NYSDOT contract D265848 bid tabulation
SIGNAL UPGRADES ROUTE 9 TOWN OF FISHKILL. Let by New York State DOT on October 15, 2026, Dutchess, Region 08. 3 bids received; low bid $599,180 by Power Line Constructors Inc.
- Owner
- New York State DOT
- Letting
- 15 OCT 2026
- Pay items
- 49
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Power Line Constructors Inc | $599,180 | Low |
| 2 | Stilsing Electric Inc | $620,336 | +4.0% |
| 3 | Binghamton Road Electric LLC | $690,729 | +15% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Power Line Constructors Inc | 2. Stilsing Electric Inc | 3. Binghamton Road Electric LLC |
|---|---|---|---|---|---|---|
| 1 | Surface-Applied Detectable Warning Units (608.20) | SY | 26 | $794.00 | $865.00 | $370.00 |
| 2 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $143,046 | $159,200 | $167,000 |
| 3 | (619.110513) | EACH | 4 | $11,749 | $6,200.00 | $27,650 |
| 4 | Maintain Traffic Signal Equipment (Requirement B) Intersection (619.1612) | MONTH | 9 | $350.00 | $140.00 | $600.00 |
| 5 | Engineer’s Field Office – Type 2 (637.12) | MONTH | 12 | $3,467.00 | $2,100.00 | $3,025.00 |
| 6 | Office Technology and Supplies (637.34) | DOL | 2,000 | $1.00 | $1.00 | $1.00 |
| 7 | (662.60000108) | 2,000 | $1.00 | $1.00 | $1.00 | |
| 8 | (680.05010007) | 2 | $32,370 | $32,100 | $32,658 | |
| 9 | (680.05020007) | 2 | $4,843.00 | $6,200.00 | $5,265.00 | |
| 10 | (680.51100010) | 12 | $135.00 | $280.00 | $435.00 | |
| 11 | (680.53010010) | 575 | $7.48 | $8.75 | $9.00 | |
| 12 | Dual Span Wire Assembly with Upper Tether Wire (680.7002) | EACH | 3 | $5,467.00 | $4,900.00 | $5,927.00 |
| 13 | (680.730214) | LF | 75 | $2.82 | $5.00 | $3.00 |
| 14 | (680.730514) | LF | 7,450 | $4.13 | $6.40 | $4.00 |
| 15 | (680.731014) | LF | 1,550 | $8.66 | $9.35 | $7.00 |
| 16 | (680.78020008) | 3 | $332.00 | $2,000.00 | $870.00 | |
| 17 | (680.78030008) | 21 | $164.00 | $310.00 | $167.00 | |
| 18 | (680.78040008) | 3 | $349.00 | $750.00 | $1,300.00 | |
| 19 | (680.80324515) | 3 | $2,956.00 | $3,300.00 | $3,597.00 | |
| 20 | (680.80324708) | 2 | $1,611.00 | $1,840.00 | $1,677.00 | |
| 21 | Traffic Signal Module - 12-inch, Red Ball, LED (680.810101) | EACH | 27 | $90.02 | $185.00 | $131.00 |
| 22 | Traffic Signal Module - 12-inch, Red Arrow, LED (680.810102) | EACH | 5 | $98.80 | $185.00 | $139.00 |
| 23 | Traffic Signal Module - 12-inch, Yellow Ball, LED (680.810103) | EACH | 25 | $90.02 | $185.00 | $131.00 |
| 24 | Traffic Signal Module - 12-inch, Yellow Arrow, LED (680.810104) | EACH | 10 | $98.80 | $185.00 | $139.00 |
| 25 | Traffic Signal Module - 12-inch, Green Ball, LED (680.810105) | EACH | 22 | $90.02 | $185.00 | $131.00 |
| 26 | Traffic Signal Module - 12-inch, Green Arrow, LED (680.810106) | EACH | 13 | $98.80 | $185.00 | $139.00 |
| 27 | Traffic Signal Section - Aluminum Type I, 12-inch (680.810107) | EACH | 102 | $373.00 | $245.00 | $217.00 |
| 28 | Traffic Signal Bracket Assembly - 1 Way (680.8111) | EACH | 19 | $338.00 | $710.00 | $822.00 |
| 29 | Traffic Signal Bracket Assembly - 2 Way (680.8112) | EACH | 8 | $724.00 | $1,050.00 | $1,244.00 |
| 30 | Pedestrian Signal Section - Aluminum Type I, 12 inch (680.813103) | EACH | 24 | $432.00 | $310.00 | $267.00 |
| 31 | Pedestrian Signal Module - 12-inch, Bi-Modal Hand/Man Symbols, LED (680.813105) | EACH | 12 | $211.00 | $295.00 | $247.00 |
| 32 | Pedestrian Signal Bracket Mount Assembly (680.8141) | EACH | 10 | $554.00 | $685.00 | $677.00 |
| 33 | Pedestrian Signal Post Top Mount Assembly (680.8142) | EACH | 2 | $792.00 | $780.00 | $827.00 |
| 34 | Pedestrian Signal Module - 12-inch Countdown Timer, LED (680.815001) | EACH | 12 | $211.00 | $295.00 | $247.00 |
| 35 | (680.8151) | EACH | 12 | $1,342.00 | $1,645.00 | $1,317.00 |
| 36 | Backplates for Traffic Signal Heads (680.8199) | EACH | 2 | $156.00 | $285.00 | $249.00 |
| 37 | (680.8201) | EACH | 10 | $1,051.00 | $920.00 | $1,051.00 |
| 38 | (680.94000008) | 2 | $1,378.00 | $1,530.00 | $1,305.00 | |
| 39 | Meter Pan (680.9402) | EACH | 2 | $1,685.00 | $1,350.00 | $1,888.00 |
| 40 | Install Electrical Disconnect/Generator Transfer Switch (680.9499) | EACH | 2 | $99.31 | $675.00 | $507.00 |
| 41 | (680.950206) | LF | 350 | $8.00 | $8.25 | $9.00 |
| 42 | (680.99010010) | 12 | $241.00 | $135.00 | $204.00 | |
| 43 | (680.99050010) | 1 | $479.00 | $1,200.00 | $1,230.00 | |
| 44 | (680.99060010) | 2 | $1,023.00 | $1,250.00 | $1,230.00 | |
| 45 | Field Change Payment (FCP) (697.03) | DOL | 37,000 | $1.00 | $1.00 | $1.00 |
| 46 | Asphalt Price Adjustment (698.04) | DOL | 100 | $1.00 | $1.00 | $1.00 |
| 47 | Fuel Price Adjustment (698.05) | DOL | 100 | $1.00 | $1.00 | $1.00 |
| 48 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 |
| 49 | Mobilization (699.040001) | LS | 1 | $20,000 | $22,000 | $25,900 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of October 15, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.