Straight Line, Inc.: SCDOT bid record
Straight Line, Inc. submitted 36 bids on South Carolina DOT contracts in the data, from 12 JUL 2022 to 10 DEC 2024, and was the low bidder on 23 of them (64%). When it was not low, its total sat a median +8.0% above the low bid.
- Owner
- South Carolina DOT
- Low bid volume
- $22,415,725
- Latest bid
- 10 DEC 2024
- Data through
- 13 OCT 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2022 | 10 | 4 | 40% |
| 2023 | 13 | 8 | 62% |
| 2024 | 13 | 11 | 85% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| District 2 | 18 | 13 | 72% |
| District 7 | 5 | 3 | 60% |
| District 4 | 4 | 2 | 50% |
| District 6 | 4 | 2 | 50% |
| District 5 | 3 | 2 | 67% |
| District 3 | 2 | 1 | 50% |
Pay items where it is most often lowest
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Peek Pavement Marking, LLC | 36 | 10 of 36 |
| TRP Construction Group, LLC | 35 | 0 of 35 |
| Oglesby Construction, Inc. | 23 | 3 of 23 |
| Performance Sealing and Striping, Inc. | 15 | 2 of 15 |
| Carolina Pavement Markings, Inc. | 5 | 3 of 5 |
| Dura Mark, Inc. | 1 | 0 of 1 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 10 DEC 2024 | 5169790 | District 2 | 2024 Center Line Milled in Rumble Stripe District 1 | 1 of 4 | $839,398 | Low, 10% under the second |
| 10 DEC 2024 | 5269880 | District 2 | 2024 Center Line Milled In Rumble Stripe District 2 | 1 of 3 | $1,695,740 | Low, 2.0% under the second |
| 10 DEC 2024 | 5369870 | District 2 | 2024 Center Line Milled in Rumble Stripe District 3 | 1 of 3 | $356,133 | Low, 17% under the second |
| 10 DEC 2024 | 5470180 | District 2 | 2024 Center Line Milled in Rumble Stripe District 4 | 1 of 4 | $1,039,215 | Low, 0.0% under the second |
| 10 DEC 2024 | 5570160 | District 2 | 2024 Center Line Milled in Rumble Stripe District 5 | 1 of 4 | $649,960 | Low, 10% under the second |
| 10 DEC 2024 | 5770170 | District 2 | 2024 Center Line Milled in Rumble Stripe District 7 | 1 of 4 | $974,198 | Low, 11% under the second |
| 13 NOV 2024 | 5170540 | District 2 | 2024 Pavement Markings - District 1 | 2 of 4 | $1,101,040 | +4.0% |
| 13 NOV 2024 | 5270590 | District 2 | 2024 Pavement Markings - District 2 | 1 of 3 | $314,231 | Low, 7.0% under the second |
| 13 NOV 2024 | 5370600 | District 2 | 2024 Pavement Markings - District 3 | 1 of 3 | $625,968 | Low, 16% under the second |
| 13 NOV 2024 | 5470610 | District 2 | 2024 Pavement Markings - District 4 | 1 of 4 | $544,225 | Low, 0.0% under the second |
| 13 NOV 2024 | 5570620 | District 2 | 2024 Pavement Markings - District 5 | 2 of 4 | $1,123,900 | +3.0% |
| 13 NOV 2024 | 5670630 | District 2 | 2024 Pavement Markings - District 6 | 1 of 3 | $2,426,225 | Low, 2.0% under the second |
| 13 NOV 2024 | 5770640 | District 2 | 2024 Pavement Markings - District 7 | 1 of 4 | $937,055 | Low, 2.0% under the second |
| 14 NOV 2023 | 5465730 | District 4 | Install centerline rumble stripes District 4 | 1 of 4 | $1,257,659 | Low, 12% under the second |
| 14 NOV 2023 | 5566820 | District 5 | 2023 Pavement Markings - District 5 | 1 of 4 | $400,554 | Low, 4.0% under the second |
| 14 NOV 2023 | 5665740 | District 6 | Install centerline rumble stripes District 6 | 1 of 5 | $1,657,806 | Low, 2.0% under the second |
| 14 NOV 2023 | 5666830 | District 6 | 2023 Pavement Markings - District 6 | 1 of 4 | $327,430 | Low, 10% under the second |
| 14 NOV 2023 | 5765750 | District 7 | Install centerline rumble stripes District 7 | 1 of 4 | $1,386,027 | Low, 5.0% under the second |
| 14 NOV 2023 | 5766840 | District 7 | 2023 Pavement Markings - District 7 | 1 of 4 | $292,739 | Low, 4.0% under the second |
| 10 OCT 2023 | 5165700 | District 2 | Install centerline rumble stripes District 1 | 2 of 5 | $1,261,005 | +14% |
| 10 OCT 2023 | 5166780 | District 2 | 2023 Pavement Markings - District 1 | 2 of 5 | $292,125 | +8.0% |
| 10 OCT 2023 | 5265720 | District 2 | Install rumble stripes in District 2 | 1 of 4 | $1,798,233 | Low, 5.0% under the second |
| 10 OCT 2023 | 5266790 | District 2 | 2023 Pavement Markings - District 2 | 2 of 4 | $352,854 | +7.0% |
| 10 OCT 2023 | 5365710 | District 3 | Install centerline rumble stripes District 3 | 1 of 4 | $1,032,664 | Low, 7.0% under the second |
| 10 OCT 2023 | 5366800 | District 3 | 2023 Pavement Markings - District 3 | 2 of 4 | $268,704 | +11% |
How this record was read
SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.
- Every bid counted here matched its published total to within one dollar; SCDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.