NYSDOT contract D265836 bid tabulation
PM Drainage Clean/ Repair/ Replace Various Locations. Let by New York State DOT on September 17, 2026, Nassau, Suffolk, Region 10. 6 bids received; low bid $3,477,167 by Rosemar Contracting Inc.
- Owner
- New York State DOT
- Letting
- 17 SEP 2026
- Pay items
- 77
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Rosemar Contracting Inc | $3,477,167 | Low |
| 2 | Quintal Contracting Corp | $4,219,177 | +21% |
| 3 | Thomas Novelli Contracting | $4,597,810 | +32% |
| 4 | Pratt Brothers Inc | $4,995,995 | +44% |
| 5 | J Anthony Enterprises Inc | $5,423,592 | +56% |
| 6 | Roadwork Ahead Inc | $6,529,404 | +88% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Rosemar Contracting Inc | 2. Quintal Contracting Corp | 3. Thomas Novelli Contracting | 4. Pratt Brothers Inc | 5. J Anthony Enterprises Inc | 6. Roadwork Ahead Inc |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.06) | LS | 1 | $10,000 | $30,000 | $20,000 | $75,000 | $100,000 | $50,000 |
| 2 | Unclassified Excavation and Disposal (203.02) | CY | 786 | $55.00 | $90.00 | $80.00 | $82.00 | $125.00 | $200.00 |
| 3 | Embankment In Place (203.03) | CY | 888 | $15.00 | $65.00 | $30.00 | $10.00 | $45.00 | $75.00 |
| 4 | Select Granular Fill (203.07) | CY | 1,040 | $25.00 | $65.00 | $30.00 | $105.00 | $65.00 | $75.00 |
| 5 | Trench and Culvert Excavation (206.0201) | CY | 3,309 | $160.00 | $61.00 | $80.00 | $180.00 | $125.00 | $100.00 |
| 6 | Geotextile Bedding (207.20) | SY | 145 | $10.00 | $15.00 | $30.00 | $10.00 | $48.00 | $27.00 |
| 7 | Sediment Filter Log - Temporary, 12”, Type B (209.1312) | LF | 43 | $50.00 | $50.00 | $30.00 | $36.00 | $50.00 | $50.00 |
| 8 | Rolled Erosion Control Product, Class II Type D, Intermediate (209.1904) | SY | 75 | $50.00 | $8.00 | $50.00 | $75.00 | $100.00 | $27.00 |
| 9 | Stabilized Construction Access (209.22) | SY | 75 | $75.00 | $65.00 | $50.00 | $75.00 | $125.00 | $27.00 |
| 10 | (304.00010018) | 21,100 | $0.50 | $0.80 | $3.00 | $0.30 | $1.00 | $3.00 | |
| 11 | (304.10119917) | 390 | $120.00 | $73.00 | $60.00 | $145.00 | $75.00 | $125.00 | |
| 12 | (404.0981) | TON | 195 | $200.00 | $450.00 | $200.00 | $295.00 | $300.00 | $500.00 |
| 13 | (404.0989) | TON | 59 | $200.00 | $575.00 | $200.00 | $295.00 | $300.00 | $500.00 |
| 14 | (404.1989) | TON | 66 | $200.00 | $575.00 | $200.00 | $295.00 | $300.00 | $300.00 |
| 15 | Diluted Tack Coat (407.0102) | GAL | 145 | $50.00 | $20.00 | $20.00 | $25.00 | $15.00 | $15.00 |
| 16 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 2,454 | $5.00 | $2.50 | $2.00 | $4.50 | $5.00 | $7.00 |
| 17 | Miscellaneous Cold Milling of Bituminous Concrete (490.30) | SY | 352 | $50.00 | $75.00 | $60.00 | $35.00 | $35.00 | $37.00 |
| 18 | (502.10010018) | LS | 1 | $5,000.00 | $5,000.00 | $20,000 | $5,000.00 | $5,000.00 | $35,000 |
| 19 | Sealing Transverse Joints- Highway Joint Sealant (502.9210) | LF | 422 | $20.00 | $5.00 | $10.00 | $26.90 | $15.00 | $19.00 |
| 20 | Sealing Longitudinal Joints-Highway Joint Sealant (502.9310) | LF | 2,380 | $20.00 | $5.00 | $10.00 | $26.90 | $5.00 | $19.00 |
| 21 | (510.02210018) | 91 | $2,500.00 | $3,500.00 | $1,800.00 | $2,200.00 | $2,000.00 | $3,700.00 | |
| 22 | (510.20000018) | 406 | $100.00 | $120.00 | $50.00 | $75.00 | $150.00 | $467.00 | |
| 23 | (510.81000018) | 224 | $50.00 | $75.00 | $30.00 | $75.00 | $125.00 | $160.00 | |
| 24 | (510.91000018) | 231 | $50.00 | $100.00 | $20.00 | $16.00 | $75.00 | $19.00 | |
| 25 | (520.09000010) | 1,914 | $5.00 | $9.00 | $6.00 | $4.50 | $5.00 | $15.00 | |
| 26 | (552.18000017) | 20,000 | $1.00 | $26.00 | $25.00 | $5.00 | $15.00 | $4.00 | |
| 27 | (553.030001) | EACH | 1 | $20,000 | $10,000 | $100,000 | $30,000 | $50,000 | $10,000 |
| 28 | (553.030002) | EACH | 1 | $20,000 | $10,000 | $100,000 | $15,000 | $50,000 | $10,000 |
| 29 | Drilling and Grouting Bolts or Reinforcing Bars (586.0201) | EACH | 252 | $100.00 | $60.00 | $50.00 | $75.00 | $50.00 | $350.00 |
| 30 | (603.6002) | LF | 1,743 | $130.00 | $149.00 | $170.00 | $165.00 | $250.00 | $400.00 |
| 31 | (604.07200110) | 12 | $3,000.00 | $3,500.00 | $2,000.00 | $1,000.00 | $3,500.00 | $3,000.00 | |
| 32 | (604.07240110) | 6 | $4,000.00 | $6,500.00 | $5,000.00 | $4,000.00 | $2,500.00 | $6,000.00 | |
| 33 | (604.07290010) | 110 | $150.00 | $150.00 | $50.00 | $265.00 | $125.00 | $100.00 | |
| 34 | (604.501006) | LF | 193 | $1,700.00 | $1,300.00 | $1,800.00 | $2,200.00 | $2,000.00 | $2,500.00 |
| 35 | (604.501011) | LF | 34 | $1,500.00 | $1,850.00 | $1,500.00 | $1,500.00 | $3,000.00 | $2,500.00 |
| 36 | (608.01050010) | 239 | $900.00 | $1,375.00 | $1,000.00 | $1,465.00 | $1,500.00 | $2,000.00 | |
| 37 | Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102) | TON | 172 | $450.00 | $600.00 | $300.00 | $625.00 | $300.00 | $379.00 |
| 38 | (609.04010510) | 130 | $200.00 | $90.00 | $60.00 | $200.00 | $75.00 | $130.00 | |
| 39 | Resetting Existing Curb (609.15) | LF | 26 | $300.00 | $100.00 | $40.00 | $425.00 | $125.00 | $100.00 |
| 40 | Topsoil - Roadside (610.1402) | CY | 135 | $100.00 | $65.00 | $100.00 | $140.00 | $160.00 | $360.00 |
| 41 | Turf Establishment - Roadside (610.1601) | SY | 772 | $4.00 | $4.50 | $20.00 | $34.00 | $50.00 | $35.00 |
| 42 | Watering Vegetation (610.19) | 1,000 GALLONS | 113 | $50.00 | $120.00 | $100.00 | $170.00 | $200.00 | $200.00 |
| 43 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $340,000 | $135,000 | $400,000 | $604,207 | $450,000 | $1,000,000 |
| 44 | Type III Construction Barricades (619.04) | EACH | 30 | $150.00 | $50.00 | $200.00 | $100.00 | $125.00 | $200.00 |
| 45 | (619.100101) | LF | 2,094 | $1.00 | $2.50 | $2.00 | $1.00 | $5.00 | $9.00 |
| 46 | (619.10050020) | 320 | $60.00 | $20.00 | $150.00 | $75.00 | $50.00 | $75.00 | |
| 47 | (619.110943) | EACH | 2 | $10,000 | $2,650.00 | $20,000 | $15,000 | $35,000 | $10,000 |
| 48 | Nighttime Operations (Entire Project) (619.24) | LS | 1 | $50,000 | $262,000 | $300,000 | $95,000 | $250,000 | $350,000 |
| 49 | Traffic Control Supervisor (619.25) | MONTH | 8 | $1,000.00 | $1,000.00 | $12,000 | $29,000 | $25,000 | $2,000.00 |
| 50 | Pavement Patching (Force Acount) (619.2601) | DOL | 10,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 51 | Cleaning Culverts with Span of 50 in. or Less (621.01) | LF | 486 | $150.00 | $160.00 | $70.00 | $70.00 | $300.00 | $62.00 |
| 52 | Cleaning Culverts with Span of More Than 50 in. (621.02) | LF | 224 | $150.00 | $220.00 | $120.00 | $150.00 | $500.00 | $130.00 |
| 53 | Cleaning Closed Drainage Systems (621.03) | LF | 971 | $10.00 | $35.00 | $30.00 | $5.00 | $15.00 | $9.00 |
| 54 | Cleaning Drainage Structures (621.04) | EACH | 33 | $750.00 | $1,200.00 | $3,000.00 | $1,000.00 | $2,000.00 | $1,000.00 |
| 55 | (621.51970008) | 271 | $100.00 | $220.00 | $100.00 | $225.00 | $300.00 | $75.00 | |
| 56 | Crushed Stone (In-Place Measure) (623.12) | CY | 242 | $50.00 | $110.00 | $120.00 | $795.00 | $85.00 | $225.00 |
| 57 | Survey Operations (625.01) | LS | 1 | $30,000 | $41,000 | $80,000 | $35,000 | $50,000 | $100,000 |
| 58 | Cleaning Existing Pavement and/or Shoulder (633.11) | SY | 24 | $100.00 | $5.00 | $40.00 | $25.00 | $125.00 | $75.00 |
| 59 | Engineer’s Field Office – Type 3 (637.13) | MONTH | 18 | $6,000.00 | $5,500.00 | $6,000.00 | $6,000.00 | $10,000 | $10,000 |
| 60 | Office Technology and Supplies (637.34) | DOL | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 61 | Construction Testing supplies – Consumables (637.36) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 62 | (637.41000115) | 18 | $100.00 | $250.00 | $800.00 | $300.00 | $500.00 | $1,000.00 | |
| 63 | (637.41000215) | 18 | $100.00 | $250.00 | $800.00 | $300.00 | $500.00 | $1,000.00 | |
| 64 | (637.41000315) | 18 | $100.00 | $250.00 | $800.00 | $300.00 | $500.00 | $1,000.00 | |
| 65 | (637.41000415) | 18 | $100.00 | $250.00 | $800.00 | $300.00 | $500.00 | $1,000.00 | |
| 66 | (637.41000515) | 18 | $100.00 | $250.00 | $800.00 | $300.00 | $500.00 | $1,000.00 | |
| 67 | (655.07030010) | 27 | $1,500.00 | $2,900.00 | $3,000.00 | $2,595.00 | $2,500.00 | $4,000.00 | |
| 68 | Cast Frame F3, UnMountable Curb Box CU3 & Reticuline Grate G3 (655.0706) | EACH | 8 | $2,000.00 | $3,300.00 | $3,000.00 | $2,945.00 | $2,800.00 | $4,000.00 |
| 69 | Manhole Frame & Cover (655.1202) | EACH | 1 | $1,000.00 | $1,350.00 | $2,000.00 | $1,285.00 | $1,500.00 | $4,000.00 |
| 70 | (685.07200110) | 2,092 | $2.60 | $4.00 | $2.00 | $4.00 | $5.00 | $18.00 | |
| 71 | (685.07200310) | 1 | $500.00 | $350.00 | $300.00 | $300.00 | $500.00 | $1,000.00 | |
| 72 | (685.07200610) | 30 | $2.80 | $7.00 | $2.00 | $4.00 | $25.00 | $18.00 | |
| 73 | Field Change Payment (FCP) (697.03) | DOL | 232,600 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 74 | Asphalt Price Adjustment (698.04) | DOL | 112 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 75 | Fuel Price Adjustment (698.05) | DOL | 1,555 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 76 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 77 | Mobilization (699.040001) | LS | 1 | $120,000 | $162,276 | $176,839 | $180,000 | $200,000 | $250,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of September 17, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.