NYSDOT contract D265662 bid tabulation
Bridge Preservation SFY 25. Let by New York State DOT on February 26, 2026, Albany, Rensselaer, Region 01. 1 bid received; low bid $15,455,797 by D A Collins Construction Co Inc.
- Owner
- New York State DOT
- Letting
- 26 FEB 2026
- Pay items
- 129
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | D A Collins Construction Co Inc | $15,455,797 | Low |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. D A Collins Construction Co Inc |
|---|---|---|---|---|
| 1 | Unclassified Excavation and Disposal (203.02) | CY | 414 | $215.00 |
| 2 | Select Granular Fill (203.07) | CY | 80 | $24.50 |
| 3 | Select Structural Fill (203.21) | CY | 21 | $785.00 |
| 4 | Controlled Low Strength Material (CLSM) (204.01) | CY | 8 | $1,000.00 |
| 5 | Structure Excavation (206.01) | CY | 21 | $565.00 |
| 6 | Trench and Culvert Excavation (206.0201) | CY | 87 | $250.00 |
| 7 | Conduit Excavation and Backfill including Surface Restoration (206.03) | LF | 266 | $34.00 |
| 8 | (206.03120010) | 450 | $26.50 | |
| 9 | (206.03120011) | 2,326 | $55.50 | |
| 10 | Geotextile Bedding (207.20) | SY | 25 | $54.00 |
| 11 | (210.481201) | SF | 2,070 | $47.00 |
| 12 | Subbase Course, Type 2 (304.12) | CY | 204 | $280.00 |
| 13 | (404.0982) | TON | 301 | $290.00 |
| 14 | (404.1989) | TON | 49 | $290.00 |
| 15 | (404.3789) | TON | 154 | $290.00 |
| 16 | Straight Tack Coat (407.0103) | GAL | 300 | $21.50 |
| 17 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 1,730 | $4.25 |
| 18 | Miscellaneous Cold Milling of Bituminous Concrete (490.30) | SY | 2,213 | $13.00 |
| 19 | (520.09000010) | 264 | $5.30 | |
| 20 | Shields and Shoring (552.17) | SF | 336 | $1.15 |
| 21 | Concrete for Structures, Performance (555.0021) | CY | 269 | $3,000.00 |
| 22 | Performance Concrete Quality Adjustment – Concrete for Structures (555.9902) | QUALITY UNIT | 1 | $7.50 |
| 23 | Epoxy-Coated Bar Reinforcement for Structures (556.0202) | LB | 22,171 | $5.40 |
| 24 | Stainless Steel Bar Reinforcement for Structures (556.0205) | LB | 8,737 | $8.00 |
| 25 | Stud Shear Connectors for Bridges (556.03) | EACH | 2,373 | $25.00 |
| 26 | (557.1012) | SY | 361 | $795.00 |
| 27 | Sidewalks and Safety Walks (557.30) | SY | 43 | $844.00 |
| 28 | (557.66130105) | 34 | $2,611.00 | |
| 29 | (557.75010216) | 480 | $460.00 | |
| 30 | Performance Concrete Quality Adjustment – Superstructure and Approach Slab (557.9901) | QUALITY UNIT | 1 | $9.00 |
| 31 | Performance Concrete Quality Adjustment – Sidewalks and Safety Walks (557.9902) | QUALITY UNIT | 1 | $12.00 |
| 32 | Longitudinal Sawcut Grooving of Structural Slab Surface (558.02) | SY | 271 | $29.50 |
| 33 | Protective Sealing of Structural Concrete on New Bridge Decks and Bridge Deck Overlays (559.01) | SF | 2,340 | $2.85 |
| 34 | Protective Sealing of New Structural Concrete (559.02) | SF | 9,572 | $2.85 |
| 35 | (564.510001) | LB | 334 | $46.50 |
| 36 | (564.510002) | LB | 4,986 | $72.00 |
| 37 | (564.700001) | EACH | 20 | $6,550.00 |
| 38 | (564.700002) | EACH | 21 | $6,850.00 |
| 39 | (564.700003) | EACH | 1 | $6,900.00 |
| 40 | (564.700004) | EACH | 4 | $7,450.00 |
| 41 | (564.700005) | EACH | 2 | $7,050.00 |
| 42 | (564.700006) | EACH | 5 | $6,950.00 |
| 43 | (564.700007) | EACH | 6 | $5,650.00 |
| 44 | Type M.R. Expansion Bearing (226 to 450 k) (565.1522) | EACH | 24 | $7,200.00 |
| 45 | Type M.R. Expansion Bearing (Over 900 k) (565.1525) | EACH | 9 | $16,600 |
| 46 | Type M.R. Fixed Bearing (Over 900 k) (565.1725) | EACH | 9 | $15,000 |
| 47 | Type E.B. Fixed Bearing (Over 225 k) (565.2025) | EACH | 9 | $4,900.00 |
| 48 | (565.20310003) | 36 | $4,950.00 | |
| 49 | Type E.B. Expansion Bearing (169 to 225 k) (565.2034) | EACH | 24 | $4,350.00 |
| 50 | Type E.B. Expansion Bearing (Over 225 k) (565.2035) | EACH | 20 | $6,950.00 |
| 51 | (566.13142001) | 304 | $2,750.00 | |
| 52 | Steel Bridge Railing (Four-Rail) (568.51) | LF | 234 | $385.00 |
| 53 | Single Slope (Full-Section) Concrete Bridge Barrier (569.05) | LF | 81 | $1,200.00 |
| 54 | Performance Concrete Quality Adjustment–Cast-In-Place Concrete Barrier (569.99) | QUALITY UNIT | 1 | $9.09 |
| 55 | Lead-Exposure Control Plan (570.01) | LS | 1 | $2,650.00 |
| 56 | Medical Testing (570.02) | DOL | 3,000 | $1.00 |
| 57 | Personal-Exposure-Monitoring Sample Analysis (570.03) | DOL | 3,000 | $1.00 |
| 58 | Decontamination Facilities (570.04) | CALENDAR WEEK | 15 | $21.50 |
| 59 | (570.150001) | LS | 1 | $90,400 |
| 60 | Disposal of Hazardous Paint Removal Waste Containing Lead (571.03) | LB | 17,615 | $0.21 |
| 61 | (572.020001) | LS | 1 | $1.15 |
| 62 | (573.010001) | LS | 1 | $513,000 |
| 63 | (576.03210011) | 16 | $410.00 | |
| 64 | Removal of Structural Concrete (580.01) | CY | 176 | $3,220.00 |
| 65 | Removal of Concrete Approach Slab (580.04) | SF | 3,340 | $12.00 |
| 66 | Removal and Replacement of Structural Concrete (582.0052) | SF | 2,474 | $350.00 |
| 67 | Removal of Structural Concrete- Replacement with Vertical and Overhead Patching Material (582.0061) | SF | 174 | $590.00 |
| 68 | (585.01) | EACH | 113 | $12,800 |
| 69 | (585.02) | EACH | 18 | $62,300 |
| 70 | Drilling and Grouting Bolts or Reinforcing Bars (586.0201) | EACH | 1,357 | $130.00 |
| 71 | Field Drill Holes in Existing Structural Steel (586.10) | EACH | 731 | $65.00 |
| 72 | Bridge Railing Removal and Storage (587.02) | LF | 577 | $39.50 |
| 73 | Installation of Stored Bridge Railing (587.03) | LF | 577 | $150.00 |
| 74 | (589.520001) | EACH | 20 | $3,350.00 |
| 75 | (589.520002) | EACH | 21 | $3,600.00 |
| 76 | (589.520003) | EACH | 1 | $3,350.00 |
| 77 | (589.520004) | EACH | 4 | $3,350.00 |
| 78 | (589.520005) | EACH | 2 | $3,350.00 |
| 79 | (589.520006) | EACH | 5 | $3,350.00 |
| 80 | (589.520007) | EACH | 6 | $3,350.00 |
| 81 | (589.520008) | EACH | 131 | $2,500.00 |
| 82 | (603.6003) | LF | 54 | $430.00 |
| 83 | Concrete Collars (603.77) | EACH | 1 | $5,250.00 |
| 84 | (603.99050002) | 4 | $965.00 | |
| 85 | (604.13000011) | 4 | $2,450.00 | |
| 86 | (604.302192) | LF | 18 | $1,000.00 |
| 87 | Single-Slope Concrete Median Barrier (Cast-in-Place) (606.3043) | LF | 50 | $615.00 |
| 88 | (607.61000005) | 120 | $80.00 | |
| 89 | (608.01030008) | 46 | $835.00 | |
| 90 | Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102) | TON | 2 | $560.00 |
| 91 | Stone Curb – Bridge (Type A) (609.0301) | LF | 80 | $205.00 |
| 92 | Stone Curb – Bridge (Type F1) (609.0302) | LF | 48 | $270.00 |
| 93 | (609.06000008) | 54 | $79.50 | |
| 94 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $2,183,000 |
| 95 | Type III Construction Barricades (619.04) | EACH | 4 | $62.00 |
| 96 | Cover Existing Pavement Marking Letters or Symbols (Removable Tape) (619.0804) | EACH | 2 | $320.00 |
| 97 | (619.100103) | LF | 9,120 | $5.85 |
| 98 | (619.100203) | EACH | 2 | $320.00 |
| 99 | (619.100303) | EACH | 8 | $105.00 |
| 100 | (619.111113) | EACH | 2 | $45,700 |
| 101 | Temporary Positive Barrier – Category 1 (Pinning Prohibited) (619.1711) | LF | 480 | $44.50 |
| 102 | Temporary Positive Barrier – Category 5 (Pinning Prohibited) (619.1715) | LF | 4,080 | $63.50 |
| 103 | Temporary Positive Barrier – Category 6 (Pinning Required) (619.1716) | LF | 1,920 | $58.50 |
| 104 | Warning Lights on Temporary Positive Barriers (619.1719) | EACH | 172 | $27.00 |
| 105 | Nighttime Operations (Entire Project) (619.24) | LS | 1 | $35,200 |
| 106 | Survey Operations (625.01) | LS | 1 | $36,500 |
| 107 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $1,850.00 |
| 108 | Welded Frame & Reticuline Grate 22 (655.1122) | EACH | 4 | $3,100.00 |
| 109 | (655.16000011) | 4 | $950.00 | |
| 110 | (662.60000108) | 3,000 | $1.00 | |
| 111 | (665.98000103) | LS | 1 | $16,400 |
| 112 | (665.98000116) | LS | 1 | $120,000 |
| 113 | (670.35250025) | 266 | $32.00 | |
| 114 | (670.41091111) | 6 | $2,750.00 | |
| 115 | (680.520406) | LF | 3,040 | $80.00 |
| 116 | (680.53000111) | 10 | $2,850.00 | |
| 117 | (680.730310) | LF | 3,040 | $9.05 |
| 118 | (680.90920008) | 2 | $1,550.00 | |
| 119 | Watertight Disconnect Box (680.9401) | EACH | 2 | $1,550.00 |
| 120 | White Epoxy Reflectorized Pavement Stripes - 15 mil (685.0101) | LF | 7,171 | $1.25 |
| 121 | Yellow Epoxy Reflectorized Pavement Stripes - 15 mil (685.0201) | LF | 5,313 | $1.25 |
| 122 | (685.06150106) | 1,462 | $3.80 | |
| 123 | White Epoxy Reflectorized Pavement Letters - 15 mil Portable/Hand Application (685.2303) | EACH | 12 | $80.00 |
| 124 | White Epoxy Reflectorized Pavement Symbols - 15 mil Portable/Hand Application (685.2403) | EACH | 7 | $240.00 |
| 125 | Field Change Payment (FCP) (697.03) | DOL | 700,000 | $1.00 |
| 126 | Asphalt Price Adjustment (698.04) | DOL | 100 | $1.00 |
| 127 | Fuel Price Adjustment (698.05) | DOL | 367 | $1.00 |
| 128 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 |
| 129 | Mobilization (699.040001) | LS | 1 | $550,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of February 26, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.