TRP Construction Group, LLC: SCDOT bid record

TRP Construction Group, LLC submitted 92 bids on South Carolina DOT contracts in the data, from 08 FEB 2022 to 09 JUN 2026, and was the low bidder on 12 of them (13%). When it was not low, its total sat a median +47% above the low bid.

Owner
South Carolina DOT
Low bid volume
$15,922,310
Latest bid
09 JUN 2026
Data through
13 OCT 2026
92Bids
12Low bids
13Win rate, percent
+47%Median gap to the low bid when not low, 80 bids

By year

YearBidsLow bidsWin rate
20222314%
20231300%
20242300%
202522418%
202611764%
TRP Construction Group, LLC, SCDOT: bids and low bids by year of letting

By district

DistrictBidsLow bidsWin rate
District 2451022%
District 58113%
District 3700%
District 4700%
District 67114%
District 7700%
Statewide400%
District 1300%
Statewide (Multiple Counties)200%
District 1, District 4100%
District 6, District 7100%
TRP Construction Group, LLC, SCDOT: bids and low bids by district

Pay items where it is most often lowest

Pay itemCodeUnitLines bidLowest on the lineIts median priceAll bidders' median
Removal of pavement markings6319505LF5815 (26%)$0.25$0.70
4" yellow solid lines(PVT.edge lines) thermo- 90 mil.6271074LF5313 (25%)$0.45$0.55
Pref.flex.retro.PVMT.mark(T- 1)perm.(60MIL)4"yel.sol.6351450LF3412 (35%)$5.68$5.00
4" white solid lines (PVT. edge lines) thermo.- 90 mil.6271010LF5911 (19%)$0.45$0.54
8" white solid lines thermoplastic - 125 mil.6271015LF3611 (31%)$2.05$3.00
Pref.flex.retro.PVMT.mark(T- 1)perm.60MIL4"WH.broken6351100LF3311 (33%)$7.00$5.00
Pref.flex.retro.PVMT.mark(T- 1)perm.(60MIL)4"WH.solid6351150LF2811 (39%)$4.25$5.00
Permanent yellow pavement markers BI-dir.- 4"X4"6301100EACH8410 (12%)$4.75$6.50
4" white broken lines(gaps excl.)thermoplastic- 90 mil.6271005LF3610 (28%)$0.52$0.60
Pref.flex.retro.PVMT.mark(T- 1)perm.(60MIL)4"yel.broken6351400LF3110 (32%)$6.75$4.50
24IN X 36IN white triang. yield bar (gaps exc)thermo-125MIL6271024LF358 (23%)$68.00$15.85
4" yellow broken lines(gaps exc)thermoplastic - 90 mil.6271064LF596 (10%)$0.55$0.50
TRP Construction Group, LLC, SCDOT: pay items where its unit price was the lowest on the line

A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.

Who it meets most

FirmContracts in commonThat firm ranked ahead
Peek Pavement Marking, LLC8768 of 87
Straight Line, Inc.3535 of 35
Oglesby Construction, Inc.3329 of 33
A & A Safety, Inc.2522 of 25
Thorn Creek Markers LLC2222 of 22
Alpha Space Control, LLC2010 of 20
Performance Sealing and Striping, Inc.1917 of 19
W. L. Markers, Inc./K & S Markers, Inc.77 of 7
Carolina Pavement Markings, Inc.66 of 6
T&H Construction and Markings, LLC52 of 5
TRP Construction Group, LLC, SCDOT: the firms on the same contracts most often

Latest bids

LetContractDistrictProjectRankIts bidAgainst the low bid
09 JUN 20265177180District 2District 1 Pavement Markings2 of 4$1,590,064+9.0%
09 JUN 20265277190District 2District 2 Pavement Marking1 of 3$1,085,655Low, 7.0% under the second
09 JUN 20265377200District 2District 3 Pavement Markings1 of 2$2,372,101Low, 19% under the second
09 JUN 20265477210District 2District 4 Pavement Markings1 of 3$1,268,919Low, 30% under the second
09 JUN 20265577220District 2District 5 Pavement Marking1 of 3$1,023,897Low, 14% under the second
09 JUN 20265677230District 2District 6 Pavement Markings1 of 3$648,931Low, 12% under the second
09 JUN 20265777240District 2District 7 Pavement Markings1 of 4$1,022,153Low, 12% under the second
10 MAR 20265576220District 22026 Raised Pavement Markers - District 56 of 6$378,200+45%
10 MAR 20265676230District 22026 Raised Pavement Markers - District 64 of 5$261,380+42%
10 MAR 20265776240District 22026 Raised Pavement Markers - District 76 of 6$286,525+43%
13 JAN 20265275280District 22025 Center Line Milled In Rumble Strip District 21 of 3$2,558,798Low, 0.0% under the second
09 DEC 20252675870District 5SC 31 Pavement Markings - US 501 to SC 7071 of 2$856,035Low, 5.0% under the second
09 DEC 20255375290District 22025 Center Line Milled In Rumble Strip District 32 of 3$446,633+6.0%
09 DEC 20255575060District 22025 Pavement Markings - District 52 of 3$1,994,8700.0%
09 DEC 20255675070District 22025 Pavement Markings - District 61 of 3$2,293,827Low, 0.0% under the second
09 DEC 20255775080District 22025 Pavement Markings - District 71 of 4$657,220Low, 1.0% under the second
09 DEC 20258875840District 1, District 42025 Milled In Rumble Strip District 1 & 42 of 3$888,015+4.0%
09 DEC 20258875900District 6, District 72025 Milled In Rumble Strip District 6 & 72 of 3$2,168,363+16%
12 NOV 20255175020District 22025 Pavement Markings - District 14 of 4$832,939+15%
12 NOV 20255275030District 22025 Pavement Markings - District 23 of 4$712,343+2.0%
12 NOV 20255375040District 22025 Pavement Markings - District 32 of 5$648,910+2.0%
12 NOV 20255475050District 22025 Pavement Markings - District 41 of 5$672,411Low, 1.0% under the second
14 OCT 20255774770District 22026 District 7 Fast Dry Paint Contract5 of 5$425,274+74%
09 SEP 20255573370District 22026 District 5 Secondary Route Raised Pavement Markers3 of 3$723,900+41%
08 APR 20258872830Statewide2025 Upper State RPMs4 of 4$1,092,800+150%
TRP Construction Group, LLC: latest SCDOT bids in the data

How this record was read

SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.

  • Every bid counted here matched its published total to within one dollar; SCDOT's rank decides who was low.
  • The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
  • A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.

A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.