ODOT contract 250575 bid tabulation
D02-PM FY2026 (PAVEMENT MARKING). Let by Ohio DOT on December 4, 2025, District 2. 4 bids received; low bid $2,837,231 by Oglesby Construction Inc, -21% against the engineer's estimate of $3,603,000.
- Owner
- Ohio DOT
- Letting
- 04 DEC 2025
- Pay items
- 30
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Oglesby Construction Inc | $2,837,231 | Low | -21% |
| 2 | Alpha Space Control LLC | $3,029,172 | +7.0% | -16% |
| 3 | The Aero-Mark Company LLC | $3,323,000 | +17% | -8.0% |
| 4 | American Roadway Logistics | $3,728,364 | +31% | +3.0% |
Engineer's estimate: $3,603,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Oglesby Construction Inc | 2. Alpha Space Control LLC | 3. The Aero-Mark Company LLC | 4. American Roadway Logistics |
|---|---|---|---|---|---|---|---|
| 1 | Edge line, 6", type 1 (642E00104) | MI | 2,620.51 | $640.00 | $628.00 | $687.00 | $785.00 |
| 2 | Lane line, 6", type 1 (642E00204) | MI | 296.48 | $300.00 | $315.00 | $395.00 | $450.00 |
| 3 | Center line, type 1 (642E00300) | MI | 1,286.40 | $425.00 | $630.00 | $453.00 | $575.00 |
| 4 | Channelizing line, 8", type 1 (642E00400) | FT | 141,241 | $0.55 | $0.42 | $0.60 | $0.60 |
| 5 | Channelizing line, 12", type 1 (642E00404) | FT | 78,612 | $0.62 | $0.53 | $0.60 | $0.75 |
| 6 | Dotted line, 4", type 1 (642E01500) | FT | 12,165 | $0.55 | $0.43 | $0.60 | $0.55 |
| 7 | Dotted line, 6", type 1 (642E01510) | FT | 107,355 | $0.62 | $0.56 | $0.60 | $0.65 |
| 8 | Dotted line, 8", type 1 (642E01522) | FT | 1,905 | $0.75 | $0.60 | $0.60 | $0.75 |
| 9 | Pavement marking, misc.:repainting, center line, T (642E50000) | MI | 60 | $425.00 | $575.00 | $424.00 | $450.00 |
| 10 | Pavement marking, misc.:repainting, edge line, typ (642E50000) | MI | 125 | $640.00 | $315.00 | $650.00 | $550.00 |
| 11 | Pavement marking, misc.:repainting, lane line, typ (642E50000) | MI | 60 | $310.00 | $575.00 | $333.00 | $350.00 |
| 12 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 100 | $80.00 | $55.00 | $86.00 | $85.00 |
| 13 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $15,000 | $47,000 | $16,699 | $35,000 |
| 14 | Maintaining traffic (614E11000) | LS | 1 | $37,000 | $12,500 | $50,000 | $100,000 |
| 15 | Mobilization (624E10000) | LS | 1 | $21,600 | $12,500 | $21,000 | $100,000 |
| 100 | Stop line, as per plan (644E00501) | FT | 4,685 | $6.60 | $3.50 | $19.50 | $10.00 |
| 101 | Railroad symbol marking, as per plan (644E01001) | EACH | 5 | $750.00 | $350.00 | $801.00 | $650.00 |
| 102 | Lane arrow, as per plan (644E01301) | EACH | 525 | $70.00 | $50.00 | $291.00 | $150.00 |
| 103 | Lane reduction arrow (644E01350) | EACH | 14 | $250.00 | $238.45 | $779.00 | $150.00 |
| 104 | Wrong way arrow (644E01360) | EACH | 18 | $125.00 | $210.00 | $521.00 | $150.00 |
| 105 | Two way left turn arrow (644E01370) | EACH | 7 | $135.00 | $95.00 | $551.00 | $300.00 |
| 106 | Yield line, as per plan (644E20801) | FT | 422 | $7.50 | $5.80 | $48.00 | $12.00 |
| 107 | Speed measurement marking (644E40000) | EACH | 30 | $250.00 | $900.00 | $197.00 | $250.00 |
| 108 | Stop line, as per plan (646E10401) | FT | 596 | $5.75 | $4.27 | $26.50 | $15.00 |
| 109 | Lane arrow, as per plan (646E20301) | EACH | 135 | $60.00 | $65.00 | $325.00 | $225.00 |
| 110 | Wrong way arrow (646E20320) | EACH | 27 | $110.00 | $215.00 | $553.00 | $325.00 |
| 111 | Lane reduction arrow (646E20350) | EACH | 5 | $200.00 | $239.75 | $725.00 | $450.00 |
| 112 | Speed measurement marking, as per plan (646E20711) | EACH | 22 | $250.00 | $900.00 | $464.00 | $350.00 |
| 113 | Yield line (646E20800) | FT | 98 | $6.75 | $5.75 | $76.00 | $20.00 |
| 114 | Portable changeable message sign, as per plan (614E18601) | SNMT | 8 | $900.00 | $750.00 | $100.00 | $1,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of December 4, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.