ODOT contract 250403 bid tabulation
D12-MNT FY2026 Tree Removal (PRUNING/OR TREE/BRUSH REMOVAL). Let by Ohio DOT on August 28, 2025, District 12. 4 bids received; low bid $363,301 by Van Curen Services Inc, -16% against the engineer's estimate of $433,000.
- Owner
- Ohio DOT
- Letting
- 28 AUG 2025
- Pay items
- 11
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Van Curen Services Inc | $363,301 | Low | -16% |
| 2 | H & H Land Clearing, LLC | $430,169 | +18% | -1.0% |
| 3 | Russell Tree Experts | $510,000 | +40% | +18% |
| 4 | Beeghly Tree LLC | $707,325 | +95% | +63% |
Engineer's estimate: $433,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Van Curen Services Inc | 2. H & H Land Clearing, LLC | 3. Russell Tree Experts | 4. Beeghly Tree LLC |
|---|---|---|---|---|---|---|---|
| 1 | Special - tree removed, 4"-12" (201E20010) | EACH | 1,668 | $78.00 | $100.00 | $125.00 | $220.00 |
| 2 | Tree removed, 18" diameter, as per plan, work orde (201E21801) | EACH | 333 | $349.00 | $370.00 | $400.00 | $530.00 |
| 3 | Tree removed, 30" diameter, as per plan, work orde (201E23001) | EACH | 52 | $940.00 | $990.00 | $1,250.00 | $1,525.00 |
| 4 | Tree removed, 48" diameter, as per plan, work orde (201E24801) | EACH | 5 | $2,450.00 | $4,000.00 | $2,100.00 | $3,485.00 |
| 5 | Roadside cleanup, as per plan (656E10001) | MSF | 16 | $600.00 | $400.00 | $2,750.00 | $650.00 |
| 6 | Erosion control (832E30000) | EACH | 1,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 7 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 200 | $95.00 | $90.00 | $75.00 | $120.00 |
| 8 | Maintenance of traffic, one lane closure on A two lane highway (614E13600) | EACH | 2 | $775.00 | $500.00 | $1,000.00 | $3,000.00 |
| 9 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $3,700.00 | $5,000.00 | $800.00 | $5,750.00 |
| 10 | Maintaining traffic (614E11000) | LS | 1 | $16,200 | $12,279 | $20,000 | $10,000 |
| 11 | Mobilization (624E10000) | LS | 1 | $4,800.00 | $25,000 | $10,000 | $10,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of August 28, 2025. Compiled by Mirage Metrics.