ODOT contract 15621 bid tabulation

I-5: cottage grove - martin creek. Let by Oregon DOT on October 30, 2025, Region 2. 5 bids received.

Owner
Oregon DOT
Letting
30 OCT 2025
Pay items
155
Data through
13 AUG 2026

Bidders

RankTotal bidAgainst the low bid
1Low
2
3
4
5
ODOT contract 15621: bids by rank

Bid tabulation

LinePay itemUnitQuantityRank 1Rank 2Rank 3Rank 4Rank 5
1Cold plane pavement removal, 2 inches deep (0620-0120000J)SY14,398$2.50$1.00$4.00$3.15$2.75
2Class 2 preparation (0504-0100000J)SY41$200.00$200.00$480.00$225.00$470.00
3Bridge deck cold plane pavement removal, 4-6 inches deep (0503-0102000J)SY360$11.00$13.00$20.00$20.00$37.70
4Class 2 preparation (0504-0100000J)SY31.50$200.00$200.00$530.00$225.00$522.00
5Class 2 preparation (0504-0100000J)SY18.50$200.00$200.00$470.00$225.00$464.40
6Hot applied joint sealant (0585-0400000A)LF141$19.86$19.00$0.24$21.28$33.65
7Polymer membrane (0590-0100000J)SF4,537.50$4.00$4.03$5.80$4.50$5.65
8Extra for asphalt approaches (0749-0100000E)EACH21$100.00$2,575.00$1,000.00$1,100.00$2,260.00
9Bridge approach slab cold plane pavement removal, 4-6 inches deep (0503-0103100J)SY124.25$11.00$7.00$15.00$20.00$72.00
10Sequential arrow signs (0222-0162000E)EACH2$3,000.00$5,000.00$1,700.00$3,600.00$6,600.00
11Temporary flexible pavement markers (0225-0149000E)EACH10,430$0.50$3.15$0.55$1.50$2.50
12Class 2 preparation (0504-0100000J)SY77$200.00$200.00$540.00$225.00$526.00
13Asphaltic plug joint seals (0585-0200100A)LF172$156.98$150.00$0.93$166.40$160.12
14Cold plane pavement removal, 0 - 6 3/4 inches deep (0620-0104000J)SY662$1.00$1.00$2.90$9.00$8.00
15Asphaltic plug joint seals (0585-0200100A)LF93.50$155.08$148.66$171.12$164.71$172.67
168 inch asphalt concrete pavement repair (0748-0104000J)SY2,826$20.00$12.00$18.00$20.50$13.30
17Milepost marker posts (0840-0106000E)EACH12$205.00$300.00$210.00$225.00$200.00
18Pavement legend, type B-HS: arrows (0867-0103100E)EACH8$640.00$625.00$670.00$700.00$645.89
19Guardrail terminals, non-flared (0810-0129000E)EACH21$3,000.00$3,000.00$3,200.00$3,300.00$3,000.00
20Triangular base breakaway sign supports (0930-0112000A)LB1,431.10$11.88$5.59$12.58$13.28$11.95
21Concrete repair (0542-0102001J)SF9$600.00$325.00$780.00$220.00$760.00
22Pollution control plan (0290-0100000A)LS1$500.00$500.00$110.00$500.00$2,500.00
23Portable changeable message signs, roller mounted (0222-0167300E)EACH6$1,000.00$100.00$210.00$4,000.00$1,470.00
24Temporary barricades, type II (0224-0104000E)EACH4$100.00$80.00$69.00$72.00$40.00
25Guardrail posts (0812-0106000E)EACH200$82.00$80.00$85.00$89.00$80.00
26General excavation (0330-0105000K)CY36$55.00$96.00$190.00$56.00$132.00
27Hot applied joint sealant (0585-0400000A)LF93.50$21.39$20.99$27.81$23.53$26.72
28Bridge removal work (0501-0100000A)SF286.50$1.75$17.45$13.96$3.84$3.66
29Perforated steel square tube anchor sign supports (0930-0117000A)LB309.20$7.44$9.70$7.76$8.09$7.28
30Pavement legend, type B-HS: yield line triangle (0867-0169100E)EACH7$150.00$150.00$160.00$167.00$155.00
31Pavement marking tape, grooved, patterned, wet weather (0865-0127100F)LF138,000$6.00$5.96$6.40$6.50$6.15
32BI-directional blue type iar markers (0855-0108100E)EACH12$18.50$18.00$19.00$20.00$18.60
33Emulsified asphalt for tack coat (0730-0100000M)TON88$700.00$0.01$0.01$1.00$1.00
34Bonded membrane removal (0504-0102000J)SY448.50$25.00$9.00$55.00$32.00$54.00
35Asphalt pavement sawcutting, 8 inches deep (0310-0119100F)LF14,300$0.01$2.32$3.00$2.00$3.10
36Concrete and crack sealer (0539-0100000J)SF5,280$2.50$2.21$1.80$2.50$1.75
37Bridge deck cold plane pavement removal, 4 - 6 inches deep (0503-0102000J)SY555$11.00$13.00$16.00$20.00$33.80
38Asphaltic plug joint seals (0585-0200100A)LF141.50$155.48$150.53$176.68$167.14$171.17
39Signs, wide angle sheeting, sheet aluminum (0940-0205100J)SF134$36.00$35.00$37.00$39.00$35.00
40Impact attenuator, type J (0830-0123000E)EACH2$50,000$48,893$52,000$61,000$48,893
41Poured joint seal (0585-0206100A)LF121$41.32$37.00$0.42$41.32$70.54
42Crack sealing (0746-0100000F)LF330$14.00$13.30$36.00$14.75$35.00
43Metal median barrier (0810-0117000F)LF700$84.00$82.00$87.00$91.00$82.00
44Construct grading at guardrail terminals (0810-0142100E)EACH21$6,000.00$12,681$5,500.00$6,200.00$7,600.00
45Guardrail blocks (0812-0108000E)EACH200$30.00$30.00$32.00$33.00$30.00
46Delineators, type 1 (0840-0100000E)EACH462$71.00$75.00$75.00$78.00$70.00
47PG 64-22 asphalt in level 2, 1/2 inch ACP (0745-0620000M)TON54$0.01$0.01$1.00$1.00$1.00
48Asphaltic plug joint seal material (0585-0201100K)CY1.42$9,500.00$9,250.00$6,600.00$10,250$9,160.00
49Signs, standard sheeting, plywood (0940-0203000J)SF65$40.00$35.00$43.00$44.00$40.00
50Concrete pavement cross-stitching repair (1999-9Z90000E)EACH80$100.00$193.11$825.00$215.00$845.00
51Concrete repair (0542-0102001J)SF40.50$600.00$147.40$750.00$132.00$735.00
52Signs, standard sheeting, extruded aluminum (0940-0201000J)SF186.50$50.00$42.00$53.00$55.00$50.00
53BI-directional yellow/red type iar markers (0855-0103200E)EACH45$18.50$18.00$19.00$20.00$18.60
54Bridge identification markers (0842-0401000E)EACH39$82.00$185.00$86.00$89.00$80.00
55Cold plane pavement removal, 3 inches deep (0620-0122000J)SY93,773$1.20$1.00$1.90$3.30$2.30
56Asphaltic plug joint seals (0585-0200100A)LF94$154.26$149.47$159.57$165.96$161.33
57Asphaltic plug joint seals (0585-0200100A)LF85$152.94$150.00$188.24$166.47$189.88
58Class 2 preparation (0504-0100000J)SY10$200.00$200.00$480.00$225.00$473.00
59Concrete repair (0542-0102001J)SF13.50$600.00$262.19$760.00$198.00$748.00
60Asphaltic plug joint seal material (0585-0201100K)CY1.19$9,500.00$9,250.00$6,700.00$10,300$5,535.00
61Hot applied joint sealant (0585-0400000A)LF97$20.62$19.00$0.28$21.65$26.86
62Bridge approach slab cold plane pavement removal, 4 - 6 inches deep (0503-0103100J)SY222.50$11.00$7.00$20.00$20.00$50.00
63Hot applied joint sealant (0585-0400000A)LF93.50$21.39$20.99$27.81$23.53$26.72
64Bridge removal work (0501-0100000A)SF241.50$2.07$20.70$16.56$4.55$4.35
65Bridge deck cold plane pavement removal, 4 - 6 inches deep (0503-0102000J)SY504.50$11.00$13.00$16.00$20.00$33.30
66Bonded membrane removal (0504-0102000J)SY504.50$25.00$9.00$50.00$32.00$48.70
67Metal beam rails (0812-0104000E)EACH100$164.00$160.00$170.00$178.00$160.00
68Wood sign posts (0910-0100000K)FBM1,112$23.50$25.00$25.00$25.50$23.00
69Automatic traffic recorder installation, I-5 mile point 170.25 (0990-0107000A)EACH1$26,000$32,000$26,000$28,500$25,707
70Extra for 8 foot posts (0810-0133000E)EACH190$36.00$36.00$38.00$40.00$36.00
71Midwest guardrail system, type 2A (0810-0146100F)LF4,188$27.50$27.00$29.00$30.00$27.00
72Level 2, 1/2 inch ACP in temporary (0745-0241000M)TON906$95.00$210.00$120.00$118.00$165.00
73Remove existing signs (0905-0100000A)LS1$2,150.00$12,200$2,200.00$2,300.00$2,090.00
74Bridge removal work (0501-0100000A)SF167.50$2.99$29.85$23.88$7.16$6.27
75Class 2 preparation (0504-0100000J)SY10$200.00$200.00$480.00$225.00$473.00
76Bridge approach slab cold plane pavement removal, 4 - 6 inches deep (0503-0103100J)SY222.50$11.00$7.00$20.00$20.00$52.00
77Asphaltic plug joint seals (0585-0200100A)LF172$156.98$150.00$0.93$166.40$160.12
78Asphaltic plug joint seal material (0585-0201100K)CY1$9,500.00$9,250.00$7,000.00$10,250$6,884.00
79Bridge removal work (0501-0100000A)SF141.50$3.53$35.34$28.27$7.77$7.42
80Adjusting guardrail (0812-0101000F)LF19,488$3.80$3.75$4.00$4.25$3.75
81Removal of structures and obstructions (0310-0106000A)LS1$4,000.00$20,000$2,500.00$6,100.00$10,000
82Bonded membrane removal (0504-0102000J)SY356$25.00$9.00$58.00$32.00$56.70
83Hot applied joint sealant (0585-0400000A)LF137.50$19.64$19.00$0.25$21.09$33.64
84Bridge removal work (0501-0100000A)SF155.50$3.22$32.15$25.72$7.07$6.75
85Bridge approach slab cold plane pavement removal, 4 - 6 inches deep (0503-0103100J)SY250$11.00$7.00$19.00$20.00$47.00
86Cold plane pavement removal, 5 inches deep (0620-0124000J)SY99,292$1.25$1.00$3.90$5.00$3.80
87Portable changeable message signs (0222-0164000E)EACH2$15,000$17,000$3,100.00$8,500.00$16,500
88Guardrail transition (0810-0126000E)EACH26$3,500.00$3,425.00$3,700.00$3,800.00$3,425.00
89Perforated steel square tube slip base sign supports (0930-0114000A)LB226.10$5.53$5.97$5.75$5.75$5.31
90Mono-directional white type iar markers, recessed (0855-0106100E)EACH1,480$22.00$21.50$23.00$24.00$22.20
91Delineators, type 5 (0840-0105000E)EACH418$20.50$25.00$21.00$22.00$20.00
92Core correlation of nuclear gauge readings (0745-0900000E)EACH3$2,000.00$1,500.00$2,500.00$2,800.00$3,000.00
93Bridge deck cold plane pavement removal, 4 - 6 inches deep (0503-0102000J)SY448.50$11.00$13.00$17.00$20.00$36.00
94Asphaltic plug joint seal material (0585-0201100K)CY0.90$9,500.00$9,250.00$7,200.00$10,250$7,855.00
95Class 2 preparation (0504-0100000J)SY21$200.00$200.00$480.00$225.00$466.00
96Temporary striping (0225-0153000F)LF255,100$0.35$0.11$0.20$0.27$0.11
97Temporary plastic drums (0224-0145000E)EACH103$60.00$60.00$27.00$99.00$40.00
98Temporary signs (0222-0102000J)SF1,665$30.00$32.00$32.00$16.00$39.00
99Delineators, type 4 alternate 2 (0840-0104200E)EACH181$46.00$30.00$48.00$50.00$45.00
100Traffic control supervisor (0223-0169000E)EACH150$1,800.00$1,250.00$960.00$1,225.00$1,340.00
101Sign support footings (0920-0100000A)CY5.60$2,321.43$5,357.14$2,321.43$2,482.14$2,227.68
102Polymer membrane (0590-0100000J)SF3,240$4.00$4.11$6.60$5.00$6.40
103Bridge removal work (0501-0100000A)SF236$2.12$21.19$16.95$4.66$4.45
104Temporary barricades, type III (0224-0105000E)EACH10$200.00$200.00$110.00$195.00$145.00
105Repair temporary impact attenuator, truck mounted (0226-0141400E)EACH4$1,000.00$1,000.00$1.00$600.00$10,000
106Sediment fence (0280-0113000F)LF603$4.00$4.25$3.00$5.00$4.25
107Gap pattern rumble strips (0857-0101500L)MI10.20$2,000.00$1,950.00$2,100.00$2,200.00$2,015.00
108Culvert drainage markers, type 1 (0842-0201000E)EACH7$76.00$200.00$80.00$83.00$75.00
109Inlet protection, type 3 (0280-0114030E)EACH18$50.00$135.00$170.00$105.00$135.00
110Asphaltic plug joint seals (0585-0200100A)LF84$154.76$150.00$178.57$166.67$180.54
111Bridge approach slab cold plane pavement removal, 2 - 4 inches deep (0503-0103100J)SY124.25$11.00$7.00$14.00$20.00$72.00
112Cold plane pavement removal, 2 - 5 inches deep (0620-0104000J)SY10$100.00$1.00$5.30$3.75$45.89
113Bridge approach slab cold plane pavement removal, 4 - 6 inches deep (0503-0103100J)SY111.50$11.00$7.00$31.00$20.00$95.00
114Bridge removal work (0501-0100000A)SF286.50$1.75$17.45$13.96$3.84$3.66
115Class 2 preparation (0504-0100000J)SY18.50$200.00$200.00$470.00$225.00$464.40
116Hot applied joint sealant (0585-0400000A)LF88$22.73$20.94$27.27$23.86$27.05
117Temporary impact attenuator, truck mounted (0226-0138000E)EACH2$10,000$6,000.00$25,000$36,000$13,225
118Stripe removal (0225-0154000F)LF61,254$0.45$0.44$0.45$0.50$0.45
119Poured joint seal (0585-0206100A)LF111.50$44.84$40.15$57.40$44.84$56.01
120Pavement bar, type B-HS (0867-0145100J)SF372$22.50$22.00$24.00$24.50$22.75
121Midwest guardrail system, type 3 (0810-0146100F)LF113$61.00$60.00$64.00$67.00$60.00
122Cold plane pavement removal, 4 inches deep (0620-0123000J)SY4,602$3.40$1.00$8.00$7.00$3.05
123Polymer membrane (0590-0100000J)SF4,033.50$4.00$4.03$6.00$4.50$5.85
124Class 2 preparation (0504-0100000J)SY21$200.00$200.00$28.00$225.00$466.00
125Sediment barrier, type 3 (0280-0115030F)LF605$5.00$5.50$6.00$8.00$5.50
126Removal of guardrail (0310-0113000A)LF5,138$5.84$5.64$6.03$6.23$5.64
127Class 2 preparation (0504-0100000J)SY25.50$200.00$200.00$450.00$225.00$440.00
128Class 2 preparation (0504-0100000J)SY71$200.00$200.00$560.00$225.00$570.00
129Asphaltic plug joint seal material (0585-0201100K)CY0.98$7,500.00$7,250.00$7,200.00$8,100.00$7,215.00
130Concrete and crack sealer (0539-0100000J)SF9,275$2.50$2.21$2.50$2.50$2.40
131Hot applied joint sealant (0585-0400000A)LF88$22.73$20.94$27.27$23.86$27.05
132Radar speed trailer (0222-0167500E)EACH4$3,000.00$6,250.00$1,200.00$6,700.00$13,235
133Bridge approach slab cold plane pavement removal, 2 - 4 inches deep (0503-0103100J)SY461.50$11.00$7.00$11.00$20.00$37.70
134Asphaltic plug joint seals (0585-0200100A)LF100.50$159.20$149.25$1.39$164.18$139.20
135Signs, standard sheeting, sheet aluminum (0940-0202000J)SF350.80$30.00$32.00$32.00$33.00$30.00
136PG 70-22ER asphalt in level 4, 1/2 inch ACP (0745-0640100M)TON2,864$0.01$0.01$1.10$1.00$1.00
137Bridge removal work (0501-0100000A)SF140$3.57$35.71$28.57$7.86$7.50
138Guardrail terminals, downstream anchor terminal (0810-0132200E)EACH18$1,600.00$1,600.00$1,700.00$1,800.00$1,600.00
139Bonded membrane removal (0504-0102000J)SY555.50$25.00$9.00$49.00$31.00$48.00
140BI-directional white/red type iar markers (0855-0103300E)EACH42$18.50$18.00$19.00$20.00$18.60
141Guardrail connections (0810-0128000E)EACH19$400.00$400.00$430.00$450.00$400.00
142Level 4, 1/2 inch lime treated ACP (0745-0422000M)TON47,720$82.00$100.00$92.00$104.00$105.50
143Class 2 preparation (0504-0100000J)SY35.50$200.00$200.00$410.00$225.00$397.00
144Class 2 preparation (0504-0100000J)SY39$200.00$200.00$450.00$225.00$438.00
145Polymer membrane (0590-0100000J)SF5,000$4.00$4.11$5.80$5.00$5.70
146Bridge removal work (0501-0100000A)SF157$3.18$31.85$25.48$7.01$6.69
147Asphaltic plug joint seal material (0585-0201100K)CY1.46$7,500.00$7,250.00$7,200.00$8,100.00$4,842.00
148Bridge approach slab cold plane pavement removal, 2 - 4 inches deep (0503-0103100J)SY461.50$11.00$7.00$13.00$20.00$37.70
149Cold plane pavement removal, 2 - 3 inches deep (0620-0112000J)SY10$100.00$1.00$5.30$3.00$45.49
150Aggregate base (0641-0102000M)TON85$100.00$68.00$83.00$44.00$84.00
151Continuous rumble strips (0857-0101000L)MI10.50$2,000.00$1,950.00$2,100.00$2,200.00$2,015.00
152Thermoplastic, sprayed, surface, non-profiled (0865-0119600F)LF9,580$2.30$2.25$2.40$2.50$2.30
153Asphaltic plug joint seal material (0585-0201100K)CY0.75$9,500.00$9,250.00$7,000.00$10,250$9,180.00
154Asphaltic plug joint seals (0585-0200100A)LF145$158.62$150.00$165.52$173.45$164.72
155Cold plane pavement removal, 0 - 4 3/4 inches deep (0620-0104000J)SY787$1.00$1.00$2.90$7.25$4.75
ODOT contract 15621: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Bid Data Program yearly workbooks. ODOT publishes rank and unit price only: no bidder names and no bid totals, so these bids cannot be checked against a total and Oregon is left out of the competitor views.

Every contract let that day: ODOT letting of October 30, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy