NYSDOT contract D265686 bid tabulation

PAVEMENT REHABILITATION - Routes 987F-SH 9480, 987G-SH 9488. Let by New York State DOT on January 8, 2026, Westchester, Region 08. 6 bids received; low bid $35,411,130 by Yonkers Contracting Company Inc.

Owner
New York State DOT
Letting
08 JAN 2026
Pay items
55
Data through
15 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Yonkers Contracting Company Inc$35,411,130Low
2Grace Industries LLC$35,949,000+2.0%
3Ecco III Enterprises Inc$38,894,000+10%
4Bove Industries Inc$40,580,000+15%
5Crisdel Group Inc$54,193,599+53%
6Jrcruz Corp$63,467,980+79%
NYSDOT contract D265686: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Yonkers Contracting Company Inc2. Grace Industries LLC3. Ecco III Enterprises Inc4. Bove Industries Inc5. Crisdel Group Inc6. Jrcruz Corp
1Unclassified Excavation and Disposal (203.02)CY8,700$250.00$125.70$120.00$195.00$179.87$140.00
2 (304.00010018)349,580$1.00$0.20$1.00$1.00$2.39$2.00
3 (304.11000008)3,480$250.00$110.00$185.00$100.00$199.42$150.00
4Pavement Density Quality Adjustment to Asphalt Items (404.0002)QUALITY UNIT2$140.00$140.00$140.00$140.00$140.00$140.00
5Longitudinal Joint Density Quality Adjustment to Asphalt Items (404.0003)QUALITY UNIT360$140.00$140.00$140.00$140.00$140.00$140.00
6 (404.0179)TON270$200.00$230.00$256.00$250.00$288.21$250.00
7 (404.1969)TON7,610$250.00$205.00$325.00$230.00$193.78$200.00
8 (406.0961)TON10,350$200.00$230.00$185.00$235.00$228.37$210.00
9Straight Tack Coat (407.0103)GAL5,280$12.00$5.00$25.00$15.00$4.94$10.00
10Asphalt Pavement Joint Adhesive (418.7603)LF96,000$1.35$0.20$1.25$1.50$0.84$0.60
11Production Cold-Mill Surface Planing of Bituminous Concrete (490.15)SY46,900$12.00$11.00$9.50$10.00$15.74$10.00
12Miscellaneous Cold Milling of Bituminous Concrete (490.30)SY2,370$50.00$51.00$85.00$135.00$70.68$20.00
13Production Grinding – Pavement Preservation with Slurry Removal (505.0402)SY262,640$6.75$10.00$15.00$8.75$6.25$10.50
14 (510.00210018)9,720$600.00$1,025.00$800.00$1,350.00$1,084.99$2,750.00
15 (510.20000018)38,850$130.00$94.00$185.00$150.00$174.91$250.00
16 (510.81000018)50,750$12.00$12.50$20.00$35.00$39.93$60.00
17 (510.81100018)5,230$80.00$8.00$55.00$32.00$56.95$60.00
18 (510.90010018)105,690$9.00$10.00$5.50$7.50$5.54$9.00
19 (510.91000018)7,550$35.00$25.00$6.50$15.00$19.74$60.00
20 (511.50000018)6,400$225.00$195.00$241.00$228.00$298.21$228.00
21 (604.070801)EACH15$8,000.00$2,100.00$3,500.00$3,800.00$2,195.83$1,800.00
22 (604.07290010)430$170.00$95.00$125.00$300.00$243.39$150.00
23 (604.07600008)30$12,500$3,700.00$8,000.00$6,100.00$2,985.95$5,000.00
24 (604.07610008)81$12,900$5,750.00$9,600.00$6,200.00$3,305.28$5,500.00
25 (609.12290008)1,900$350.00$178.52$110.00$102.00$207.45$150.00
26Turf Establishment – Performance (610.1605)SY400$20.00$20.00$63.00$20.00$27.42$10.00
27Basic Work Zone Traffic Control (Daily Operations) (619.0101)LS1$2,162,000$3,121,426$3,233,597$1,345,506$9,900,000$4,050,000
28 (619.0901)LF307,900$0.40$0.50$0.30$0.29$0.32$0.90
29 (619.110511)EACH4$17,000$40,000$25,000$20,000$27,419$12,000
30Maintain Traffic Signal Equipment (Requirement B) Intersection (619.1612)MONTH1$500.00$1,000.00$650.00$650.00$712.89$15,000
31Nighttime Operations (Entire Project) (619.24)LS1$913,000$1,100,000$390,000$300,000$5,540,000$500,000
32Traffic Control Supervisor (619.25)MONTH20$5,000.00$15,000$115.00$1,500.00$20,000$12,500
33Cleaning Closed Drainage Systems (621.03)LF13,800$18.00$14.00$9.00$8.50$60.32$9.00
34Cleaning Drainage Structures (621.04)EACH280$750.00$800.00$200.00$775.00$548.38$750.00
35Survey Operations (625.01)LS1$275,000$150,000$225,000$275,000$215,000$200,000
36 (627.50140008)4,600$25.00$2.50$2.75$2.00$4.74$7.00
37 (633.05040008)LS1$750,000$180,000$110,000$300,000$135,571$25,000
38 (635.13010011)307,900$0.50$0.60$0.45$0.42$0.46$1.00
39Engineer’s Field Office – Type 4 (637.14)MONTH24$11,000$5,500.00$9,000.00$14,000$8,856.41$10,150
40Office Technology and Supplies (637.34)DOL5,000$1.00$1.00$1.00$1.00$1.00$1.00
41Milled-In Audible Roadway Delineators (MIARDs) (649.01)LF60,230$1.00$0.50$0.95$0.50$0.54$0.80
42 (655.30010010)15$2,500.00$2,000.00$3,300.00$1,595.00$1,754.80$1,450.00
43 (680.05010007)1$24,640$30,000$25,000$24,640$27,024$35,000
44 (680.05020007)1$4,250.00$5,100.00$4,250.00$4,250.00$4,661.19$10,000
45 (680.51200208)4$900.00$2,600.00$2,600.00$500.00$1,645.13$2,500.00
46White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102)LF14,200$2.85$3.40$0.65$0.64$0.70$1.00
47 (685.16010014)199,600$2.00$2.40$1.00$0.98$1.07$0.90
48 (685.17010014)108,300$2.00$2.40$1.00$0.98$1.07$0.90
49White Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3104)LF11,000$2.85$3.40$2.60$2.60$2.85$1.00
50White Epoxy Reflectorized Pavement Symbols - 20 mil Portable/Hand Application (685.3404)EACH15$250.00$300.00$250.00$250.00$274.19$150.00
51Field Change Payment (FCP) (697.03)DOL1,000,000$1.00$1.00$1.00$1.00$1.00$1.00
52Asphalt Price Adjustment (698.04)DOL21,270$1.00$1.00$1.00$1.00$1.00$1.00
53Fuel Price Adjustment (698.05)DOL9,960$1.00$1.00$1.00$1.00$1.00$1.00
54Steel/Iron Price Adjustment (698.06)DOL100$1.00$1.00$1.00$1.00$1.00$1.00
55Mobilization (699.040001)LS1$1,200,000$1,376,640$1,480,000$1,550,000$2,000,000$2,441,076
NYSDOT contract D265686: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.

Every contract let that day: NYSDOT letting of January 8, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy