NYSDOT contract D265700 bid tabulation

Rehabilitation of I-86 Bridges over ICRR. Let by New York State DOT on March 12, 2026, Tioga, Region 09. 4 bids received; low bid $6,772,000 by R De Vincentis Construction Inc.

Owner
New York State DOT
Letting
12 MAR 2026
Pay items
115
Data through
15 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1R De Vincentis Construction Inc$6,772,000Low
2Vector Construction Corp$6,827,909+1.0%
3Economy Paving Co Inc$7,997,098+18%
4Bothar Construction LLC$8,845,220+31%
NYSDOT contract D265700: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. R De Vincentis Construction Inc2. Vector Construction Corp3. Economy Paving Co Inc4. Bothar Construction LLC
1Unclassified Excavation and Disposal (203.02)CY2,385$14.00$35.00$35.00$59.10
2Embankment In Place (203.03)CY2,815$22.00$56.00$35.00$85.45
3Select Structural Fill (203.21)CY27$275.00$180.00$35.00$137.10
4 (203.24010017)6$250.00$160.00$100.00$153.70
5 (203.51990006)68$48.00$17.00$10.00$88.70
6Structure Excavation (206.01)CY133$27.00$70.00$55.00$70.00
7Seed and Mulch – Temporary (209.1003)SY1,000$3.00$2.00$5.00$2.15
8Removal and Disposal of Bond Breaker/Filler ACM (BV14) (210.3312)SF172$110.00$125.00$100.00$67.00
9Subbase Course, Optional Type (304.15)CY2,481$76.00$100.00$95.00$82.70
10 (404.0983)TON340$195.00$180.00$195.00$217.50
11 (404.2589)TON283$170.00$145.00$195.00$182.10
12 (404.4289)TON343$180.00$125.00$185.00$165.70
13 (404.4489)TON1,231$145.00$110.00$165.00$132.00
14 (407.01040009)697$11.00$7.00$3.00$7.70
15Asphalt Pavement Joint Adhesive (418.7603)LF539$5.00$2.50$1.00$3.60
16Miscellaneous Cold Milling of Bituminous Concrete (490.30)SY1,770$15.00$11.00$14.50$21.00
17Miscellaneous Cold Milling of Portland Cement Concrete (490.40)SY1,563$33.00$22.00$16.50$30.50
18 (555.97130016)34$6,200.00$4,000.00$6,050.00$4,165.00
19Performance Concrete Quality Adjustment – Concrete for Structures (555.9902)QUALITY UNIT1$14.28$14.28$14.28$14.28
20Uncoated Bar Reinforcement for Concrete Structures (556.0201)LB451$45.00$5.00$5.00$19.90
21Stud Shear Connectors for Bridges (556.03)EACH120$60.00$17.00$25.00$1.90
22Superstructure Slab with Separate Wearing Surface – Bottom Formwork Not Required (557.09)SY59$125.00$500.00$225.00$720.50
23 (557.1012)SY437$475.00$500.00$475.00$513.30
24 (557.1112)SY165$2,850.00$1,500.00$2,950.00$2,771.00
25Winter Surface Treatment – Superstructure Slabs and Structural Approach Slabs (557.29)SY2,316$1.00$0.01$1.00$1.25
26 (557.60010004)2,219$35.00$30.00$19.50$22.25
27 (557.75010216)334$450.00$480.00$245.00$635.30
28Performance Concrete Quality Adjustment – Superstructure and Approach Slab (557.9901)QUALITY UNIT1$9.90$9.90$9.90$9.90
29Longitudinal Sawcut Grooving of Structural Slab Surface (558.02)SY2,219$10.00$10.00$9.50$10.30
30Protective Sealing of Structural Concrete on New Bridge Decks and Bridge Deck Overlays (559.01)SF19,964$1.25$1.00$0.55$1.25
31Protective Sealing of New Structural Concrete (559.02)SF10,436$1.25$1.00$0.85$1.30
32Protective Sealing of Concrete with Coating Type Protective Sealer (559.04)SQUAREFOOT11,372$4.50$4.50$3.50$8.30
33 (564.510001)LB5,156$27.00$28.00$75.00$56.90
34Type E.B. Fixed Bearing (112 to 168 k) (565.2023)EACH10$2,600.00$3,000.00$6,500.00$3,178.00
35 (565.20310003)10$5,000.00$5,000.00$6,500.00$3,435.00
36Type E.B. Expansion Bearing (56 to 111 k) (565.2032)EACH10$2,500.00$3,000.00$6,500.00$3,178.00
37Type E.B. Expansion Bearing (112 to 168 k) (565.2033)EACH10$3,200.00$3,000.00$6,500.00$3,178.00
38Type E.B. Expansion Bearing (169 to 225 k) (565.2034)EACH20$3,300.00$3,000.00$6,500.00$3,178.00
39Armorless Bridge Joint (567.60)LF84$400.00$380.00$335.00$579.70
40Transition Bridge Railing (568.70)LF320$340.00$310.00$195.00$222.00
41 (569.40010208)990$256.00$350.00$355.00$743.50
42Personal-Exposure-Monitoring Sample Analysis (570.03)DOL3,000$1.00$1.00$1.00$1.00
43Decontamination Facilities (570.04)CALENDAR WEEK2$100.00$100.00$100.00$115.00
44 (570.09)LS1$5,000.00$4,000.00$1,000.00$4,140.00
45Disposal of Non-Hazardous Industrial Solid Paint Removal Waste (571.04)LB927$3.00$6.00$1.00$5.75
46 (574.030001)SF680$96.00$250.00$10.00$349.70
47Scuppers (Type B) (576.02)EACH4$4,000.00$4,500.00$4,500.00$6,015.00
48 (576.25000002)500$35.00$12.00$10.00$21.05
49Reinforcing Bar Exposure (579.02)SF4,618$66.00$43.00$70.00$64.75
50Removal of Structural Concrete (580.01)CY145$3,500.00$3,000.00$3,250.00$3,502.00
51Removal of Concrete Approach Slab (580.04)SF3,668$10.00$12.00$7.50$7.05
52Removal and Replacement of Structural Concrete (582.0051)CY2$8,300.00$9,200.00$9,500.00$10,641
53Removal and Replacement of Structural Concrete (582.0052)SF1,256$200.00$240.00$225.00$175.10
54 (584.030202)1,907$50.00$145.00$105.00$96.80
55 (584.032001)178$70.00$201.00$195.00$97.75
56 (584.9901)1$14.49$14.49$14.49$14.49
57 (585.01)EACH20$2,500.00$4,000.00$7,050.00$6,847.00
58 (585.02)EACH40$4,100.00$6,000.00$14,000$6,800.00
59Drilling and Grouting Bolts or Reinforcing Bars (586.0201)EACH930$40.00$38.00$45.00$39.40
60Field Drill Holes in Existing Structural Steel (586.10)EACH160$60.00$30.00$100.00$97.30
61Bridge Railing Removal and Disposal (587.01)LF118$30.00$290.00$20.00$45.20
62 (589.01)4,245$25.00$8.00$1.00$7.60
63 (589.520001)EACH60$900.00$550.00$775.00$520.50
64Box Beam Guide Railing (606.10)LF118$91.00$90.00$60.00$68.25
65Box Beam End Piece (606.120101)EACH1$1,100.00$1,000.00$855.00$982.00
66Box Beam Guide Railing End Assembly Type IIA (606.120201)EACH1$3,600.00$3,400.00$2,350.00$2,701.00
67Box Beam End Assembly Type III (606.1203)EACH1$10,500$9,800.00$7,040.00$8,100.00
68Resetting Box Beam Guide Railing (606.53)LF316$42.00$40.00$35.00$44.00
69Removing and Storing Box Beam Guide Railing (606.63)LF316$12.00$8.00$10.00$6.95
70 (607.06400016)484$110.00$100.00$95.00$211.80
71Stone Curb – Bridge (Type A) (609.0301)LF113$175.00$120.00$145.00$222.35
72Weed Removal (610.13)SY10,515$1.10$1.00$0.50$0.60
73Topsoil – Reuse On-Site Materials (610.1401)CY838$56.00$39.00$10.00$66.00
74Topsoil - Roadside (610.1402)CY330$87.00$60.00$75.00$108.40
75Turf Establishment - Roadside (610.1601)SY9,635$2.00$1.60$1.50$1.50
76 (610.16093524)8,556$2.25$1.80$2.00$2.40
77Watering Vegetation (610.19)1,000 GALLONS476$25.00$20.00$5.00$12.00
78Mowing (610.21)SY35,120$0.65$0.50$0.50$0.55
79Improvement of Vegetated Areas (614.05)SY510$9.00$6.00$10.00$12.10
80 (617.01010024)1,058$2.50$2.00$3.00$4.00
81 (617.10000024)335$55.00$55.00$20.00$83.85
82 (617.11000024)LS1$3,000.00$3,200.00$1,000.00$3,188.00
83Basic Work Zone Traffic Control (619.01)LS1$275,000$487,000$745,000$700,000
84Type III Construction Barricades (619.04)EACH37$225.00$150.00$250.00$202.40
85 (619.080101)LF892$1.65$5.00$5.00$2.35
86 (619.080102)LF3,834$1.65$5.00$5.00$1.75
87Cover Existing Pavement Marking Stripes (Removable Tape) (619.0803)LF2,172$12.00$9.00$8.50$12.15
88 (619.0903)LF6,568$12.00$5.00$5.00$12.35
89 (619.100101)LF18,305$0.40$0.30$0.30$0.40
90 (619.100102)LF24,420$0.75$0.90$0.85$0.75
91 (619.111112)EACH4$21,000$12,000$20,000$32,795
92Temporary Positive Barrier – Category 3 (Pinning Prohibited) (619.1713)LF4,180$66.00$40.00$50.00$92.75
93Temporary Rumble Strips (619.22)LF1,728$18.00$16.00$15.00$29.70
94Stone Filling (Light) (620.03)CY91$230.00$160.00$145.00$203.80
95Bedding Material, Type 1 (620.0801)CY22$350.00$160.00$100.00$142.90
96Survey Operations (625.01)LS1$35,000$30,000$50,000$67,041
97Concrete Cylinder Curing Equipment (637.04)EACH2$5,000.00$3,500.00$5,000.00$4,484.00
98Engineer’s Field Office – Type 1 (637.11)MONTH24$2,200.00$2,499.00$3,000.00$3,587.00
99Office Technology and Supplies (637.34)DOL2,500$1.00$1.00$1.00$1.00
100 (642.31510024)380$5.00$2.70$25.00$27.00
101Type A Sign Posts (645.81)EACH3$525.00$500.00$275.00$316.25
102Delineator, Snowplowing Marker, Supplementary Snowplowing Marker Panels (646.22)EACH10$40.00$40.00$15.00$13.80
103Steel Post, 2.0 lb/ft (646.32)EACH10$185.00$170.00$65.00$74.75
104Remove and Store Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.41)EACH1$115.00$160.00$250.00$64.05
105Remove and Dispose Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.51)EACH2$85.00$80.00$250.00$23.00
106 (647.83001002)10$40.00$11.00$50.00$17.25
107 (675.99000023)360,000$1.00$1.00$1.00$1.00
108 (685.16010014)28,730$1.85$1.30$1.25$1.90
109 (685.21010004)9,048$1.85$1.30$1.50$1.90
110 (691.04000020)36,000$1.00$1.00$1.00$1.00
111Field Change Payment (FCP) (697.03)DOL270,000$1.00$1.00$1.00$1.00
112Asphalt Price Adjustment (698.04)DOL2,600$1.00$1.00$1.00$1.00
113Fuel Price Adjustment (698.05)DOL3,050$1.00$1.00$1.00$1.00
114Steel/Iron Price Adjustment (698.06)DOL100$1.00$1.00$1.00$1.00
115Mobilization (699.040001)LS1$254,520$260,000$301,012$335,000
NYSDOT contract D265700: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.

Every contract let that day: NYSDOT letting of March 12, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy