NYSDOT contract D265780 bid tabulation

Guiderail Replacement: Interstate 84 West Orange County. Let by New York State DOT on March 26, 2026, Orange, Region 08. 2 bids received; low bid $2,287,407 by J Fletcher Creamer & Son Inc.

Owner
New York State DOT
Letting
26 MAR 2026
Pay items
22
Data through
15 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1J Fletcher Creamer & Son Inc$2,287,407Low
2Road Safety Systems LLC$2,435,491+6.0%
NYSDOT contract D265780: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. J Fletcher Creamer & Son Inc2. Road Safety Systems LLC
1 (203.24010017)271$35.00$40.10
2Box Beam Guide Railing (606.10)LF26,354$56.50$59.80
3Box Beam End Piece (606.120101)EACH27$1,200.00$744.50
4Box Beam End Assembly Type III (606.1203)EACH27$7,100.00$8,885.60
5HPBO (Mod.) Corrugated Beam Guide Railing End Terminal (Energy-Absorbing) (606.27)EACH1$4,000.00$5,949.20
6 (606.59600015)3,927$1.00$15.40
7Removing and Disposing Cable Guide Railing (606.70)LF26,551$6.00$1.10
8Removing and Disposing Anchorage Units for Cable Guide railing or Median Barrier (606.79)EACH64$1,100.00$228.20
9Transition: HPBO (Mod.) Corrugated Guide Railing to Beam Box Beam Guide Railing (606.8901)EACH1$5,000.00$7,408.30
10Basic Work Zone Traffic Control (619.01)LS1$72,154$236,358
11 (619.110512)EACH5$3,000.00$1,900.00
12Clean, Grade and Shape Existing Roadside Section (621.05)LF26,354$1.00$0.20
13Survey Operations (625.01)LS1$5,000.00$7,380.70
14Engineer’s Field Office – Type 1 (637.11)MONTH9$3,500.00$3,535.50
15Office Technology and Supplies (637.34)DOL2,000$1.00$1.00
16Reference Marker, Delineator, Snowplowing Marker, Supplementary Snowplowing Marker Panels Relocation (646.24)EACH130$1.00$6.50
17Steel Post, 2.0 lb/ft (646.32)EACH187$50.00$45.20
18Field Change Payment (FCP) (697.03)DOL75,000$1.00$1.00
19Asphalt Price Adjustment (698.04)DOL100$1.00$1.00
20Fuel Price Adjustment (698.05)DOL500$1.00$1.00
21Steel/Iron Price Adjustment (698.06)DOL100$1.00$1.00
22Mobilization (699.040001)LS1$85,000$93,672
NYSDOT contract D265780: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.

Every contract let that day: NYSDOT letting of March 26, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy