,000$1.00$1.00$1.00$1.00$1.00$1.00
116Field Change Payment (FCP) (697.03)DOL856,000$1.00$1.00$1.00$1.00$1.00$1.00
117Asphalt Price Adjustment (698.04)DOL552$1.00$1.00$1.00$1.00$1.00$1.00
118Fuel Price Adjustment (698.05)DOL100$1.00$1.00$1.00$1.00$1.00$1.00
119Steel/Iron Price Adjustment (698.06)DOL100$1.00$1.00$1.00$1.00$1.00$1.00
120Mobilization (699.040001)LS1$900,000$1,227,000$1,230,000$1,200,000$1,248,000$1,350,000
NYSDOT contract D265495: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.

Every contract let that day: NYSDOT letting of October 23, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy