NYSDOT contract D265684 bid tabulation
ADA COMPLIANCE CONTRACT - Routes NY 25, 25A & 111. Let by New York State DOT on February 5, 2026, Suffolk, Region 10. 7 bids received; low bid $2,094,314 by GGG Construction Corp.
- Owner
- New York State DOT
- Letting
- 05 FEB 2026
- Pay items
- 70
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | GGG Construction Corp | $2,094,314 | Low |
| 2 | Rosemar Contracting Inc | $2,768,405 | +32% |
| 3 | Roadwork Ahead Inc | $2,823,197 | +35% |
| 4 | Thomas Novelli Contracting | $2,858,723 | +36% |
| 5 | Pratt Brothers Inc | $3,039,000 | +45% |
| 6 | J Anthony Enterprises Inc | $3,543,987 | +69% |
| 7 | Quintal Contracting Corp | $3,992,095 | +91% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. GGG Construction Corp | 2. Rosemar Contracting Inc | 3. Roadwork Ahead Inc | 4. Thomas Novelli Contracting | 5. Pratt Brothers Inc | 6. J Anthony Enterprises Inc |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.06) | LS | 1 | $1,000.00 | $10,000 | $20,000 | $10,000 | $25,000 | $50,000 |
| 2 | Unclassified Excavation and Disposal (203.02) | CY | 750 | $50.00 | $80.00 | $100.00 | $70.00 | $131.00 | $75.00 |
| 3 | (209.11010024) | 5 | $50.00 | $350.00 | $400.00 | $200.00 | $225.00 | $350.00 | |
| 4 | (304.10119917) | 468 | $50.00 | $125.00 | $45.00 | $80.00 | $145.00 | $65.00 | |
| 5 | (404.0189) | TON | 36 | $300.00 | $300.00 | $100.00 | $300.00 | $395.00 | $150.00 |
| 6 | (404.0981) | TON | 36 | $300.00 | $300.00 | $800.00 | $300.00 | $395.00 | $250.00 |
| 7 | (404.1989) | TON | 58 | $300.00 | $300.00 | $450.00 | $300.00 | $595.00 | $250.00 |
| 8 | (404.2589) | TON | 112 | $275.00 | $300.00 | $450.00 | $300.00 | $595.00 | $250.00 |
| 9 | Diluted Tack Coat (407.0102) | GAL | 77 | $5.00 | $10.00 | $4.00 | $20.00 | $40.00 | $10.00 |
| 10 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 700 | $1.00 | $5.00 | $6.00 | $5.00 | $7.50 | $10.00 |
| 11 | Miscellaneous Cold Milling of Bituminous Concrete (490.30) | SY | 509 | $6.95 | $50.00 | $12.00 | $100.00 | $40.00 | $25.00 |
| 12 | (520.05000010) | 77 | $10.00 | $10.00 | $10.00 | $20.00 | $20.00 | $15.00 | |
| 13 | (520.09000010) | 2,654.50 | $4.00 | $10.00 | $5.00 | $6.00 | $5.00 | $7.00 | |
| 14 | Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.000013) | QUALITY UNIT | 1 | $125.00 | $125.00 | $125.00 | $125.00 | $125.00 | $125.00 |
| 15 | Concrete Sidewalks and Driveways (608.0101) | CY | 245.85 | $1,050.00 | $1,300.00 | $800.00 | $900.00 | $1,500.00 | $1,000.00 |
| 16 | Accelerated Cure Sidewalks and Driveways (608.0102) | CY | 24.55 | $1,050.00 | $1,500.00 | $1,000.00 | $960.00 | $1,600.00 | $1,500.00 |
| 17 | (608.01050109) | 63 | $5,250.00 | $6,800.00 | $6,000.00 | $7,000.00 | $6,500.00 | $7,000.00 | |
| 18 | (608.01050209) | 23 | $5,250.00 | $7,700.00 | $6,900.00 | $7,000.00 | $5,000.00 | $7,000.00 | |
| 19 | (608.01050309) | 5 | $8,250.00 | $11,000 | $6,900.00 | $10,000 | $12,500 | $11,000 | |
| 20 | (608.01050409) | 1 | $8,500.00 | $12,000 | $7,100.00 | $10,000 | $12,000 | $11,000 | |
| 21 | (608.01050809) | 9 | $6,850.00 | $10,000 | $7,400.00 | $10,000 | $9,000.00 | $12,000 | |
| 22 | (608.01050909) | 16 | $5,695.00 | $9,000.00 | $7,250.00 | $10,000 | $9,500.00 | $9,000.00 | |
| 23 | (608.01051009) | 6 | $5,595.00 | $8,000.00 | $6,700.00 | $10,000 | $11,000 | $10,000 | |
| 24 | (608.01051109) | 7 | $5,595.00 | $8,000.00 | $6,700.00 | $10,000 | $7,000.00 | $5,000.00 | |
| 25 | (608.01051209) | 1 | $21,000 | $20,000 | $13,000 | $10,000 | $25,000 | $17,500 | |
| 26 | (608.01051309) | 2 | $5,750.00 | $8,000.00 | $7,500.00 | $10,000 | $12,000 | $7,000.00 | |
| 27 | (608.02010015) | 1,637 | $25.00 | $50.00 | $50.00 | $70.00 | $75.00 | $75.00 | |
| 28 | Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102) | TON | 5.24 | $500.00 | $300.00 | $300.00 | $400.00 | $1,300.00 | $400.00 |
| 29 | (608.03010005) | 5 | $250.00 | $300.00 | $200.00 | $500.00 | $450.00 | $200.00 | |
| 30 | Embedded Detectable Warning Units (608.21) | SY | 1 | $550.00 | $500.00 | $500.00 | $300.00 | $500.00 | $200.00 |
| 31 | (609.04010510) | 1,035.50 | $45.00 | $60.00 | $48.00 | $70.00 | $55.00 | $65.00 | |
| 32 | (609.0403) | LF | 110 | $65.00 | $80.00 | $48.00 | $70.00 | $58.00 | $65.00 |
| 33 | Mycorrhizal Fungi (610.0701) | LB | 14 | $50.00 | $30.00 | $100.00 | $100.00 | $27.00 | $30.00 |
| 34 | Moisture Retention Additive (610.08) | LB | 5 | $50.00 | $30.00 | $100.00 | $100.00 | $27.00 | $30.00 |
| 35 | Topsoil - Roadside (610.1402) | CY | 208.44 | $50.00 | $35.00 | $110.00 | $150.00 | $112.00 | $115.00 |
| 36 | Turf Establishment - Roadside (610.1601) | SY | 1,250.67 | $10.00 | $4.00 | $10.00 | $15.00 | $6.00 | $6.50 |
| 37 | Watering Vegetation (610.19) | 1,000 GALLONS | 67 | $50.00 | $100.00 | $220.00 | $100.00 | $98.00 | $110.00 |
| 38 | (611.0161) | EACH | 11 | $1,100.00 | $1,200.00 | $1,680.00 | $1,000.00 | $1,200.00 | $1,300.00 |
| 39 | (611.0201) | EACH | 22 | $850.00 | $900.00 | $1,500.00 | $1,000.00 | $900.00 | $1,000.00 |
| 40 | (611.19010024) | 3 | $1,100.00 | $500.00 | $600.00 | $100.00 | $500.00 | $600.00 | |
| 41 | (611.19020024) | 5 | $850.00 | $300.00 | $600.00 | $100.00 | $300.00 | $350.00 | |
| 42 | Pre-Existing Stump Removal over 24” to 48” diameter at 6 inches above grade (614.0702) | EACH | 3 | $750.00 | $740.00 | $1,000.00 | $500.00 | $2,000.00 | $150.00 |
| 43 | Basic Work Zone Traffic Control (Daily Operations) (619.0101) | LS | 1 | $75,000 | $200,000 | $475,000 | $250,000 | $240,463 | $900,000 |
| 44 | Type III Construction Barricades (619.04) | EACH | 50 | $50.00 | $75.00 | $100.00 | $50.00 | $125.00 | $150.00 |
| 45 | (619.080102) | LF | 952.50 | $1.85 | $2.00 | $4.00 | $3.00 | $1.65 | $2.00 |
| 46 | (619.10050020) | 1 | $100.00 | $200.00 | $3,000.00 | $2,000.00 | $650.00 | $500.00 | |
| 47 | (619.111133) | EACH | 1 | $3,500.00 | $10,000 | $15,000 | $15,000 | $25,000 | $35,000 |
| 48 | Mailboxes (619.27) | EACH | 3 | $1,000.00 | $200.00 | $500.00 | $1,000.00 | $750.00 | $500.00 |
| 49 | Survey Operations (625.01) | LS | 1 | $25,000 | $25,000 | $10,000 | $20,000 | $35,000 | $20,000 |
| 50 | Cleaning, Sealing and/or Filling Joints (633.13) | LF | 1,030 | $5.00 | $10.00 | $6.00 | $12.00 | $10.00 | $10.00 |
| 51 | Cleaning and Preparation of Pavement Surfaces-Lines (635.0103) | LF | 20,000 | $1.85 | $1.65 | $2.00 | $2.00 | $1.65 | $1.80 |
| 52 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $5,000.00 | $2,500.00 | $500.00 | $3,000.00 | $1,500.00 | $2,500.00 |
| 53 | Engineer’s Field Office – Type 3 (637.13) | MONTH | 14 | $4,000.00 | $4,500.00 | $6,000.00 | $5,000.00 | $6,000.00 | $8,000.00 |
| 54 | Office Technology and Supplies (637.34) | DOL | 3,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 55 | Construction Testing supplies – Consumables (637.36) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 56 | (637.41000115) | 14 | $100.00 | $200.00 | $200.00 | $500.00 | $300.00 | $500.00 | |
| 57 | Relocate Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.31) | EACH | 12 | $350.00 | $500.00 | $1,000.00 | $500.00 | $570.00 | $300.00 |
| 58 | Remove and Dispose Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.51) | EACH | 2 | $300.00 | $500.00 | $100.00 | $600.00 | $350.00 | $175.00 |
| 59 | (680.51111010) | 2 | $750.00 | $250.00 | $460.00 | $900.00 | $1,200.00 | $1,000.00 | |
| 60 | (680.83200010) | LS | 1 | $500.00 | $10,000 | $8,000.00 | $20,000 | $25,000 | $2,500.00 |
| 61 | (685.07200110) | 162 | $1.70 | $1.50 | $10.00 | $20.00 | $1.50 | $1.65 | |
| 62 | (685.07200510) | 450 | $4.00 | $3.50 | $10.00 | $20.00 | $3.50 | $3.85 | |
| 63 | (685.07200610) | 33 | $1.70 | $1.50 | $10.00 | $20.00 | $1.50 | $1.65 | |
| 64 | White Thermoplastic Reflectorized Pavement Stripes (687.0101) | LF | 8,000 | $2.00 | $1.75 | $2.50 | $6.00 | $1.75 | $1.90 |
| 65 | White Preformed Reflectorized Pavement Stripes (688.01) | LF | 29,700 | $4.40 | $3.85 | $4.85 | $3.00 | $3.85 | $4.00 |
| 66 | Field Change Payment (FCP) (697.03) | DOL | 281,157.77 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 67 | Asphalt Price Adjustment (698.04) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 68 | Fuel Price Adjustment (698.05) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 69 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 70 | Mobilization (699.040001) | LS | 1 | $80,551 | $106,000 | $100,000 | $109,946 | $100,000 | $135,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of February 5, 2026. Compiled by Mirage Metrics.