NYSDOT contract D265652 bid tabulation
SAFETY ENHACEMENTS ESTIMATE SUMMARY. Let by New York State DOT on February 26, 2026, Nassau, Suffolk, Region 10. 2 bids received; low bid $6,891,959 by GGG Construction Corp.
- Owner
- New York State DOT
- Letting
- 26 FEB 2026
- Pay items
- 166
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | GGG Construction Corp | $6,891,959 | Low |
| 2 | Quintal Contracting Corp | $7,520,114 | +9.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. GGG Construction Corp | 2. Quintal Contracting Corp |
|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.06) | LS | 1 | $35,000 | $10,000 |
| 2 | Unclassified Excavation and Disposal (203.02) | CY | 1,188 | $150.00 | $105.00 |
| 3 | (203.02990006) | 240 | $150.00 | $60.00 | |
| 4 | Embankment In Place (203.03) | CY | 573 | $50.00 | $87.00 |
| 5 | Select Granular Fill (203.07) | CY | 427 | $35.00 | $87.00 |
| 6 | Trench and Culvert Excavation (206.0201) | CY | 1,053 | $25.00 | $90.00 |
| 7 | (206.03100010) | 55 | $150.00 | $100.00 | |
| 8 | Test Pit Excavation (206.05) | EACH | 9 | $1,500.00 | $1,200.00 |
| 9 | SWTD - Maximum Treatment Flow Rate over 5.0 cfs up to 7.0 cfs (208.5601) | EACH | 1 | $150,000 | $140,000 |
| 10 | (209.11010024) | 14 | $200.00 | $425.00 | |
| 11 | (304.10119917) | 453 | $150.00 | $140.00 | |
| 12 | Pavement Density Quality Adjustment to Asphalt Items (404.0002) | QUALITY UNIT | 678 | $90.31 | $90.31 |
| 13 | Longitudinal Joint Density Quality Adjustment to Asphalt Items (404.0003) | QUALITY UNIT | 526 | $103.49 | $103.49 |
| 14 | (404.0189) | TON | 239 | $300.00 | $495.00 |
| 15 | (404.0961) | TON | 585 | $300.00 | $495.00 |
| 16 | (404.1289) | TON | 174 | $300.00 | $495.00 |
| 17 | (404.1989) | TON | 159 | $300.00 | $495.00 |
| 18 | (404.3789) | TON | 3,812 | $125.00 | $375.00 |
| 19 | Diluted Tack Coat (407.0102) | GAL | 4,442 | $12.00 | $24.00 |
| 20 | Bituminous Material (Chip Seal) (410.30) | GAL | 1 | $5,000.00 | $750.00 |
| 21 | (413.04030118) | 1 | $5,000.00 | $7,500.00 | |
| 22 | (415.03010118) | 1 | $5,000.00 | $9,500.00 | |
| 23 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 2,828 | $10.00 | $5.75 |
| 24 | Production Cold Milling of Bituminous Concrete (490.10) | SY | 3,645 | $25.00 | $24.50 |
| 25 | (502.9100) | 3,164 | $30.00 | $25.00 | |
| 26 | Longitudinal Joints (502.9110) | LF | 2,912 | $15.00 | $25.00 |
| 27 | Sealing Transverse Joints- Highway Joint Sealant (502.9210) | LF | 3,595 | $18.00 | $7.50 |
| 28 | Sealing Longitudinal Joints-Highway Joint Sealant (502.9310) | LF | 2,912 | $18.00 | $8.00 |
| 29 | PCC Foundation for Pavement, PEM Concrete (503.1013) | CY | 142 | $1,750.00 | $1,500.00 |
| 30 | Production Grinding – Pavement Preservation with Slurry Removal (505.0402) | SY | 121,986 | $12.50 | $8.75 |
| 31 | (510.81000018) | 4,112 | $35.00 | $56.00 | |
| 32 | (511.10000018) | 6 | $3,000.00 | $1,000.00 | |
| 33 | (520.05000010) | 370 | $12.00 | $9.00 | |
| 34 | (520.09000010) | 1,909 | $9.00 | $8.00 | |
| 35 | Temporary Timber Sheeting (552.12) | SF | 5,403 | $7.50 | $25.00 |
| 36 | Interim Timber Sheeting (552.14) | SF | 96 | $30.00 | $85.00 |
| 37 | Shields and Shoring (552.17) | SF | 3,009 | $5.00 | $20.00 |
| 38 | Concrete for Structures, Performance (555.0021) | CY | 37 | $2,500.00 | $2,000.00 |
| 39 | (555.72950010) | 186 | $100.00 | $155.00 | |
| 40 | Performance Concrete Quality Adjustment – Concrete for Structures (555.9902) | QUALITY UNIT | 1 | $9.32 | $9.32 |
| 41 | Epoxy-Coated Bar Reinforcement for Structures (556.0202) | LB | 3,190 | $6.00 | $4.00 |
| 42 | (559.91100010) | 186 | $40.00 | $18.00 | |
| 43 | (603.6002) | LF | 408 | $200.00 | $275.00 |
| 44 | (603.6003) | LF | 87 | $200.00 | $300.00 |
| 45 | (604.07240110) | 2 | $6,000.00 | $10,000 | |
| 46 | (604.07260011) | 1 | $5,000.00 | $15,000 | |
| 47 | (604.501011) | LF | 11 | $2,000.00 | $2,500.00 |
| 48 | (604.501012) | LF | 27 | $2,500.00 | $1,250.00 |
| 49 | (604.501023) | LF | 8 | $2,750.00 | $1,900.00 |
| 50 | (604.50180010) | 19 | $4,000.00 | $1,500.00 | |
| 51 | (608.01020005) | 9 | $1,800.00 | $2,900.00 | |
| 52 | (608.01050010) | 60 | $1,500.00 | $1,400.00 | |
| 53 | (608.01050109) | 2 | $7,500.00 | $7,500.00 | |
| 54 | (608.01050309) | 1 | $8,000.00 | $14,000 | |
| 55 | (608.02010015) | 26 | $150.00 | $375.00 | |
| 56 | (608.02020015) | 92 | $150.00 | $100.00 | |
| 57 | (609.0405) | LF | 61 | $105.00 | $65.00 |
| 58 | (609.0406) | LF | 392 | $105.00 | $90.00 |
| 59 | (609.0407) | LF | 129 | $105.00 | $115.00 |
| 60 | Optional Curb (Precast Concrete Type PVF6 or Cast-In-Place Concrete Type VF6 or Stone Type NVF) (609.0901) | LF | 563 | $105.00 | $65.00 |
| 61 | Mycorrhizal Fungi (610.0701) | LB | 5 | $85.00 | $200.00 |
| 62 | Moisture Retention Additive (610.08) | LB | 24 | $50.00 | $100.00 |
| 63 | Topsoil - Roadside (610.1402) | CY | 48 | $150.00 | $79.00 |
| 64 | Turf Establishment - Roadside (610.1601) | SY | 430 | $8.50 | $4.75 |
| 65 | Wildflower Seeding (610.17) | SY | 693 | $10.00 | $10.00 |
| 66 | Watering Vegetation (610.19) | 1,000 GALLONS | 4 | $600.00 | $2,000.00 |
| 67 | Mowing Limits Markers (610.22) | EACH | 7 | $150.00 | $15.00 |
| 68 | (611.0161) | EACH | 6 | $1,500.00 | $950.00 |
| 69 | (611.0461) | EACH | 15 | $150.00 | $200.00 |
| 70 | (611.0561) | EACH | 15 | $135.00 | $250.00 |
| 71 | (611.19010024) | 6 | $325.00 | $600.00 | |
| 72 | (611.19040024) | 15 | $65.00 | $150.00 | |
| 73 | (611.19050024) | 15 | $50.00 | $250.00 | |
| 74 | (614.060104) | EACH | 3 | $1,000.00 | $350.00 |
| 75 | (614.060204) | EACH | 19 | $1,800.00 | $875.00 |
| 76 | (614.060304) | EACH | 3 | $3,250.00 | $1,500.00 |
| 77 | (614.060404) | EACH | 1 | $4,000.00 | $1,900.00 |
| 78 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $500,000 | $585,000 |
| 79 | Type III Construction Barricades (619.04) | EACH | 21 | $350.00 | $50.00 |
| 80 | (619.080102) | LF | 1,624 | $2.50 | $3.50 |
| 81 | (619.100102) | LF | 8,132 | $1.10 | $1.25 |
| 82 | (619.100202) | EACH | 2 | $230.00 | $280.00 |
| 83 | (619.100302) | EACH | 8 | $170.00 | $280.00 |
| 84 | (619.10050020) | 600 | $6.00 | $12.00 | |
| 85 | (619.111133) | EACH | 16 | $10,000 | $5,000.00 |
| 86 | Maintain Traffic Signal Equipment (Requirement A) Intersection (619.1611) | MONTH | 18 | $529.00 | $650.00 |
| 87 | Temporary Positive Barrier – Category 2 (Pinning Permitted) (619.1712) | LF | 80 | $150.00 | $175.00 |
| 88 | Warning Lights on Temporary Positive Barriers (619.1719) | EACH | 4 | $100.00 | $100.00 |
| 89 | Temporary Impact Attenuator - Redirective (Test Level 3) (619.1803) | EACH | 1 | $7,500.00 | $10,000 |
| 90 | Nighttime Operations (Entire Project) (619.24) | LS | 1 | $250,000 | $795.00 |
| 91 | Cleaning Closed Drainage Systems (621.03) | LF | 24 | $50.00 | $200.00 |
| 92 | Cleaning Drainage Structures (621.04) | EACH | 5 | $1,500.00 | $1,500.00 |
| 93 | Crushed Stone (In-Place Measure) (623.12) | CY | 6 | $200.00 | $120.00 |
| 94 | (623.12010004) | 10 | $200.00 | $125.00 | |
| 95 | Survey Operations (625.01) | LS | 1 | $50,000 | $50,000 |
| 96 | Cleaning, Sealing and/or Filling Cracks (633.12) | LS | 1 | $15,000 | $18,000 |
| 97 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $2,000.00 | $4,000.00 |
| 98 | Engineer’s Field Office – Type 3 (637.13) | MONTH | 14 | $5,500.00 | $7,500.00 |
| 99 | Office Technology and Supplies (637.34) | DOL | 5,000 | $1.00 | $1.00 |
| 100 | Construction Testing supplies – Consumables (637.36) | DOL | 100 | $1.00 | $1.00 |
| 101 | (637.41000115) | 14 | $500.00 | $300.00 | |
| 102 | (637.41000215) | 14 | $500.00 | $300.00 | |
| 103 | (637.41000315) | 14 | $500.00 | $300.00 | |
| 104 | (637.41000415) | 14 | $500.00 | $300.00 | |
| 105 | (637.41000515) | 14 | $500.00 | $300.00 | |
| 106 | Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102) | SF | 26 | $150.00 | $500.00 |
| 107 | Type A Sign Posts (645.81) | EACH | 5 | $500.00 | $350.00 |
| 108 | (647.18010108) | 1 | $2,500.00 | $2,500.00 | |
| 109 | Relocate Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.31) | EACH | 3 | $2,000.00 | $1,500.00 |
| 110 | Remove and Store Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.41) | EACH | 1 | $1,500.00 | $800.00 |
| 111 | Remove and Dispose Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.51) | EACH | 3 | $1,500.00 | $700.00 |
| 112 | Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61) | EACH | 4 | $2,000.00 | $750.00 |
| 113 | (655.07030010) | 1 | $3,000.00 | $3,500.00 | |
| 114 | Cast Frame F3, UnMountable Curb Box CU3 & Reticuline Grate G3 (655.0706) | EACH | 10 | $3,500.00 | $3,000.00 |
| 115 | Manhole Frame & Cover (655.1202) | EACH | 5 | $2,000.00 | $1,575.00 |
| 116 | Adjust Existing Valve Box Elevation (663.33) | EACH | 1 | $500.00 | $1,500.00 |
| 117 | (680.05010007) | 1 | $36,655 | $43,030 | |
| 118 | (680.05020007) | 1 | $4,746.00 | $6,500.00 | |
| 119 | Pole Excavation and Concrete Foundation (680.5001) | CY | 18 | $2,700.00 | $1,500.00 |
| 120 | (680.51050010) | 2 | $3,500.00 | $3,500.00 | |
| 121 | (680.520103) | LF | 16 | $62.00 | $80.00 |
| 122 | (680.520106) | LF | 25 | $48.00 | $80.00 |
| 123 | (680.520108) | LF | 14 | $58.00 | $80.00 |
| 124 | (680.520110) | LF | 16 | $83.00 | $97.00 |
| 125 | Single Span Wire Assembly (680.7001) | EACH | 2 | $3,137.00 | $3,683.00 |
| 126 | (680.730214) | LF | 182 | $16.00 | $19.00 |
| 127 | (680.730514) | LF | 4,407 | $5.00 | $5.25 |
| 128 | (680.731014) | LF | 1,247 | $7.00 | $7.30 |
| 129 | (680.79400010) | 1 | $1,000.00 | $497.00 | |
| 130 | (680.79490010) | 1 | $1,500.00 | $2,500.00 | |
| 131 | Traffic Signal Module - 12-inch, Red Ball, LED (680.810101) | EACH | 10 | $183.00 | $215.00 |
| 132 | Traffic Signal Module - 12-inch, Red Arrow, LED (680.810102) | EACH | 5 | $214.00 | $251.00 |
| 133 | Traffic Signal Module - 12-inch, Yellow Ball, LED (680.810103) | EACH | 10 | $183.00 | $215.00 |
| 134 | Traffic Signal Module - 12-inch, Yellow Arrow, LED (680.810104) | EACH | 10 | $192.00 | $225.00 |
| 135 | Traffic Signal Module - 12-inch, Green Ball, LED (680.810105) | EACH | 10 | $183.00 | $215.00 |
| 136 | Traffic Signal Module - 12-inch, Green Arrow, LED (680.810106) | EACH | 7 | $207.00 | $243.00 |
| 137 | Traffic Signal Section - Polycarbonate, Type I, 12-inch (680.810601) | EACH | 52 | $533.00 | $625.00 |
| 138 | Traffic Signal Bracket Assembly - 1 Way (680.8111) | EACH | 15 | $607.00 | $713.00 |
| 139 | Traffic Signal Bracket Assembly - 2 Way (680.8112) | EACH | 3 | $1,031.00 | $1,210.00 |
| 140 | Pedestrian Signal Section, Aluminum, Type I, for 16 inches by 18 inches LED module (680.813108) | EACH | 1 | $690.00 | $810.00 |
| 141 | Pedestrian Signal Bracket Mount Assembly (680.8141) | EACH | 1 | $519.00 | $609.00 |
| 142 | Pedestrian Signal Module - 16-inch x 18-inch, Bi-Modal Hand/Man Symbols with Countdown Timer, LED (680.815002) | EACH | 1 | $455.00 | $533.00 |
| 143 | (680.8151) | EACH | 6 | $1,350.00 | $1,585.00 |
| 144 | (680.8152) | EACH | 2 | $4,200.00 | $2,945.00 |
| 145 | Backplates for Traffic Signal Heads (680.8199) | EACH | 15 | $641.00 | $752.00 |
| 146 | (680.8204) | EACH | 4 | $1,330.00 | $1,560.00 |
| 147 | (680.8207) | EACH | 2 | $1,467.00 | $1,683.50 |
| 148 | (680.82250101) | 7 | $212.00 | $248.00 | |
| 149 | (680.82507010) | 1 | $2,100.00 | $2,465.00 | |
| 150 | (680.82540009) | 1,007 | $6.00 | $6.60 | |
| 151 | (680.83200010) | LS | 1 | $1,668.00 | $5,000.00 |
| 152 | (680.85166010) | 1 | $48,865 | $57,363 | |
| 153 | (680.85166510) | 1 | $49,753 | $58,405 | |
| 154 | Performance Concrete Quality Adjustment (680.99) | QUALITY UNIT | 2 | $11.00 | $11.00 |
| 155 | (680.99100010) | 1 | $6,342.00 | $7,445.00 | |
| 156 | (685.07150110) | 17,661 | $1.10 | $1.05 | |
| 157 | (685.07150310) | 14 | $205.00 | $222.75 | |
| 158 | (685.07150410) | 2,904 | $2.50 | $2.65 | |
| 159 | (685.07150610) | 14,245 | $1.10 | $1.05 | |
| 160 | (685.07150710) | 210 | $2.50 | $2.65 | |
| 161 | (685.07150810) | 9 | $55.00 | $60.00 | |
| 162 | Field Change Payment (FCP) (697.03) | DOL | 230,000 | $1.00 | $1.00 |
| 163 | Asphalt Price Adjustment (698.04) | DOL | 6,211 | $1.00 | $1.00 |
| 164 | Fuel Price Adjustment (698.05) | DOL | 1,085 | $1.00 | $1.00 |
| 165 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 |
| 166 | Mobilization (699.040001) | LS | 1 | $265,075 | $287,748 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of February 26, 2026. Compiled by Mirage Metrics.