A & A Safety, Inc.: SCDOT bid record
A & A Safety, Inc. submitted 38 bids on South Carolina DOT contracts in the data, from 08 FEB 2022 to 10 MAR 2026, and was the low bidder on 0 of them (0%). When it was not low, its total sat a median +22% above the low bid.
- Owner
- South Carolina DOT
- Low bid volume
- $0
- Latest bid
- 10 MAR 2026
- Data through
- 13 OCT 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2022 | 10 | 0 | 0% |
| 2023 | 9 | 0 | 0% |
| 2024 | 7 | 0 | 0% |
| 2025 | 9 | 0 | 0% |
| 2026 | 3 | 0 | 0% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| District 2 | 10 | 0 | 0% |
| Statewide | 6 | 0 | 0% |
| District 3 | 4 | 0 | 0% |
| District 4 | 4 | 0 | 0% |
| District 5 | 4 | 0 | 0% |
| District 6 | 3 | 0 | 0% |
| District 7 | 3 | 0 | 0% |
| District 1 | 2 | 0 | 0% |
| Statewide (Multiple Counties) | 2 | 0 | 0% |
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Peek Pavement Marking, LLC | 35 | 12 of 35 |
| Thorn Creek Markers LLC | 28 | 28 of 28 |
| TRP Construction Group, LLC | 25 | 3 of 25 |
| W. L. Markers, Inc./K & S Markers, Inc. | 10 | 10 of 10 |
| Alpha Space Control, LLC | 3 | 3 of 3 |
| Al-Mumin Enterprise LLC | 2 | 2 of 2 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 10 MAR 2026 | 5576220 | District 2 | 2026 Raised Pavement Markers - District 5 | 5 of 6 | $362,870 | +39% |
| 10 MAR 2026 | 5676230 | District 2 | 2026 Raised Pavement Markers - District 6 | 3 of 5 | $250,845 | +36% |
| 10 MAR 2026 | 5776240 | District 2 | 2026 Raised Pavement Markers - District 7 | 5 of 6 | $272,225 | +36% |
| 08 APR 2025 | 8872830 | Statewide | 2025 Upper State RPMs | 2 of 4 | $584,217 | +34% |
| 08 APR 2025 | 8872840 | Statewide | 2025 Lower State RPMs | 2 of 4 | $597,521 | +34% |
| 11 MAR 2025 | 5171820 | District 1 | 2025 Raised Pavement Markers - District 1 | 2 of 4 | $296,680 | +21% |
| 11 MAR 2025 | 5271830 | District 2 | 2025 Raised Pavement Markers - District 2 | 3 of 4 | $316,173 | +23% |
| 11 MAR 2025 | 5371870 | District 3 | 2025 Raised Pavement Markers - District 3 | 2 of 4 | $355,610 | +17% |
| 11 MAR 2025 | 5471880 | District 4 | 2025 Raised Pavement Markers - District 4 | 3 of 4 | $265,260 | +25% |
| 11 MAR 2025 | 5571890 | District 5 | 2025 Raised Pavement Markers - District 5 | 3 of 4 | $414,585 | +33% |
| 11 MAR 2025 | 5671900 | District 6 | 2025 Raised Pavement Markers - District 6 | 2 of 4 | $260,370 | +13% |
| 11 MAR 2025 | 5771910 | District 7 | 2025 Raised Pavement Markers - District 7 | 3 of 4 | $299,725 | +22% |
| 09 JUL 2024 | 5569190 | District 2 | 2025 District 5 Secondary Route Raised Pavement Markers | 3 of 3 | $677,295 | +72% |
| 13 FEB 2024 | 5168340 | District 1 | District 1 RPMS | 3 of 4 | $378,238 | +24% |
| 13 FEB 2024 | 5268350 | District 2 | District 2 RPMs | 3 of 4 | $360,470 | +22% |
| 13 FEB 2024 | 5368360 | District 3 | District 3 RPMs | 4 of 4 | $460,205 | +28% |
| 13 FEB 2024 | 5468370 | District 4 | District 4 RPMs | 3 of 4 | $327,536 | +20% |
| 13 FEB 2024 | 8868320 | Statewide (Multiple Counties) | 2024 Upper State Interstate RPMS | 2 of 3 | $556,263 | +40% |
| 13 FEB 2024 | 8868330 | Statewide (Multiple Counties) | 2024 Lower State Interstate RPMs | 2 of 4 | $564,569 | +38% |
| 14 MAR 2023 | 5564610 | District 5 | Pavement Markers - District 5 | 2 of 3 | $414,098 | +7.0% |
| 14 MAR 2023 | 5664630 | District 6 | Pavement Markers - District 6 | 2 of 3 | $297,735 | +2.0% |
| 14 MAR 2023 | 5764640 | District 7 | Pavement Markers - District 7 | 2 of 3 | $349,825 | 0.0% |
| 14 FEB 2023 | 5164570 | District 2 | Pavement Markers - District 1 | 2 of 3 | $332,390 | +12% |
| 14 FEB 2023 | 5264580 | District 2 | Pavement Markers - District 2 | 2 of 3 | $320,200 | +11% |
| 14 FEB 2023 | 5364590 | District 3 | Pavement Markers - District 3 | 2 of 3 | $427,850 | +21% |
How this record was read
SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.
- Every bid counted here matched its published total to within one dollar; SCDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.