SCDOT letting results, February 14, 2023
17 contracts let by South Carolina DOT on February 14, 2023, $38,855,060 in low bids, a median of 3 bidders per contract.
- Owner
- South Carolina DOT
- Contracts
- 17
- Low bids, total
- $38,855,060
- Data through
- 13 OCT 2026
Contracts let that day
| Contract | Project | District | Bids | Low bidder | Low bid | Second bid | Gap | Source |
|---|---|---|---|---|---|---|---|---|
| 2614850 | Widening - SC 9 (Horry Co) | District 5 | 2 | King Asphalt, Inc. | $14,222,167 | $15,551,587 | +9.0% | SCDOT |
| 2664710 | Rehabilitation - Horry County | District 5 | 2 | Coastal Asphalt, LLC | $4,999,406 | $5,650,054 | +13% | SCDOT |
| 5564700 | Rehabilition - Georgetown/Williamsburg Co | District 5 | 2 | Coastal Asphalt, LLC | $4,185,837 | $5,205,729 | +24% | SCDOT |
| 8862701 | Signing - Lower State (On-Call) | Statewide | 1 | W.M. Roebuck, Incorporated | $3,559,622 | SCDOT | ||
| 0264510 | Rehabilitation - Aiken Co | District 7 | 2 | Satterfield Construction Company, Inc. | $2,998,962 | $3,860,501 | +29% | SCDOT |
| 3564690 | Rehabilitation - Marlboro County | District 5 | 2 | Lynches River Contracting, Inc. | $2,297,010 | $2,304,565 | 0.0% | SCDOT |
| 1164380 | Rehabilitation - Cherokee County | District 4 | 2 | Rogers Group, Inc. | $1,936,580 | $2,371,488 | +22% | SCDOT |
| 5164260 | Signal Upgrades - Lexington/Richland Co | District 1 | 4 | Grant Electrical Contracting, LLC | $1,159,639 | $1,258,900 | +9.0% | SCDOT |
| 4464150 | Bridge Repairs - S-18 (Padgetts Creek) | District 4 | 9 | Dane Construction, LLC | $861,818 | $899,128 | +4.0% | SCDOT |
| 1264200 | Bridge Repair - SC 97 (Turkey Creek) | District 4 | 9 | Dane Construction, LLC | $430,320 | $488,550 | +14% | SCDOT |
| 8864680 | Pavement Markings - Lower State (Interstate) | Statewide | 3 | Thorn Creek Markers LLC | $399,041 | $442,668 | +11% | SCDOT |
| 8864670 | Pavement Markings - Upper State (Interstate) | Statewide | 3 | Thorn Creek Markers LLC | $373,034 | $430,042 | +15% | SCDOT |
| 5364590 | Pavement Markers - District 3 | District 3 | 3 | Thorn Creek Markers LLC | $352,860 | $427,850 | +21% | SCDOT |
| 5164570 | Pavement Markers - District 1 | District 2 | 3 | Thorn Creek Markers LLC | $295,696 | $332,390 | +12% | SCDOT |
| 5264580 | Pavement Markers - District 2 | District 2 | 3 | Thorn Creek Markers LLC | $288,790 | $320,200 | +11% | SCDOT |
| 5464600 | Pavement Markers - District 4 | District 4 | 3 | Thorn Creek Markers LLC | $265,580 | $300,240 | +13% | SCDOT |
| 2857990 | Enhancement - S-349 (Kershaw Co) | District 1 | 4 | First Construction Management, LLC | $228,701 | $283,612 | +24% | SCDOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than SCDOT received, the others did not match their published totals and are left out.