ODOT contract 15591 bid tabulation

Us97:chiloquin br - or39:hwy50 sb over hwy4 nb br. Let by Oregon DOT on March 20, 2025, Region 4. 3 bids received.

Owner
Oregon DOT
Letting
20 MAR 2025
Pay items
81
Data through
13 AUG 2026

Bidders

RankTotal bidAgainst the low bid
1Low
2
3
ODOT contract 15591: bids by rank

Bid tabulation

LinePay itemUnitQuantityRank 1Rank 2Rank 3
1Guardrail blocks (0812-0108000E)EACH120$40.00$40.00$40.00
2Radar speed trailer (0222-0167500E)EACH1$5,500.00$1,600.00$8,650.00
3Stripe removal (0225-0154000F)LF1,450$1.25$2.00$1.25
4Perforated steel square tube slip base sign supports (0930-0114000A)LB96.10$7.80$8.84$20.81
5Sign support footings (0920-0100000A)CY0.12$3,333.33$4,583.33$16,667
6Moving temporary impact attenuators, narrow site system (0226-0137000E)EACH1$1,750.00$1,000.00$2,000.00
7Surface preparation (0594-0103000A)LS1$3,000.00$4,000.00$10,000
8Longitudinal pavement markings - paint (0860-0200000F)LF3,000$3.50$4.00$3.50
9Construct structural concrete overlay (0559-0302000J)SY1,013$150.00$110.00$130.00
10Coating materials (0594-0105000A)LS1$1,500.00$500.00$10,000
11Bridge jacking at bent 5 (0255-0100000A)LS1$20,000$40,000$58,600
12Bridge jacking at bent 2 (0255-0100000A)LS1$20,000$40,000$58,600
13Elastomeric concrete nosing material (0584-0103000C)CF22$115.00$300.00$110.00
14Removal of surfacings (0310-0103000J)SY286$20.00$35.00$20.00
15Structural concrete overlay material (0559-0300000K)CY43$500.00$500.00$450.00
16Removal of guardrail (0310-0113000A)LF1,137$7.92$8.80$17.59
177 inch asphalt concrete pavement repair (0748-0103000J)SY132$183.00$50.00$60.00
18Adjusting catch basins (0490-0102000E)EACH2$4,000.00$3,000.00$1,500.00
19Construct structural concrete overlay (0559-0302000J)SY495$250.00$110.00$121.00
20Concrete deck micro-milling, 1/2 inch depth (0505-0100000J)SY1,013$40.00$20.00$28.57
21Temporary impact attenuator, narrow site system (0226-0134000E)EACH1$3,950.00$3,500.00$5,000.00
22Constructing elastomeric concrete nosing (0584-0104000J)SF105$150.00$200.00$60.00
23Guardrail terminals, downstream anchor terminal (0810-0132200E)EACH1$1,500.00$1,500.00$1,500.00
24Separated paint (0296-0300000O)LB1$2,500.00$100.00$10,000
25Flaggers (0223-0168000T)HR200$85.00$80.00$70.00
26Temporary striping (0225-0153000F)LF2,100$0.65$2.00$0.65
27Clearing and grubbing (0320-0100000A)ACRE0.10$200,000$20,000$300,000
28Hot applied joint sealant (0585-0400000A)LF95$31.58$73.68$31.58
29Temporary work access and containment (0253-0106000A)LS1$10,000$100,000$40,000
30Deep cut hydrodemolition, 1 inch depth (0505-0102000J)SY1,013$165.00$160.00$120.00
31Traffic control supervisor (0223-0169000E)EACH60$850.00$500.00$650.00
32Bridge removal work (0501-0100000A)SF10$500.00$200.00$2,000.00
33Cold plane pavement removal, 2 - 3 inches deep (0620-0112000J)SY956$15.00$20.00$7.20
34Portable changeable message signs (0222-0164000E)EACH3$6,000.00$7,000.00$6,000.00
35Guardrail terminals, non-flared (0810-0129000E)EACH5$4,800.00$4,800.00$4,800.00
36Temporary plastic drums (0224-0145000E)EACH100$50.00$40.00$50.00
37Repair temporary impact attenuator, truck mounted (0226-0141400E)EACH1$1.00$1.00$1,150.00
38Concrete washout facility (0280-0112500E)EACH2$500.00$1,000.00$1,500.00
39Asphalt pavement sawcutting (0310-0119000F)LF2,744$5.00$2.00$3.60
40Coating application (0594-0104000A)LS1$3,000.00$3,000.00$10,000
41Concrete deck micro-milling, 2 inch depth (0505-0100000J)SY495$50.00$35.00$23.38
42Aggregate shoulders (0640-0101000M)TON540$35.00$75.00$66.00
43Structural concrete overlay material (0559-0300000K)CY88$500.00$400.00$450.00
44Drainage curbs (0480-0100000F)LF20$100.00$250.00$100.00
45Temporary signs (0222-0102000J)SF674$26.00$26.00$35.00
46Inlet protection, type 3 (0280-0114030E)EACH6$50.00$80.00$90.00
47Construction entrance, type 1 (0280-0110010E)EACH4$3,500.00$1,500.00$3,000.00
48Surface texturing (0540-0401000J)SY455$10.00$10.00$8.25
49Modifying existing bridge drains (0581-0110000E)EACH4$5,000.00$800.00$850.00
50Guardrail height conversion, type 2A weatherized (0810-0147000E)EACH2$1,500.00$1,500.00$1,500.00
51Temporary flexible pavement markers (0225-0149000E)EACH105$5.00$6.00$2.77
52Removal of structures and obstructions (0310-0106000A)LS1$35,000$1,000.00$20,000
53Reinforcement, grade 60 (0530-0104000A)LB930$10.75$26.88$21.51
54Remove and reinstall existing signs (0905-0101000A)LS1$250.00$250.00$2,000.00
55Precompressed foam silicone joint seal (0585-0215000A)LF60$95.83$416.67$166.67
56Reflective barrier panels (0226-0141100E)EACH19$40.00$250.00$40.00
57Level 3, 1/2 inch ACP mixture (0744-0302000M)TON600$236.00$225.00$224.00
58Pollution control plan (0290-0100000A)LS1$100.00$1,000.00$5,000.00
59Surface texturing (0540-0401000J)SY904$10.00$10.00$8.25
60General structural concrete, class 3300 (0540-0301000A)CY5.50$6,363.64$4,545.45$7,272.73
61Constructing elastomeric concrete nosing (0584-0104000J)SF154$150.00$125.00$60.00
62Major adjustment of manholes (0490-0121000E)EACH2$10,000$1,200.00$1,500.00
63General excavation (0330-0105000K)CY430$30.00$80.00$64.00
64Elastomeric concrete nosing material (0584-0103000C)CF32$115.00$250.00$110.00
65Temporary barricades, type III (0224-0105000E)EACH16$200.00$175.00$200.00
66Bridge approach slab cold plane pavement removal, 2-4 inches deep (0503-0103100J)SY287$30.00$35.00$23.35
67Midwest guardrail system, type 2A weatherized (0810-0146100F)LF900$35.00$34.00$34.00
68Bearing devices, 14 inch wide, 14 inch long, 5.5 inch thick (0582-0020000E)EACH8$2,500.00$4,000.00$2,300.00
69Midwest guardrail system, type 3 weatherized (0810-0146100F)LF100$70.00$68.00$68.00
70Bridge removal work (0501-0100000A)SF8$1,250.00$3,750.00$2,500.00
71Selective hydrodemolition (0505-0101000J)SY495$130.00$150.00$151.00
72Guardrail transition (0810-0126000E)EACH8$5,025.00$5,000.00$5,025.00
73Structure excavation (0510-0101000A)CY13.50$370.37$592.59$1,481.48
74Bridge removal work (0501-0100000A)SF10$1,500.00$1,000.00$2,000.00
75Bridge identification markers (0842-0401000E)EACH1$275.00$300.00$350.00
76Cold plane pavement removal, 3 inches deep (0620-0122000J)SY2,010$9.00$15.00$7.43
77Temporary barrier (0226-0126100F)LF1,500$28.00$40.00$35.00
78Construct and remove temporary roadbed and surfacing (0230-0200000A)LS1$5,000.00$8,000.00$5,000.00
79Temporary impact attenuator, truck mounted (0226-0138000E)EACH1$1.00$20,000$20,000
80Repair temporary impact attenuator, narrow site system (0226-0141300E)EACH2$1.00$500.00$5,000.00
81Extra for asphalt approaches (0749-0100000E)EACH6$1,700.00$2,000.00$1,700.00
ODOT contract 15591: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Bid Data Program yearly workbooks. ODOT publishes rank and unit price only: no bidder names and no bid totals, so these bids cannot be checked against a total and Oregon is left out of the competitor views.

Every contract let that day: ODOT letting of March 20, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy