NYSDOT contract D265772 bid tabulation
Culvert Replacement & Signal Rehabilitation - I-990 & NY-263. Let by New York State DOT on May 21, 2026, Erie, Region 05. 4 bids received; low bid $3,613,249 by Oakgrove Construction Inc.
- Owner
- New York State DOT
- Letting
- 21 MAY 2026
- Pay items
- 119
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Oakgrove Construction Inc | $3,613,249 | Low |
| 2 | McLaughlin Construction Corp/DBA Edbauer Construction | $3,946,658 | +9.0% |
| 3 | Concrete Applied Technologies Corp/DBA:Catco | $4,283,646 | +19% |
| 4 | Cold Spring Construction Company | $4,454,550 | +23% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Oakgrove Construction Inc | 2. McLaughlin Construction Corp/DBA Edbauer Construction | 3. Concrete Applied Technologies Corp/DBA:Catco | 4. Cold Spring Construction Company |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.06) | LS | 1 | $5,000.00 | $50,000 | $10,000 | $15,000 |
| 2 | Unclassified Excavation and Disposal (203.02) | CY | 8,640 | $25.00 | $30.00 | $27.00 | $35.00 |
| 3 | Embankment In Place (203.03) | CY | 10,877 | $15.00 | $33.00 | $30.00 | $55.00 |
| 4 | Select Granular Fill (203.07) | CY | 964 | $80.00 | $90.00 | $70.00 | $75.00 |
| 5 | (203.24010017) | 36 | $100.00 | $180.00 | $150.00 | $100.00 | |
| 6 | Structure Excavation (206.01) | CY | 6,938 | $30.00 | $24.00 | $28.00 | $40.00 |
| 7 | Trench and Culvert Excavation (206.0201) | CY | 348 | $25.00 | $32.00 | $60.00 | $45.00 |
| 8 | (206.03060005) | 268 | $75.00 | $90.00 | $65.00 | $80.00 | |
| 9 | Geotextile Bedding (207.20) | SY | 739 | $4.00 | $3.00 | $5.00 | $5.00 |
| 10 | Seed and Mulch – Temporary (209.1003) | SY | 4,091 | $1.00 | $0.50 | $1.00 | $0.50 |
| 11 | (209.23010009) | 960 | $8.00 | $1.50 | $9.00 | $5.00 | |
| 12 | (304.15010005) | 2,351 | $45.00 | $87.00 | $75.00 | $90.00 | |
| 13 | Pavement Density Quality Adjustment to Asphalt Items (404.0002) | QUALITY UNIT | 92 | $105.00 | $105.00 | $105.00 | $105.00 |
| 14 | Longitudinal Joint Density Quality Adjustment to Asphalt Items (404.0003) | QUALITY UNIT | 24 | $105.00 | $105.00 | $105.00 | $105.00 |
| 15 | (404.0982) | TON | 140 | $150.00 | $340.00 | $225.00 | $140.00 |
| 16 | (404.1989) | TON | 226 | $125.00 | $250.00 | $160.00 | $130.00 |
| 17 | (404.3789) | TON | 374 | $100.00 | $172.00 | $140.00 | $125.00 |
| 18 | (404.4389) | TON | 1,082 | $85.00 | $142.00 | $110.00 | $135.00 |
| 19 | Diluted Tack Coat (407.0102) | GAL | 812 | $8.00 | $15.00 | $8.00 | $10.00 |
| 20 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 2,595 | $0.50 | $0.50 | $2.00 | $1.25 |
| 21 | Miscellaneous Cold Milling of Bituminous Concrete (490.30) | SY | 150 | $25.00 | $42.00 | $40.00 | $35.00 |
| 22 | Sealing Transverse Joints- Highway Joint Sealant (502.9210) | LF | 192 | $15.00 | $45.00 | $25.00 | $10.00 |
| 23 | Sealing Longitudinal Joints-Highway Joint Sealant (502.9310) | LF | 95 | $10.00 | $45.00 | $25.00 | $10.00 |
| 24 | Bump Grinding - PCC with Slurry Removal (505.0102) | SY | 183 | $150.00 | $125.00 | $120.00 | $125.00 |
| 25 | (510.00120018) | 64 | $750.00 | $940.00 | $1,300.00 | $700.00 | |
| 26 | (510.81000018) | 32 | $60.00 | $143.00 | $100.00 | $80.00 | |
| 27 | (510.91000018) | 144 | $35.00 | $60.00 | $30.00 | $30.00 | |
| 28 | (510.91100018) | 95 | $20.00 | $42.00 | $30.00 | $20.00 | |
| 29 | (553.030001) | EACH | 1 | $20,000 | $100.00 | $50,000 | $15,000 |
| 30 | (595.50000018) | 10,030 | $4.00 | $7.00 | $4.50 | $5.00 | |
| 31 | (603.64140715) | 295 | $2,500.00 | $2,450.00 | $2,335.00 | $2,250.00 | |
| 32 | (603.67000001) | 36 | $2,000.00 | $2,550.00 | $2,400.00 | $3,000.00 | |
| 33 | (603.9836) | LF | 190 | $100.00 | $132.00 | $140.00 | $150.00 |
| 34 | (606.32960011) | 842 | $15.00 | $10.00 | $30.00 | $20.00 | |
| 35 | (607.41010010) | 160 | $5.00 | $0.25 | $10.00 | $5.00 | |
| 36 | Topsoil - Roadside (610.1402) | CY | 1,006 | $35.00 | $50.00 | $75.00 | $60.00 |
| 37 | Turf Establishment - Roadside (610.1601) | SY | 9,050 | $1.50 | $0.20 | $1.75 | $1.00 |
| 38 | Watering Vegetation (610.19) | 1,000 GALLONS | 11 | $10.00 | $25.00 | $400.00 | $75.00 |
| 39 | (613.04000001) | 153 | $85.00 | $48.00 | $150.00 | $80.00 | |
| 40 | (617.10000024) | 20 | $100.00 | $10.00 | $88.00 | $20.00 | |
| 41 | (617.11000024) | LS | 1 | $500.00 | $100.00 | $2,500.00 | $250.00 |
| 42 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $389,150 | $186,598 | $503,000 | $225,000 |
| 43 | (619.080102) | LF | 120 | $15.00 | $12.00 | $12.00 | $12.00 |
| 44 | Cover Existing Pavement Marking Stripes (Removable Tape) (619.0803) | LF | 2,675 | $5.00 | $5.00 | $6.00 | $10.00 |
| 45 | (619.100102) | LF | 10,650 | $1.50 | $0.87 | $0.87 | $1.00 |
| 46 | (619.111113) | EACH | 2 | $8,500.00 | $10,000 | $18,400 | $15,000 |
| 47 | Temporary Glare Screen (619.12) | LF | 1,000 | $8.00 | $16.00 | $6.00 | $2.00 |
| 48 | Maintain Traffic Signal Equipment (Requirement A) Intersection (619.1611) | MONTH | 12 | $200.00 | $915.00 | $10.00 | $250.00 |
| 49 | (619.17060005) | 5,371 | $4.00 | $1.00 | $2.15 | $2.00 | |
| 50 | Temporary Positive Barrier – Category 5 (Pinning Prohibited) (619.1715) | LF | 5,425 | $15.00 | $24.00 | $38.00 | $50.00 |
| 51 | Temporary Impact Attenuator - Redirective (Test Level 3) (619.1803) | EACH | 1 | $3,500.00 | $7,500.00 | $4,600.00 | $7,500.00 |
| 52 | (619.60750011) | 1,924 | $10.00 | $5.00 | $13.00 | $5.00 | |
| 53 | Stone Filling (Heavy) (620.05) | CY | 164 | $125.00 | $120.00 | $205.00 | $200.00 |
| 54 | Bedding Material, Type 1 (620.0801) | CY | 20 | $150.00 | $110.00 | $175.00 | $150.00 |
| 55 | Bedding Material, Type 2 (620.0802) | CY | 20 | $150.00 | $110.00 | $175.00 | $150.00 |
| 56 | Crushed Gravel (In-Place Measure) (623.11) | CY | 234 | $150.00 | $127.00 | $120.00 | $150.00 |
| 57 | Survey Operations (625.01) | LS | 1 | $17,500 | $54,200 | $45,000 | $50,000 |
| 58 | (627.50140008) | 1,761 | $3.00 | $0.50 | $6.00 | $7.00 | |
| 59 | Cleaning Existing Pavement and/or Shoulder (633.11) | SY | 2,867 | $0.25 | $0.59 | $1.00 | $1.00 |
| 60 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $1,500.00 | $1.00 | $3,600.00 | $500.00 |
| 61 | Engineer’s Field Office – Type 2 (637.12) | MONTH | 20 | $2,000.00 | $1,800.00 | $3,000.00 | $2,750.00 |
| 62 | Office Technology and Supplies (637.34) | DOL | 500 | $1.00 | $1.00 | $1.00 | $1.00 |
| 63 | (637.41000115) | 24 | $100.00 | $200.00 | $200.00 | $225.00 | |
| 64 | White Paint Reflectorized Pavement Stripes – 15 mils (640.10) | LF | 2,249 | $1.25 | $1.10 | $1.10 | $1.00 |
| 65 | Yellow Paint Reflectorized Pavement Stripes - 15 mils (640.11) | LF | 659 | $1.25 | $2.00 | $1.60 | $1.50 |
| 66 | Anchor Bolts (644.11) | LB | 594 | $15.00 | $15.00 | $12.00 | $12.00 |
| 67 | Drilled Shaft for Overhead Sign Structures (644.20) | CY | 20 | $1,500.00 | $50.00 | $100.00 | $350.00 |
| 68 | (644.421515) | EACH | 1 | $100,000 | $115,000 | $110,000 | $125,000 |
| 69 | Performance Concrete Quality Adjustment (644.99) | QUALITY UNIT | 1 | $21.00 | $21.00 | $21.00 | $21.00 |
| 70 | Ground-Mounted Sign Panels without Z-bars (645.5101) | SF | 23 | $40.00 | $72.00 | $43.00 | $45.00 |
| 71 | Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102) | SF | 930 | $40.00 | $41.00 | $41.50 | $45.00 |
| 72 | Overhead Sign Panels (645.61) | SF | 90 | $50.00 | $50.00 | $102.00 | $100.00 |
| 73 | Type A Sign Posts (645.81) | EACH | 91 | $200.00 | $215.00 | $203.00 | $225.00 |
| 74 | High-Capacity Type A Sign Posts with Soil Plates Only (645.8106) | EACH | 8 | $1,200.00 | $1,220.00 | $1,200.00 | $1,250.00 |
| 75 | (645.81090003) | 22 | $75.00 | $57.00 | $83.00 | $75.00 | |
| 76 | Reference Marker Panel (646.21) | EACH | 5 | $40.00 | $40.00 | $43.00 | $40.00 |
| 77 | Steel Post, 2.0 lb/ft (646.32) | EACH | 5 | $100.00 | $75.00 | $85.00 | $125.00 |
| 78 | Remove and Store Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.41) | EACH | 45 | $50.00 | $95.00 | $43.00 | $100.00 |
| 79 | Remove and Store Sign Panel, Sign Panel Assembly Size II (30-100 Square Feet) (647.42) | EACH | 3 | $75.00 | $720.00 | $63.00 | $400.00 |
| 80 | (647.83001002) | 5 | $30.00 | $30.00 | $16.00 | $50.00 | |
| 81 | Milled-In Audible Roadway Delineators (MIARDs) (649.01) | LF | 1,180 | $6.00 | $6.00 | $6.00 | $6.00 |
| 82 | (650.1008) | LF | 308 | $350.00 | $158.00 | $150.00 | $75.00 |
| 83 | (680.05010007) | 1 | $30,000 | $35,380 | $28,500 | $30,000 | |
| 84 | (680.05020007) | 1 | $5,000.00 | $5,189.00 | $5,300.00 | $6,500.00 | |
| 85 | (680.05040004) | 2 | $5,000.00 | $2,899.00 | $5,300.00 | $6,000.00 | |
| 86 | Concrete Base for Controller Cabinet (680.5002) | EACH | 1 | $8,000.00 | $6,248.00 | $4,000.00 | $6,500.00 |
| 87 | (680.510301) | EACH | 3 | $3,000.00 | $4,047.00 | $2,700.00 | $3,000.00 |
| 88 | (680.51100010) | 2 | $500.00 | $440.00 | $350.00 | $500.00 | |
| 89 | (680.520105) | LF | 18 | $30.00 | $49.00 | $100.00 | $50.00 |
| 90 | (680.520506) | LF | 19 | $20.00 | $14.00 | $50.00 | $45.00 |
| 91 | (680.520508) | LF | 1,227 | $25.00 | $12.00 | $18.00 | $22.00 |
| 92 | Single Span Wire Assembly (680.7001) | EACH | 1 | $3,000.00 | $7,545.00 | $4,000.00 | $3,500.00 |
| 93 | (680.730514) | LF | 1,036 | $5.00 | $9.00 | $5.10 | $8.00 |
| 94 | (680.77000105) | 1 | $5,000.00 | $4,192.00 | $3,000.00 | $6,000.00 | |
| 95 | (680.78010005) | 2 | $600.00 | $449.00 | $1,000.00 | $1,500.00 | |
| 96 | (680.78030005) | 1 | $1,000.00 | $880.00 | $1,200.00 | $2,500.00 | |
| 97 | (680.78040005) | 2 | $3,000.00 | $981.00 | $2,700.00 | $3,500.00 | |
| 98 | (680.79000105) | 1 | $5,000.00 | $5,836.00 | $5,000.00 | $5,000.00 | |
| 99 | (680.80324515) | 1 | $4,000.00 | $2,304.00 | $3,700.00 | $5,000.00 | |
| 100 | (680.80324708) | 1 | $3,000.00 | $1,527.00 | $1,850.00 | $3,500.00 | |
| 101 | Traffic Signal Module - 12-inch, Red Ball, LED (680.810101) | EACH | 6 | $200.00 | $90.00 | $150.00 | $400.00 |
| 102 | Traffic Signal Module - 12-inch, Yellow Ball, LED (680.810103) | EACH | 6 | $200.00 | $90.00 | $150.00 | $400.00 |
| 103 | Traffic Signal Module - 12-inch, Green Ball, LED (680.810105) | EACH | 6 | $200.00 | $90.00 | $150.00 | $400.00 |
| 104 | Traffic Signal Section - Aluminum Type I, 12-inch (680.810107) | EACH | 18 | $300.00 | $134.00 | $220.00 | $400.00 |
| 105 | Traffic Signal Bracket Assembly - 1 Way (680.8111) | EACH | 6 | $500.00 | $471.00 | $410.00 | $800.00 |
| 106 | Traffic Signal Disconnect Hanger (680.8120) | EACH | 6 | $500.00 | $968.00 | $800.00 | $900.00 |
| 107 | (680.8205) | EACH | 2 | $1,400.00 | $1,235.00 | $1,100.00 | $1,500.00 |
| 108 | (680.82250801) | 5 | $600.00 | $1,050.00 | $500.00 | $1,000.00 | |
| 109 | (680.83010005) | 13 | $15.00 | $70.00 | $20.00 | $50.00 | |
| 110 | (680.950106) | LF | 54 | $10.00 | $40.00 | $10.00 | $15.00 |
| 111 | White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102) | LF | 2,249 | $4.00 | $4.20 | $4.20 | $4.00 |
| 112 | Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202) | LF | 659 | $4.00 | $4.20 | $4.20 | $4.00 |
| 113 | Yellow Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3204) | LF | 3,300 | $7.00 | $7.00 | $6.65 | $6.50 |
| 114 | White Epoxy Reflectorized Pavement Symbols - 20 mil Portable/Hand Application (685.3404) | EACH | 13 | $500.00 | $350.00 | $335.00 | $350.00 |
| 115 | Field Change Payment (FCP) (697.03) | DOL | 167,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 116 | Asphalt Price Adjustment (698.04) | DOL | 1,157 | $1.00 | $1.00 | $1.00 | $1.00 |
| 117 | Fuel Price Adjustment (698.05) | DOL | 390 | $1.00 | $1.00 | $1.00 | $1.00 |
| 118 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 |
| 119 | Mobilization (699.040001) | LS | 1 | $138,950 | $151,000 | $164,000 | $170,507 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of May 21, 2026. Compiled by Mirage Metrics.