NYSDOT contract D265702 bid tabulation
I-81 VIADUCT (COMMUNITY GRID) - CONTRACT 6A. Let by New York State DOT on July 30, 2026, Onondaga, Region 03. 3 bids received; low bid $143,519,598 by Lancaster Development and Tully Construction Co LLC.
- Owner
- New York State DOT
- Letting
- 30 JUL 2026
- Pay items
- 416
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Lancaster Development and Tully Construction Co LLC | $143,519,598 | Low |
| 2 | CDS Civil JV | $197,802,000 | +38% |
| 3 | Cold Spring Construction Company | $203,888,129 | +42% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Lancaster Development and Tully Construction Co LLC | 2. CDS Civil JV | 3. Cold Spring Construction Company |
|---|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.07) | ACRE | 1 | $4,000.00 | $9,000.00 | $4,950.00 |
| 2 | Unclassified Excavation and Disposal (203.02) | CY | 31,796 | $79.30 | $153.00 | $48.00 |
| 3 | Embankment In Place (203.03) | CY | 20,141 | $74.00 | $99.00 | $58.00 |
| 4 | Select Granular Fill (203.07) | CY | 16,486 | $320.00 | $99.00 | $110.00 |
| 5 | Select Structural Fill (203.21) | CY | 700 | $167.00 | $153.00 | $68.00 |
| 6 | Controlled Low Strength Material (CLSM) (204.01) | CY | 10,801 | $498.00 | $360.00 | $665.00 |
| 7 | (205.0201) | LS | 1 | $3,443,000 | $540,000 | $10,000,000 |
| 8 | Field Organic Vapor Monitoring of Contaminated Soil (205.03) | HR | 3,667 | $178.00 | $162.00 | $215.00 |
| 9 | (205.050101) | TON | 313 | $700.00 | $450.00 | $495.00 |
| 10 | (205.050201) | TON | 125,310 | $37.00 | $81.00 | $90.00 |
| 11 | (205.97300003) | 31,187 | $1.60 | $3.24 | $5.00 | |
| 12 | (205.97400003) | 6,206,279 | $0.15 | $0.18 | $0.25 | |
| 13 | Structure Excavation (206.01) | CY | 2,680 | $62.90 | $144.00 | $35.00 |
| 14 | Trench and Culvert Excavation (206.0201) | CY | 87,034 | $105.00 | $270.00 | $50.00 |
| 15 | Conduit Excavation and Backfill including Surface Restoration (206.03) | LF | 10,627 | $27.20 | $63.00 | $63.00 |
| 16 | Test Pit Excavation (206.05) | EACH | 127 | $2,070.00 | $9,000.00 | $4,000.00 |
| 17 | Geotextile Bedding (207.20) | SY | 8,805 | $4.25 | $4.50 | $5.25 |
| 18 | Geotextile Separation (207.21) | SY | 31,803 | $3.15 | $0.90 | $2.75 |
| 19 | Prefabricated Composite Structural Drain (207.26) | SY | 280 | $19.90 | $27.00 | $28.00 |
| 20 | SWTD - Maximum Treatment Flow Rate over 1.0 cfs up to 2.0 cfs (208.5201) | EACH | 5 | $34,900 | $90,000 | $40,000 |
| 21 | SWTD - Maximum Treatment Flow Rate over 2.0 cfs up to 2.8 cfs (208.5301) | EACH | 2 | $43,400 | $90,000 | $50,000 |
| 22 | SWTD - Maximum Treatment Flow Rate over 2.8 cfs up to 3.8 cfs (208.5401) | EACH | 2 | $67,400 | $126,000 | $95,000 |
| 23 | Mulch – Temporary (209.100101) | SY | 45 | $13.40 | $36.00 | $30.00 |
| 24 | Seed and Mulch – Temporary (209.1003) | SY | 350 | $12.80 | $9.00 | $6.00 |
| 25 | Sediment Filter Log – Temporary, 12″, Type A (209.1311) | LF | 290 | $17.50 | $45.00 | $11.75 |
| 26 | Turbidity Curtain – Temporary (209.1501) | LF | 75 | $83.80 | $108.00 | $35.00 |
| 27 | Drainage Structure Inlet Protection, Catch Basin Inserts for Trash, Sediment and Debris Removal – Temporary (209.1706) | EACH | 117 | $480.00 | $306.00 | $225.00 |
| 28 | Rolled Erosion Control Product, Class II Type A, Intermediate (209.1901) | SY | 480 | $15.80 | $9.00 | $7.15 |
| 29 | Subbase Course, Optional Type (304.15) | CY | 15,420 | $138.00 | $99.00 | $115.00 |
| 30 | (404.2589) | TON | 13,729 | $161.00 | $270.00 | $130.00 |
| 31 | (406.0189) | TON | 426 | $279.00 | $450.00 | $295.00 |
| 32 | (406.0982) | TON | 3,029 | $254.00 | $234.00 | $220.00 |
| 33 | (406.1989) | TON | 4,339 | $202.00 | $172.00 | $180.00 |
| 34 | Diluted Tack Coat (407.0102) | GAL | 6,058 | $2.50 | $2.70 | $8.00 |
| 35 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 38,965 | $1.55 | $4.50 | $1.10 |
| 36 | Miscellaneous Cold Milling of Bituminous Concrete (490.30) | SY | 631 | $32.90 | $27.00 | $120.00 |
| 37 | (502.0222) | 31 | $2,170.00 | $1,890.00 | $815.00 | |
| 38 | Performance Concrete Quality Adjustment - PCC Pavement (502.99) | QUALITY UNIT | 1 | $11.00 | $11.00 | $11.00 |
| 39 | PCC Foundation for Pavement, PEM Concrete (503.1013) | CY | 413 | $1,660.00 | $1,710.00 | $1,525.00 |
| 40 | Constructing Longitudinal Joints in Foundation Pavement (503.9110) | LF | 3,838 | $24.70 | $54.00 | $14.00 |
| 41 | (510.81000018) | 2,559 | $35.70 | $54.00 | $50.00 | |
| 42 | Micropiles (Contractor Designed) (551.30) | EACH | 16 | $24,000 | $45,000 | $12,000 |
| 43 | (551.33) | 554 | $151.00 | $180.00 | $150.00 | |
| 44 | Furnishing Equipment for Installing Micropiles (551.34) | LS | 1 | $103,000 | $306,000 | $1,000,000 |
| 45 | Static Pile Compressive Load Test (551.35) | EACH | 3 | $61,700 | $72,000 | $35,000 |
| 46 | Temporary Steel Sheeting (552.13) | SF | 8,230 | $94.40 | $144.00 | $70.00 |
| 47 | Interim Steel Sheeting (552.15) | SF | 990 | $115.00 | $171.00 | $150.00 |
| 48 | Shields and Shoring (552.17) | SF | 442,206 | $22.00 | $4.50 | $10.00 |
| 49 | (552.2001) | LF | 370 | $331.00 | $450.00 | $125.00 |
| 50 | (552.2002) | LF | 1,600 | $336.00 | $450.00 | $125.00 |
| 51 | (552.2003) | LF | 1,620 | $339.00 | $450.00 | $125.00 |
| 52 | (552.2101) | LF | 10 | $890.00 | $810.00 | $0.01 |
| 53 | (552.2102) | LF | 310 | $791.00 | $810.00 | $950.00 |
| 54 | (552.2103) | LF | 400 | $798.00 | $810.00 | $950.00 |
| 55 | (552.2201) | LF | 370 | $442.00 | $54.00 | $375.00 |
| 56 | (552.2202) | LF | 1,630 | $492.00 | $54.00 | $415.00 |
| 57 | (552.2203) | LF | 1,980 | $408.00 | $54.00 | $350.00 |
| 58 | (552.230201) | SF | 1,350 | $80.10 | $27.00 | $100.00 |
| 59 | (552.230202) | SF | 7,310 | $83.60 | $90.00 | $95.00 |
| 60 | (552.230203) | SF | 7,570 | $76.70 | $117.00 | $75.00 |
| 61 | (553.020001) | EACH | 1 | $195,000 | $450,000 | $1,000,000 |
| 62 | Footing Concrete, Performance (555.0011) | CY | 141 | $1,520.00 | $1,440.00 | $2,500.00 |
| 63 | Concrete for Structures, Performance (555.0021) | CY | 770 | $2,760.00 | $2,430.00 | $2,375.00 |
| 64 | Performance Concrete Quality Adjustment – Footing Concrete (555.9901) | QUALITY UNIT | 1 | $5.50 | $5.50 | $5.50 |
| 65 | Performance Concrete Quality Adjustment – Concrete for Structures (555.9902) | QUALITY UNIT | 1 | $15.00 | $15.00 | $15.00 |
| 66 | Epoxy-Coated Bar Reinforcement for Structures (556.0202) | LB | 146,173 | $2.55 | $4.50 | $2.25 |
| 67 | Protective Sealing of New Structural Concrete (559.02) | SF | 3,310 | $4.50 | $2.70 | $1.80 |
| 68 | (559.91100010) | 350 | $7.85 | $9.00 | $21.00 | |
| 69 | Type E.P. Bearing (All Load Ranges) (565.1821) | EACH | 4 | $6,290.00 | $18,000 | $6,000.00 |
| 70 | Drilling and Grouting Bolts or Reinforcing Bars (586.0201) | EACH | 67 | $66.20 | $90.00 | $29.00 |
| 71 | (595.50000018) | 85,020 | $24.10 | $0.90 | $7.75 | |
| 72 | (601.01110001) | 348 | $114.00 | $90.00 | $215.00 | |
| 73 | (601.04030011) | 1,800 | $27.40 | $18.00 | $20.00 | |
| 74 | (603.6015) | LF | 43 | $953.00 | $4,500.00 | $875.00 |
| 75 | (603.63060615) | 108 | $2,630.00 | $6,300.00 | $1,675.00 | |
| 76 | (603.64100815) | 4,640 | $3,080.00 | $11,610 | $1,710.00 | |
| 77 | (603.64120415) | 62 | $3,080.00 | $15,400 | $2,100.00 | |
| 78 | (603.64120615) | 34 | $3,220.00 | $16,200 | $2,500.00 | |
| 79 | (603.98101004) | 2 | $401.00 | $180.00 | $650.00 | |
| 80 | (603.98101204) | 6 | $342.00 | $225.00 | $250.00 | |
| 81 | (603.9815) | LF | 4,500 | $113.00 | $297.00 | $140.00 |
| 82 | (603.9818) | LF | 296 | $130.00 | $450.00 | $170.00 |
| 83 | (603.9824) | LF | 474 | $171.00 | $540.00 | $180.00 |
| 84 | (603.9830) | LF | 170 | $247.00 | $1,080.00 | $250.00 |
| 85 | (603.9842) | LF | 116 | $347.00 | $1,540.00 | $410.00 |
| 86 | (603.9860) | LF | 59 | $481.00 | $3,600.00 | $520.00 |
| 87 | (603.99010008) | 1 | $23,500 | $90,000 | $7,400.00 | |
| 88 | (603.99100105) | LS | 1 | $2,028,000 | $450,000 | $2,000,000 |
| 89 | (603.99100205) | LS | 1 | $2,028,000 | $450,000 | $2,000,000 |
| 90 | (603.99240015) | 97 | $178.00 | $540.00 | $190.00 | |
| 91 | (603.99250015) | 3,713 | $242.00 | $720.00 | $209.00 | |
| 92 | (604.070301) | EACH | 4 | $5,420.00 | $4,500.00 | $5,000.00 |
| 93 | (604.070303) | EACH | 7 | $5,420.00 | $4,500.00 | $5,000.00 |
| 94 | (604.070305) | EACH | 1 | $5,420.00 | $4,500.00 | $4,500.00 |
| 95 | (604.070306) | EACH | 11 | $2,710.00 | $1,800.00 | $3,750.00 |
| 96 | (604.070307) | EACH | 4 | $2,700.00 | $2,700.00 | $3,250.00 |
| 97 | (604.070308) | EACH | 5 | $5,520.00 | $4,500.00 | $16,000 |
| 98 | (604.07260011) | 4 | $3,530.00 | $9,000.00 | $5,500.00 | |
| 99 | (604.300673) | LF | 476 | $822.00 | $2,700.00 | $1,350.00 |
| 100 | (604.302091) | LF | 95 | $616.00 | $2,700.00 | $950.00 |
| 101 | (604.4048) | LF | 388 | $1,250.00 | $1,260.00 | $1,050.00 |
| 102 | (604.4060) | LF | 76 | $290.00 | $1,350.00 | $650.00 |
| 103 | (604.4072) | LF | 14 | $1,090.00 | $2,700.00 | $2,400.00 |
| 104 | (604.4096) | LF | 66 | $760.00 | $1,800.00 | $1,600.00 |
| 105 | (604.500301) | LF | 19 | $9,390.00 | $22,500 | $9,000.00 |
| 106 | (604.500302) | LF | 135 | $6,450.00 | $22,500 | $9,000.00 |
| 107 | (604.500303) | LF | 20 | $7,850.00 | $22,500 | $7,500.00 |
| 108 | (604.500304) | LF | 18 | $18,200 | $32,400 | $18,500 |
| 109 | (604.500305) | LF | 18 | $16,900 | $27,000 | $25,000 |
| 110 | (604.500306) | LF | 52 | $11,700 | $27,000 | $12,000 |
| 111 | (604.500307) | LF | 14 | $16,200 | $32,500 | $21,000 |
| 112 | (604.500308) | LF | 14 | $8,420.00 | $22,500 | $9,500.00 |
| 113 | (604.500309) | LF | 15 | $5,810.00 | $18,000 | $8,000.00 |
| 114 | (604.500310) | LF | 16 | $5,700.00 | $18,000 | $9,500.00 |
| 115 | (604.500512) | LF | 114 | $9,550.00 | $22,500 | $8,000.00 |
| 116 | Underdrain Filter, Type I (605.0901) | CY | 624 | $228.00 | $90.00 | $180.00 |
| 117 | (605.1701) | LF | 7,891 | $7.65 | $36.00 | $5.00 |
| 118 | Box Beam Guide Railing (606.10) | LF | 228 | $96.00 | $72.00 | $75.00 |
| 119 | Box Beam End Piece (606.120101) | EACH | 6 | $1,270.00 | $1,008.00 | $925.00 |
| 120 | (606.71000015) | 260 | $15.10 | $12.60 | $15.00 | |
| 121 | (607.10010039) | 327 | $792.00 | $504.00 | $570.00 | |
| 122 | (607.4051) | EACH | 1 | $21,200 | $27,000 | $20,000 |
| 123 | (607.41010010) | 1,104 | $11.70 | $13.50 | $5.50 | |
| 124 | (607.95000008) | 122 | $14.40 | $45.00 | $20.00 | |
| 125 | (607.97010007) | 88 | $879.00 | $1,008.00 | $640.00 | |
| 126 | Concrete Sidewalks and Driveways (608.0101) | CY | 1,501 | $1,660.00 | $1,800.00 | $1,150.00 |
| 127 | (608.01050109) | 3 | $7,030.00 | $5,400.00 | $13,000 | |
| 128 | (608.01050309) | 8 | $10,900 | $9,000.00 | $16,000 | |
| 129 | (608.01050409) | 8 | $10,900 | $9,000.00 | $16,000 | |
| 130 | (608.01050709) | 27 | $10,800 | $9,000.00 | $16,000 | |
| 131 | (608.01050809) | 6 | $7,450.00 | $9,000.00 | $13,000 | |
| 132 | (608.01051109) | 5 | $6,070.00 | $5,400.00 | $12,000 | |
| 133 | Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102) | TON | 481 | $388.00 | $450.00 | $425.00 |
| 134 | Brick Paved Sidewalks and Driveways (Sand Setting Bed) (608.03) | SY | 1,778 | $384.00 | $450.00 | $450.00 |
| 135 | (608.41000024) | 38 | $429.00 | $450.00 | $375.00 | |
| 136 | Stone Curb – Near Vertical Face (NVF) (609.0212) | LF | 10,519 | $102.00 | $90.00 | $63.00 |
| 137 | (609.02120011) | 648 | $231.00 | $117.00 | $150.00 | |
| 138 | (609.10010404) | 190 | $30.10 | $54.00 | $58.00 | |
| 139 | Resetting Existing Curb (609.15) | LF | 465 | $89.60 | $63.00 | $62.00 |
| 140 | (609.15100011) | 550 | $44.20 | $9.00 | $50.00 | |
| 141 | Mycorrhizal Fungi (610.0701) | LB | 732 | $34.30 | $45.00 | $40.00 |
| 142 | Moisture Retention Additive (610.08) | LB | 3 | $137.00 | $36.00 | $30.00 |
| 143 | Mulch for Planting Type A, B & D Wood Chips and Shredded Bark (610.1101) | CY | 183 | $137.00 | $162.00 | $160.00 |
| 144 | Weed Removal (610.13) | SY | 52,292 | $1.05 | $1.35 | $1.35 |
| 145 | (610.14000011) | 2,391 | $224.00 | $153.00 | $275.00 | |
| 146 | Topsoil - Lawns (610.1403) | CY | 63 | $333.00 | $81.00 | $300.00 |
| 147 | Topsoil - Special Planting Mix (610.1404) | CY | 59 | $219.00 | $252.00 | $275.00 |
| 148 | Turf Establishment -Lawns (610.1602) | SY | 377 | $8.70 | $6.30 | $6.00 |
| 149 | (611.0111) | EACH | 85 | $1,370.00 | $900.00 | $890.00 |
| 150 | (611.0211) | EACH | 10 | $1,170.00 | $900.00 | $800.00 |
| 151 | (611.0412) | EACH | 5,040 | $165.00 | $63.00 | $65.00 |
| 152 | (611.0512) | EACH | 529 | $206.00 | $144.00 | $140.00 |
| 153 | (611.0611) | EACH | 5,314 | $96.00 | $5.40 | $26.50 |
| 154 | Portable Drip Irrigation System (611.17) | EACH | 95 | $11.00 | $27.00 | $36.00 |
| 155 | Removal of Portable Drip Irrigation System (611.18) | EACH | 95 | $27.40 | $36.00 | $36.00 |
| 156 | Post-Planting Care (611.19) | EACH | 6,327 | $13.70 | $27.00 | $30.00 |
| 157 | (614.060104) | EACH | 22 | $446.00 | $450.00 | $330.00 |
| 158 | (614.060204) | EACH | 26 | $747.00 | $1,080.00 | $550.00 |
| 159 | (614.060304) | EACH | 19 | $1,710.00 | $1,368.00 | $1,250.00 |
| 160 | (614.060404) | EACH | 8 | $2,060.00 | $1,980.00 | $1,500.00 |
| 161 | (615.43000011) | 414 | $29.60 | $10.80 | $12.50 | |
| 162 | (617.01030024) | 4,179 | $8.00 | $45.00 | $80.00 | |
| 163 | (617.10000024) | 4,179 | $35.00 | $45.00 | $60.00 | |
| 164 | (617.11000024) | LS | 1 | $21,300 | $5,004.00 | $5,000.00 |
| 165 | (618.71000024) | 114 | $54.90 | $13.50 | $74.00 | |
| 166 | (618.78111115) | 48 | $3,070.00 | $4,500.00 | $5,000.00 | |
| 167 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $7,398,000 | $5,476,314 | $72,000,000 |
| 168 | Type III Construction Barricades (619.04) | EACH | 1,000 | $70.40 | $63.00 | $250.00 |
| 169 | Temporary Business Signs (619.0701) | SF | 450 | $85.90 | $54.00 | $55.00 |
| 170 | (619.080101) | LF | 3,600 | $3.10 | $1.80 | $2.25 |
| 171 | (619.080201) | EACH | 2 | $206.00 | $450.00 | $150.00 |
| 172 | Cover Existing Pavement Marking Stripes (Removable Tape) (619.0803) | LF | 2,000 | $7.55 | $9.00 | $7.75 |
| 173 | Cover Existing Pavement Marking Letters or Symbols (Removable Tape) (619.0804) | EACH | 10 | $206.00 | $450.00 | $350.00 |
| 174 | (619.0901) | LF | 1,000 | $1.70 | $3.60 | $1.25 |
| 175 | (619.100101) | LF | 3,600 | $1.70 | $3.60 | $1.25 |
| 176 | (619.100201) | EACH | 2 | $309.00 | $540.00 | $230.00 |
| 177 | (619.111113) | EACH | 4 | $34,600 | $36,000 | $55,000 |
| 178 | Maintain Traffic Signal Equipment (Requirement C) Intersection (619.1613) | MONTH | 474 | $96.50 | $477.00 | $500.00 |
| 179 | Temporary Positive Barrier – Category 6 (Pinning Required) (619.1716) | LF | 740 | $143.00 | $126.00 | $40.00 |
| 180 | Temporary Impact Attenuator - Gating (Test Level 2) (619.1812) | EACH | 4 | $26,900 | $18,000 | $7,000.00 |
| 181 | Nighttime Operations (Entire Project) (619.24) | LS | 1 | $246,000 | $90,000 | $50,000 |
| 182 | Traffic Control Supervisor (619.25) | MONTH | 40 | $27,500 | $900.00 | $0.01 |
| 183 | Pavement Patching (Force Acount) (619.2601) | DOL | 10,000 | $1.00 | $1.00 | $1.00 |
| 184 | (619.28000007) | 4,800 | $32.80 | $9.00 | $16.00 | |
| 185 | (619.67020010) | LS | 1 | $58,900 | $450,000 | $1,000,000 |
| 186 | Stone Filling (Heavy) (620.05) | CY | 13 | $332.00 | $720.00 | $240.00 |
| 187 | (620.06520009) | 19 | $110.00 | $450.00 | $120.00 | |
| 188 | Bedding Material, Type 2 (620.0802) | CY | 3,903 | $212.00 | $270.00 | $190.00 |
| 189 | Survey Operations (625.01) | LS | 1 | $2,485,047 | $1,800,000 | $9,000,000 |
| 190 | Steel Pin and Cap Right of Way Markers (625.05) | EACH | 10 | $800.00 | $810.00 | $600.00 |
| 191 | (625.130001) | EACH | 1 | $253,000 | $14,400 | $150,000 |
| 192 | (627.50140008) | 11,599 | $11.50 | $9.00 | $7.00 | |
| 193 | (634.35000011) | 780 | $14.70 | $18.00 | $10.00 | |
| 194 | (634.99010017) | LS | 1 | $137,000 | $450,000 | $75,000 |
| 195 | (634.99020017) | LS | 1 | $275,000 | $900,000 | $400,000 |
| 196 | Field Laboratory (637.01) | EACH | 1 | $125,000 | $15,400 | $40,000 |
| 197 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $7,260.00 | $9,000.00 | $400.00 |
| 198 | Engineer’s Field Office – Type 4 (637.14) | MONTH | 40 | $17,000 | $11,700 | $9,000.00 |
| 199 | Rain Gauge (637.26) | EACH | 1 | $88.90 | $900.00 | $80.00 |
| 200 | Partnering Workshop (637.35) | DOL | 5,000 | $1.00 | $1.00 | $1.00 |
| 201 | Construction Testing supplies – Consumables (637.36) | DOL | 100 | $1.00 | $1.00 | $1.00 |
| 202 | (637.40000120) | 40 | $2,000.00 | $900.00 | $2,000.00 | |
| 203 | (637.40000220) | 40 | $2,000.00 | $900.00 | $2,000.00 | |
| 204 | (637.40000320) | 40 | $2,000.00 | $900.00 | $2,000.00 | |
| 205 | (637.41000115) | 40 | $178.00 | $360.00 | $170.00 | |
| 206 | (637.41000215) | 40 | $178.00 | $360.00 | $170.00 | |
| 207 | (637.41000315) | 40 | $178.00 | $360.00 | $170.00 | |
| 208 | (637.41000415) | 40 | $178.00 | $360.00 | $170.00 | |
| 209 | (637.41000515) | 40 | $178.00 | $360.00 | $170.00 | |
| 210 | (637.41000615) | 40 | $178.00 | $360.00 | $170.00 | |
| 211 | (637.41000715) | 40 | $178.00 | $360.00 | $170.00 | |
| 212 | (637.41000815) | 40 | $178.00 | $360.00 | $170.00 | |
| 213 | (637.41000915) | 40 | $178.00 | $360.00 | $170.00 | |
| 214 | (637.41001015) | 40 | $178.00 | $360.00 | $170.00 | |
| 215 | (639.21010011) | LS | 1 | $200,000 | $200,000 | $200,000 |
| 216 | Ground-Mounted Sign Panels without Z-bars (645.5101) | SF | 238 | $110.00 | $81.00 | $80.00 |
| 217 | Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102) | SF | 481 | $82.30 | $63.00 | $60.00 |
| 218 | Overhead Sign Panels (645.61) | SF | 482 | $169.00 | $9.00 | $63.00 |
| 219 | Type A Sign Posts (645.81) | EACH | 214 | $322.00 | $243.00 | $235.00 |
| 220 | (645.81090003) | 16 | $89.10 | $63.00 | $65.00 | |
| 221 | Relocate Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.31) | EACH | 38 | $329.00 | $243.00 | $240.00 |
| 222 | Remove and Store Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.41) | EACH | 53 | $110.00 | $81.00 | $80.00 |
| 223 | Remove and Dispose Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.51) | EACH | 6 | $117.00 | $90.00 | $85.00 |
| 224 | Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61) | EACH | 53 | $89.10 | $63.00 | $65.00 |
| 225 | Cast Frame F3, UnMountable Curb Box CU3 & Parallel Bar Grate 8 PCB (655.0806) | EACH | 81 | $5,330.00 | $7,200.00 | $4,200.00 |
| 226 | Parallel Bar Frame 11 PCB & Parallel Bar Grate 11 PCB (655.0902) | EACH | 20 | $3,650.00 | $2,700.00 | $2,800.00 |
| 227 | Manhole Frame & Cover (655.1202) | EACH | 72 | $3,050.00 | $1,800.00 | $3,600.00 |
| 228 | (660.21240008) | 15 | $1,780.00 | $450.00 | $850.00 | |
| 229 | (660.21320008) | 59 | $1,850.00 | $630.00 | $650.00 | |
| 230 | (662.60000115) | LS | 1 | $8,000.00 | $8,000.00 | $8,000.00 |
| 231 | (663.0104) | LF | 128 | $526.00 | $333.00 | $215.00 |
| 232 | (663.0106) | LF | 687 | $256.00 | $405.00 | $200.00 |
| 233 | (663.0108) | LF | 1,965 | $313.00 | $450.00 | $175.00 |
| 234 | (663.0110) | LF | 116 | $498.00 | $540.00 | $350.00 |
| 235 | (663.0112) | LF | 1,306 | $455.00 | $630.00 | $200.00 |
| 236 | (663.0116) | LF | 1,964 | $569.00 | $810.00 | $200.00 |
| 237 | (663.0120) | LF | 409 | $853.00 | $810.00 | $215.00 |
| 238 | (663.0124) | LF | 87 | $1,140.00 | $900.00 | $450.00 |
| 239 | (663.0136) | LF | 999 | $1,560.00 | $1,080.00 | $775.00 |
| 240 | (663.0603) | LF | 4 | $711.00 | $1,800.00 | $650.00 |
| 241 | (663.0604) | LF | 10 | $327.00 | $1,980.00 | $550.00 |
| 242 | (663.0607) | LF | 48 | $569.00 | $2,250.00 | $325.00 |
| 243 | (663.1116) | EACH | 14 | $19,900 | $11,700 | $9,000.00 |
| 244 | (663.1120) | EACH | 5 | $28,400 | $15,300 | $15,000 |
| 245 | (663.1124) | EACH | 1 | $42,700 | $22,500 | $22,500 |
| 246 | (663.1136) | EACH | 5 | $99,500 | $54,000 | $45,000 |
| 247 | (663.1206) | EACH | 18 | $4,270.00 | $1,800.00 | $2,000.00 |
| 248 | (663.1208) | EACH | 17 | $7,110.00 | $3,600.00 | $3,000.00 |
| 249 | (663.1210) | EACH | 1 | $10,700 | $4,500.00 | $4,500.00 |
| 250 | (663.1212) | EACH | 16 | $12,800 | $5,400.00 | $5,500.00 |
| 251 | (663.1301) | EACH | 16 | $19,600 | $8,100.00 | $12,000 |
| 252 | (663.160404) | EACH | 3 | $19,900 | $14,400 | $15,000 |
| 253 | (663.160606) | EACH | 7 | $21,300 | $15,300 | $15,000 |
| 254 | (663.161010) | EACH | 2 | $25,600 | $18,000 | $20,000 |
| 255 | (663.161606) | EACH | 1 | $27,000 | $18,000 | $20,000 |
| 256 | (663.163636) | EACH | 1 | $235,000 | $36,000 | $160,000 |
| 257 | Iron Water Main Fittings (3 - 8 inch diameter) (663.2001) | LB | 3,739 | $21.30 | $5.40 | $30.00 |
| 258 | Iron Water Main Fittings (10 - 16 inch diameter) (663.2002) | LB | 11,978 | $25.60 | $7.20 | $18.00 |
| 259 | Iron Water Main Fittings (18 inch diameter and larger) (663.2003) | LB | 12,392 | $35.60 | $18.00 | $22.00 |
| 260 | (663.2104) | EACH | 5 | $299.00 | $63.00 | $70.00 |
| 261 | (663.2106) | EACH | 62 | $277.00 | $81.00 | $90.00 |
| 262 | (663.2108) | EACH | 137 | $356.00 | $99.00 | $125.00 |
| 263 | (663.2110) | EACH | 4 | $512.00 | $135.00 | $170.00 |
| 264 | (663.2112) | EACH | 93 | $555.00 | $180.00 | $225.00 |
| 265 | (663.2116) | EACH | 65 | $995.00 | $297.00 | $375.00 |
| 266 | (663.2120) | EACH | 25 | $1,420.00 | $900.00 | $600.00 |
| 267 | (663.2124) | EACH | 9 | $2,130.00 | $1,260.00 | $825.00 |
| 268 | (663.2136) | EACH | 19 | $5,690.00 | $2,700.00 | $2,500.00 |
| 269 | (663.2603) | EACH | 1 | $1,420.00 | $360.00 | $2,500.00 |
| 270 | (663.2604) | EACH | 1 | $1,710.00 | $405.00 | $2,500.00 |
| 271 | (663.2607) | EACH | 4 | $3,980.00 | $900.00 | $3,500.00 |
| 272 | (663.4106) | LF | 1,374 | $65.10 | $153.00 | $90.00 |
| 273 | (663.4108) | LF | 538 | $72.70 | $270.00 | $90.00 |
| 274 | (663.4112) | LF | 1,646 | $91.70 | $63.00 | $90.00 |
| 275 | (663.4116) | LF | 1,914 | $129.00 | $90.00 | $90.00 |
| 276 | (663.4120) | LF | 278 | $141.00 | $180.00 | $110.00 |
| 277 | (663.4124) | LF | 88 | $222.00 | $180.00 | $110.00 |
| 278 | (663.4136) | LF | 1,001 | $221.00 | $18.00 | $110.00 |
| 279 | Remove and Dispose of Existing Hydrant (663.43) | EACH | 17 | $1,400.00 | $945.00 | $2,500.00 |
| 280 | Remove and Dispose of Existing Water Service Connection (663.44) | EACH | 22 | $1,120.00 | $810.00 | $3,000.00 |
| 281 | (665.20000011) | 37 | $599.00 | $360.00 | $1,000.00 | |
| 282 | (670.0106) | EACH | 48 | $4,100.00 | $4,500.00 | $4,500.00 |
| 283 | (670.0108) | EACH | 32 | $4,210.00 | $4,870.00 | $5,000.00 |
| 284 | (670.15100108) | 32 | $35,700 | $23,400 | $7,000.00 | |
| 285 | (670.15100208) | 45 | $18,600 | $12,510 | $8,000.00 | |
| 286 | (670.2602) | LF | 9,434 | $6.15 | $9.00 | $14.00 |
| 287 | Pullboxes over 7 1/2 to 10 cubic feet, inside volume (Lighting) (670.3010) | EACH | 39 | $2,750.00 | $2,070.00 | $3,600.00 |
| 288 | (670.7004) | LF | 32,608 | $4.05 | $3.60 | $2.00 |
| 289 | Ground Wire No. 6 AWG. (670.7501) | LF | 800 | $4.05 | $2.70 | $2.25 |
| 290 | Remove and Store Lamppost Assembly (670.80) | EACH | 14 | $848.00 | $810.00 | $1,500.00 |
| 291 | Remove and Dispose of Lamppost Assembly (670.81) | EACH | 48 | $668.00 | $1,080.00 | $1,250.00 |
| 292 | Remove Lamppost Foundation (670.82) | EACH | 62 | $820.00 | $450.00 | $1,500.00 |
| 293 | Relocate Lamppost Assembly (670.90) | EACH | 3 | $5,890.00 | $2,430.00 | $3,250.00 |
| 294 | (670.91010011) | 6 | $283.00 | $855.00 | $300.00 | |
| 295 | Performance Concrete Quality Adjustment (670.99) | QUALITY UNIT | 1 | $21.89 | $21.89 | $21.89 |
| 296 | (680.05010007) | 9 | $42,700 | $34,200 | $35,000 | |
| 297 | (680.05020007) | 4 | $6,060.00 | $4,950.00 | $6,000.00 | |
| 298 | (680.10010001) | 27 | $4,470.00 | $756.00 | $2,750.00 | |
| 299 | (680.10020001) | 30 | $3,580.00 | $720.00 | $2,350.00 | |
| 300 | (680.10040001) | 30 | $276.00 | $288.00 | $175.00 | |
| 301 | (680.10050001) | 12 | $186.00 | $648.00 | $850.00 | |
| 302 | Pole Excavation and Concrete Foundation (680.5001) | CY | 114 | $2,940.00 | $4,860.00 | $2,300.00 |
| 303 | (680.510301) | EACH | 20 | $2,750.00 | $2,160.00 | $2,500.00 |
| 304 | (680.510401) | EACH | 4 | $3,070.00 | $2,493.00 | $3,000.00 |
| 305 | (680.510501) | EACH | 20 | $2,240.00 | $2,250.00 | $2,000.00 |
| 306 | (680.520106) | LF | 200 | $43.40 | $24.30 | $35.00 |
| 307 | (680.520108) | LF | 1,010 | $44.00 | $51.30 | $40.00 |
| 308 | (680.520110) | LF | 180 | $138.00 | $66.70 | $48.00 |
| 309 | (680.520706) | LF | 300 | $9.80 | $8.10 | $25.00 |
| 310 | (680.520708) | LF | 1,740 | $10.80 | $12.60 | $26.00 |
| 311 | (680.622031) | EACH | 2 | $19,300 | $15,300 | $16,000 |
| 312 | (680.622033) | EACH | 3 | $15,250 | $16,200 | $17,000 |
| 313 | (680.622034) | EACH | 1 | $21,700 | $18,000 | $17,000 |
| 314 | (680.622035) | EACH | 1 | $21,900 | $16,200 | $17,000 |
| 315 | (680.622036) | EACH | 3 | $20,500 | $17,100 | $17,000 |
| 316 | (680.622037) | EACH | 2 | $20,600 | $17,100 | $17,000 |
| 317 | (680.622038) | EACH | 1 | $20,800 | $18,000 | $17,000 |
| 318 | (680.622039) | EACH | 1 | $21,000 | $17,100 | $18,000 |
| 319 | (680.622040) | EACH | 2 | $22,300 | $18,540 | $18,000 |
| 320 | (680.622041) | EACH | 1 | $21,900 | $20,700 | $18,000 |
| 321 | (680.622042) | EACH | 2 | $22,100 | $20,700 | $18,000 |
| 322 | (680.622043) | EACH | 1 | $22,500 | $20,700 | $19,000 |
| 323 | (680.622044) | EACH | 1 | $22,900 | $20,700 | $19,000 |
| 324 | (680.622048) | EACH | 1 | $28,400 | $22,500 | $23,000 |
| 325 | (680.622053) | EACH | 1 | $31,500 | $27,000 | $26,000 |
| 326 | (680.622057) | EACH | 1 | $34,400 | $32,400 | $26,000 |
| 327 | (680.622058) | EACH | 1 | $32,800 | $27,000 | $27,000 |
| 328 | (680.632032) | EACH | 1 | $32,900 | $27,000 | $24,000 |
| 329 | (680.632048) | EACH | 1 | $44,600 | $30,600 | $35,000 |
| 330 | (680.632052) | EACH | 1 | $52,600 | $36,000 | $40,000 |
| 331 | (680.670801) | EACH | 3 | $2,060.00 | $2,457.00 | $1,600.00 |
| 332 | (680.670802) | EACH | 15 | $1,910.00 | $2,430.00 | $1,700.00 |
| 333 | (680.681001) | EACH | 12 | $2,140.00 | $2,430.00 | $1,800.00 |
| 334 | Riser Assembly, 1-inch Diameter (680.700603) | EACH | 8 | $930.00 | $1,350.00 | $2,200.00 |
| 335 | Riser Assembly, 1-1/ 2-inch Diameter (680.700604) | EACH | 6 | $985.00 | $1,350.00 | $2,400.00 |
| 336 | Riser Assembly, 2-inch Diameter (680.700606) | EACH | 1 | $999.00 | $540.00 | $2,750.00 |
| 337 | (680.730514) | LF | 4,040 | $6.05 | $5.40 | $4.00 |
| 338 | (680.730714) | LF | 13,970 | $8.35 | $5.40 | $5.25 |
| 339 | (680.77000105) | 1 | $1,960.00 | $2,970.00 | $5,500.00 | |
| 340 | (680.78010005) | 1 | $310.00 | $549.00 | $800.00 | |
| 341 | (680.79000105) | 9 | $11,000 | $18,000 | $9,000.00 | |
| 342 | (680.80324515) | 2 | $3,480.00 | $3,600.00 | $4,000.00 | |
| 343 | (680.80370501) | 6 | $36,600 | $27,000 | $27,000 | |
| 344 | Traffic Signal Module - 12-inch, Red Ball, LED (680.810101) | EACH | 60 | $107.50 | $108.00 | $325.00 |
| 345 | Traffic Signal Module - 12-inch, Yellow Ball, LED (680.810103) | EACH | 56 | $147.00 | $108.00 | $325.00 |
| 346 | Traffic Signal Module - 12-inch, Green Ball, LED (680.810105) | EACH | 56 | $147.00 | $108.00 | $325.00 |
| 347 | Traffic Signal Section - Polycarbonate, Type I, 12-inch (680.810601) | EACH | 180 | $241.00 | $279.00 | $225.00 |
| 348 | Traffic Signal Bracket Assembly - 1 Way (680.8111) | EACH | 32 | $510.00 | $540.00 | $300.00 |
| 349 | (680.81230008) | 44 | $758.00 | $720.00 | $425.00 | |
| 350 | Pedestrian Signal Module - 12-inch, Bi-Modal Hand/Man Symbols, LED (680.813105) | EACH | 68 | $309.00 | $225.00 | $350.00 |
| 351 | Pedestrian Signal Section - Polycarbonate, Type I, 12-inch (680.813106) | EACH | 136 | $393.00 | $450.00 | $325.00 |
| 352 | Pedestrian Signal Bracket Mount Assembly (680.8141) | EACH | 47 | $655.00 | $900.00 | $500.00 |
| 353 | Pedestrian Signal Post Top Mount Assembly (680.8142) | EACH | 12 | $510.00 | $1,260.00 | $450.00 |
| 354 | Pedestrian Signal Module - 12-inch Countdown Timer, LED (680.815001) | EACH | 68 | $309.00 | $252.00 | $350.00 |
| 355 | (680.8151) | EACH | 68 | $1,450.00 | $1,440.00 | $1,900.00 |
| 356 | Backplates for Traffic Signal Heads (680.8199) | EACH | 60 | $345.00 | $450.00 | $450.00 |
| 357 | (680.8205) | EACH | 14 | $1,180.00 | $900.00 | $1,250.00 |
| 358 | (680.8207) | EACH | 26 | $1,170.00 | $810.00 | $1,250.00 |
| 359 | Breakaway Transformer Base (680.8223) | EACH | 11 | $1,280.00 | $1,260.00 | $1,250.00 |
| 360 | (680.90920001) | 4 | $1,100.00 | $1,800.00 | $3,250.00 | |
| 361 | (680.90920103) | 4 | $630.00 | $1,980.00 | $3,250.00 | |
| 362 | Install Electrical Disconnect/Generator Transfer Switch (680.9499) | EACH | 8 | $958.00 | $378.00 | $2,200.00 |
| 363 | (680.950106) | LF | 720 | $3.45 | $3.60 | $10.50 |
| 364 | (680.96460011) | 5 | $6,510.00 | $3,600.00 | $15,000 | |
| 365 | Performance Concrete Quality Adjustment (680.99) | QUALITY UNIT | 1 | $12.50 | $12.50 | $12.50 |
| 366 | (683.90000002) | 1 | $2,380.00 | $2,790.00 | $50,000 | |
| 367 | (683.95050010) | 5 | $4,790.00 | $3,600.00 | $12,000 | |
| 368 | White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102) | LF | 10,088 | $2.00 | $2.70 | $1.45 |
| 369 | Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202) | LF | 12,002 | $2.00 | $2.70 | $1.45 |
| 370 | White Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3104) | LF | 43,074 | $4.05 | $4.50 | $2.95 |
| 371 | Yellow Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3204) | LF | 1,260 | $4.05 | $4.50 | $2.95 |
| 372 | White Epoxy Reflectorized Pavement Letters - 20 mil Portable/Hand Application (685.3304) | EACH | 89 | $206.00 | $153.00 | $150.00 |
| 373 | White Epoxy Reflectorized Pavement Symbols - 20 mil Portable/Hand Application (685.3404) | EACH | 43 | $391.00 | $360.00 | $290.00 |
| 374 | (686.05000011) | 10 | $9,600.00 | $7,200.00 | $5,000.00 | |
| 375 | (691.04000020) | 437,000 | $1.00 | $1.00 | $1.00 | |
| 376 | (691.14000015) | 1,145,000 | $1.00 | $1.00 | $1.00 | |
| 377 | (695.33140103) | 1 | $15,000 | $32,400 | $50,000 | |
| 378 | (695.33140203) | 1 | $15,000 | $32,400 | $50,000 | |
| 379 | (695.33140303) | 1 | $15,000 | $32,400 | $50,000 | |
| 380 | (695.33140403) | 1 | $15,000 | $32,400 | $50,000 | |
| 381 | (695.33140503) | 1 | $15,000 | $32,400 | $50,000 | |
| 382 | (695.33140603) | 1 | $15,000 | $32,400 | $50,000 | |
| 383 | (695.33140703) | 1 | $15,000 | $32,400 | $50,000 | |
| 384 | (695.33140803) | 1 | $15,000 | $32,400 | $50,000 | |
| 385 | (695.33140903) | 1 | $15,000 | $32,400 | $50,000 | |
| 386 | (695.33141003) | 1 | $15,000 | $32,400 | $50,000 | |
| 387 | (695.33141103) | 1 | $15,000 | $32,400 | $50,000 | |
| 388 | (695.33141203) | 1 | $15,000 | $32,400 | $50,000 | |
| 389 | (695.33141303) | 1 | $15,000 | $32,400 | $50,000 | |
| 390 | (695.33141403) | 1 | $15,000 | $32,400 | $50,000 | |
| 391 | (695.33141503) | 1 | $15,000 | $32,400 | $50,000 | |
| 392 | (695.33141603) | 1 | $15,000 | $32,400 | $50,000 | |
| 393 | (695.33141703) | 1 | $15,000 | $32,400 | $50,000 | |
| 394 | (695.33141803) | 1 | $15,000 | $32,400 | $50,000 | |
| 395 | (695.33141903) | 1 | $15,000 | $32,400 | $50,000 | |
| 396 | (695.33142003) | 1 | $15,000 | $32,400 | $50,000 | |
| 397 | (695.33142103) | 1 | $15,000 | $32,400 | $50,000 | |
| 398 | (695.33142203) | 1 | $15,000 | $32,400 | $50,000 | |
| 399 | (695.33142303) | 1 | $15,000 | $32,400 | $50,000 | |
| 400 | (695.33142403) | 1 | $15,000 | $32,400 | $50,000 | |
| 401 | (695.33142503) | 1 | $15,000 | $32,400 | $50,000 | |
| 402 | (695.33142603) | 1 | $15,000 | $32,400 | $50,000 | |
| 403 | (695.33142703) | 1 | $15,000 | $32,400 | $50,000 | |
| 404 | (695.33142803) | 1 | $15,000 | $32,400 | $50,000 | |
| 405 | (695.33142903) | 1 | $15,000 | $32,400 | $50,000 | |
| 406 | (695.33143003) | 1 | $15,000 | $32,400 | $50,000 | |
| 407 | (695.33143103) | 1 | $15,000 | $32,400 | $50,000 | |
| 408 | (695.33143203) | 1 | $15,000 | $32,400 | $50,000 | |
| 409 | (695.33143303) | 1 | $15,000 | $32,400 | $50,000 | |
| 410 | (695.33143403) | 1 | $15,000 | $32,400 | $50,000 | |
| 411 | (695.33143503) | 1 | $15,000 | $32,400 | $50,000 | |
| 412 | Field Change Payment (FCP) (697.03) | DOL | 6,670,000 | $1.00 | $1.00 | $1.00 |
| 413 | Asphalt Price Adjustment (698.04) | DOL | 9,869 | $1.00 | $1.00 | $1.00 |
| 414 | Fuel Price Adjustment (698.05) | DOL | 3,504 | $1.00 | $1.00 | $1.00 |
| 415 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 |
| 416 | Mobilization (699.040001) | LS | 1 | $5,506,714 | $7,600,000 | $7,841,500 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of July 30, 2026. Compiled by Mirage Metrics.