ODOT contract 250387 bid tabulation
LUC-/OTT-IR 280/SR 65/SR 163 FY26 Elec Mnt (BRIDGE REPAIR). Let by Ohio DOT on August 14, 2025, LUC. 1 bid received; low bid $254,518 by U S Utility Contractor Company, +82% against the engineer's estimate of $140,000.
- Owner
- Ohio DOT
- Letting
- 14 AUG 2025
- Pay items
- 29
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | U S Utility Contractor Company | $254,518 | Low | +82% |
Engineer's estimate: $140,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. U S Utility Contractor Company |
|---|---|---|---|---|
| 1 | Maintaining traffic, misc.:lane closure with flagg (614E18000) | EACH | 2 | $2,405.00 |
| 2 | Maintaining traffic, misc.:one lane closure on A 4 (614E18000) | EACH | 4 | $6,415.00 |
| 3 | Maintaining traffic, misc.:shoulder closure (614E18000) | EACH | 8 | $3,625.00 |
| 4 | Special -monthly maintenance and inspection, craig (690E98000) | EACH | 9 | $1,950.00 |
| 5 | Special -routine maintenance and inspection, port (690E98000) | EACH | 8 | $1,950.00 |
| 6 | Special -routine maintenance and inspection, pump (690E98000) | EACH | 12 | $900.00 |
| 7 | Special -routine maintenance and inspection, pump (690E98000) | EACH | 12 | $900.00 |
| 8 | Special -routine maintenance and inspection, pump (690E98000) | EACH | 12 | $900.00 |
| 9 | Special -routine maintenance and inspection, pump (690E98000) | EACH | 12 | $900.00 |
| 10 | Special -repair, inspect, clean, and service vario (690E98400) | LS | 1 | $2,300.00 |
| 11 | Special -repair, inspect, clean, and service vario (690E98400) | LS | 1 | $2,300.00 |
| 12 | Special -repair, inspect, clean, and service vario (690E98400) | LS | 1 | $3,850.00 |
| 13 | Special -test motor insulation, 4 main motors and (690E98400) | LS | 1 | $1,850.00 |
| 14 | Special -testing of backflow valve, craig bridge (690E98400) | LS | 1 | $795.00 |
| 15 | Special -testing of backflow valve, port clinton L (690E98400) | LS | 1 | $795.00 |
| 16 | Special -helper electrician at 1.5 time (690E98600) | HR | 8 | $220.00 |
| 17 | Special -helper electrician at double time (690E98600) | HR | 8 | $255.00 |
| 18 | Special -helper electrician at straight time (690E98600) | HR | 200 | $145.00 |
| 19 | Special -helper mill-wright at 1.5 time (690E98600) | HR | 4 | $121.00 |
| 20 | Special -helper mill-wright at double time (690E98600) | HR | 4 | $148.50 |
| 21 | Special -helper mill-wright at straight time (690E98600) | HR | 8 | $104.50 |
| 22 | Special -journeyman electrician at 1.5 time (690E98600) | HR | 16 | $245.00 |
| 23 | Special -journeyman electrician at double time (690E98600) | HR | 10 | $290.00 |
| 24 | Special -journeyman electrician at straight time (690E98600) | HR | 266 | $160.00 |
| 25 | Special -journeyman mill-wright at 1.5 time (690E98600) | HR | 4 | $145.00 |
| 26 | Special -journeyman mill-wright at double time (690E98600) | HR | 4 | $170.50 |
| 27 | Special -journeyman mill-wright at straight time (690E98600) | HR | 12 | $121.00 |
| 28 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $5,500.00 |
| 29 | Mobilization (624E10000) | LS | 1 | $14,500 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of August 14, 2025. Compiled by Mirage Metrics.