ODOT contract 260387 bid tabulation
LOR-/MED-SR 18/SR 301-00.00/08.189 (MICROSURFACING). Let by Ohio DOT on August 27, 2026, LOR. 1 bid received; low bid $1,390,738 by Strawser Construction Inc, +5.4% against the engineer's estimate of $1,320,000.
- Owner
- Ohio DOT
- Letting
- 27 AUG 2026
- Pay items
- 36
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Strawser Construction Inc | $1,390,738 | Low | +5.0% |
Engineer's estimate: $1,320,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Strawser Construction Inc |
|---|---|---|---|---|
| 1 | Monument assembly adjusted to grade, as per plan (623E39501) | EACH | 1 | $1,600.00 |
| 2 | Monument assembly reconstructed to grade, as per plan (623E39601) | EACH | 1 | $2,050.00 |
| 3 | Post construction survey monument verification and report (623E51000) | LS | 1 | $3,075.00 |
| 4 | Erosion control (832E30000) | EACH | 1,500 | $1.00 |
| 5 | Catch basin adjusted to grade (611E98630) | EACH | 8 | $1,500.00 |
| 6 | Inlet adjusted to grade (611E99150) | EACH | 2 | $1,800.00 |
| 7 | Partial depth pavement repair (asphalt concrete base), as per plan (251E01043) | CY | 336 | $530.00 |
| 8 | Partial depth pavement repair (asphalt concrete base), as per plan (251E01043) | CY | 84 | $530.00 |
| 9 | Pavement repair, as per plan (253E02001) | CY | 34 | $530.00 |
| 10 | Pavement repair, as per plan (253E02001) | CY | 8 | $530.00 |
| 11 | Microsurfacing, surface course (FR) (421E10000) | SY | 122,856 | $3.38 |
| 12 | Microsurfacing, leveling course (421E10020) | SY | 122,856 | $2.25 |
| 13 | Rumble stripes, edge line (asphalt concrete) (618E41000) | MI | 10.74 | $1,090.00 |
| 14 | Rumble stripes, center line (asphalt concrete) (618E43000) | MI | 5.37 | $1,300.00 |
| 16 | Pavement planing, asphalt concrete, class A (taper (897E01010) | SY | 918 | $20.00 |
| 17 | Patching planed surface (897E02000) | SY | 12 | $75.00 |
| 18 | RPM (621E00100) | EACH | 491 | $36.50 |
| 19 | Raised pavement marker removed (621E54000) | EACH | 485 | $15.00 |
| 20 | Edge line, 6", type 1 (642E00104) | MI | 15.04 | $905.00 |
| 21 | Center line, type 1 (642E00300) | MI | 7.52 | $1,310.00 |
| 22 | Removal of pavement marking (642E30030) | MI | 7.52 | $1,050.00 |
| 23 | Removal of pavement marking (642E30030) | MI | 15.04 | $1,050.00 |
| 24 | Stop line (644E00500) | FT | 318 | $10.60 |
| 25 | Railroad symbol marking (644E01000) | EACH | 2 | $695.00 |
| 26 | Removal of pavement marking (644E30000) | FT | 318 | $5.35 |
| 27 | Removal of pavement marking (644E30020) | EACH | 2 | $530.00 |
| 28 | Work zone marking sign (614E12460) | EACH | 58 | $68.30 |
| 29 | Portable changeable message sign, as per plan (614E18601) | SNMT | 6 | $960.00 |
| 30 | Work zone center line, class III, 642 paint (614E21550) | MI | 22.56 | $905.00 |
| 31 | Work zone stop line, class III, 642 paint (614E26610) | FT | 954 | $3.75 |
| 32 | Work zone railroad symbol marking, class III, 642 paint (614E32210) | EACH | 6 | $185.00 |
| 33 | Premium for contract performance bond, payment bond and maintenance bond (103E06000) | LS | 1 | $7,500.00 |
| 34 | Maintaining traffic (614E11000) | LS | 1 | $116,860 |
| 35 | Construction layout stakes and surveying (623E10000) | LS | 1 | $3,000.00 |
| 36 | Mobilization (624E10000) | LS | 1 | $117,717 |
| 100 | Special -maltene based longitudinal joint stabiliz (690E98300) | SY | 6,304 | $5.18 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of August 27, 2026. Compiled by Mirage Metrics.