SCDOT contract 0469020 bid tabulation
District 2,Package 6. Let by South Carolina DOT on May 13, 2025, Anderson, District 2. 7 bids received; low bid $1,954,034 by United Infrastructure Group, Inc..
- Owner
- South Carolina DOT
- Letting
- 13 MAY 2025
- Pay items
- 41
- Data through
- 13 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | United Infrastructure Group, Inc. | $1,954,034 | Low |
| 2 | Cekra, Inc. | $1,965,499 | +1.0% |
| 3 | Freyssinet, Inc. | $2,465,130 | +26% |
| 4 | Ipc Paving LLC | $2,648,664 | +36% |
| 5 | Omega Coatings & Construction, LLC | $2,920,815 | +49% |
| 6 | Dane Construction, LLC | $3,752,782 | +92% |
| 7 | American Civil Constructors West Coast, | $4,797,000 | +145% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. United Infrastructure Group, Inc. | 2. Cekra, Inc. | 3. Freyssinet, Inc. | 4. Ipc Paving LLC | 5. Omega Coatings & Construction, LLC | 6. Dane Construction, LLC |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Mobilization (1031000) | LS | 1 | $97,702 | $90,000 | $122,000 | $132,000 | $225,000 | $185,000 |
| 0020 | Bonds and insurance (1032010) | LS | 1 | $58,621 | $36,000 | $49,000 | $52,000 | $40,000 | $75,000 |
| 0030 | Removal & disposal of designated portions of existing bridge (2028200) | LS | 1 | $91,800 | $40,000 | $16,600 | $67,000 | $25,000 | $150,000 |
| 0040 | No. 57 stone for backfill (2052000) | TON | 7.90 | $572.25 | $600.00 | $265.00 | $182.00 | $600.00 | $105.00 |
| 0050 | Liquid asphalt binder PG64-22 (4011004) | TON | 5.50 | $885.00 | $900.00 | $1,430.00 | $800.00 | $1,060.00 | $885.00 |
| 0060 | Milling existing asphalt pavement 2.0" (4013120) | SY | 756 | $22.00 | $22.00 | $35.00 | $35.00 | $26.00 | $22.00 |
| 0070 | Asphalt surface course type B (4040320) | TON | 92 | $360.00 | $375.00 | $580.00 | $650.00 | $432.00 | $360.00 |
| 0080 | Traffic control (6011000) | LS | 1 | $20,000 | $35,000 | $24,200 | $48,000 | $175,000 | $150,000 |
| 0090 | Barricade - type III (6041200) | LF | 54 | $45.00 | $30.00 | $40.00 | $26.50 | $135.00 | $22.50 |
| 0100 | Permanent construction signs (ground mounted) (6051120) | SF | 1,197 | $6.50 | $14.00 | $10.00 | $6.25 | $8.45 | $6.50 |
| 0110 | Permanent construction signs (barricade mounted) (6051125) | SF | 78 | $6.50 | $14.00 | $14.00 | $6.00 | $8.45 | $6.50 |
| 0120 | Construction zone electric changeable message sign (trailer (6062000) | EACH | 2 | $1,900.00 | $6,500.00 | $8,700.00 | $2,700.00 | $570.00 | $17,900 |
| 0130 | Type B - flashing light (608100B) | EACH | 16 | $20.00 | $100.00 | $64.00 | $85.00 | $60.00 | $45.00 |
| 0140 | 4" white solid lines (PVT. edge lines) epoxy paint fast cure (6262010) | LF | 680 | $5.00 | $5.00 | $8.00 | $5.00 | $10.00 | $7.00 |
| 0150 | 4"yellow solid lines- PVT.edge&no passing zone - epoxy paint fast cure (6262110) | LF | 680 | $5.00 | $5.00 | $8.00 | $5.00 | $10.00 | $7.00 |
| 0160 | 4" white solid lines (PVT. edge lines) thermo.- 90 mil. (6271010) | LF | 400 | $2.00 | $2.00 | $3.00 | $2.00 | $6.00 | $2.50 |
| 0170 | 4" yellow solid lines(PVT.edge lines) thermo- 90 mil. (6271074) | LF | 400 | $2.00 | $2.00 | $3.00 | $2.00 | $6.00 | $2.50 |
| 0180 | Permanent yellow pavement markers BI-dir.- 4"X4" (6301100) | EACH | 16 | $7.50 | $7.50 | $26.00 | $7.50 | $10.00 | $45.00 |
| 0190 | Milled-in rumble strip (6321000) | MI | 0.10 | $12,000 | $100,000 | $40,300 | $500.00 | $100,000 | $500.00 |
| 0200 | Epoxy crack injection (7013446) | LF | 100 | $80.00 | $85.00 | $94.00 | $190.00 | $125.00 | $35.00 |
| 0210 | Reinf. steel for structures (bridge) (7031200) | LB | 500 | $0.50 | $3.00 | $7.50 | $7.00 | $10.00 | $20.00 |
| 0220 | Structural steel (7091120) | LB | 24,917 | $0.50 | $6.00 | $8.00 | $10.00 | $38.00 | $15.00 |
| 0230 | Cleaning and painting existing structural steel (7101000) | LS | 1 | $215,600 | $175,000 | $578,000 | $495,000 | $360,000 | $287,325 |
| 0240 | Elastomeric bearing (7243100) | EACH | 24 | $2,800.00 | $6,000.00 | $2,530.00 | $4,500.00 | $3,500.00 | $600.00 |
| 0250 | Machine preparation of existing surface (7260200) | SY | 1,663 | $17.51 | $18.00 | $39.00 | $26.00 | $30.00 | $40.00 |
| 0260 | Blast cleaning (7260300) | SY | 1,663 | $9.27 | $7.00 | $23.00 | $12.00 | $25.00 | $14.00 |
| 0270 | Concrete class 4000 for full depth deck patching (7260800) | CY | 10 | $1,800.00 | $4,200.00 | $2,130.00 | $7,100.00 | $9,500.00 | $8,000.00 |
| 0280 | Concrete class 4000 for partial depth deck patching (7260850) | SY | 40 | $150.00 | $280.00 | $1,780.00 | $1,100.00 | $1,600.00 | $1,000.00 |
| 0290 | Jacking bridge (7262000) | LS | 1 | $200,000 | $160,000 | $40,000 | $158,000 | $81,000 | $380,713 |
| 0300 | Rip-rap (class B) (8041020) | TON | 11.40 | $200.00 | $600.00 | $280.00 | $165.00 | $200.00 | $200.00 |
| 0310 | Geotextile for erosion control under riprap(class 2)type A (8048200) | SY | 40 | $6.42 | $10.00 | $38.00 | $26.00 | $10.00 | $7.00 |
| 0320 | BR006 - reinforced concrete tee-beam repair type A (8990011) | CF | 5 | $720.00 | $2,500.00 | $970.00 | $2,250.00 | $950.00 | $5,000.00 |
| 0330 | Bridge pile wrap (8990017) | LF | 80 | $800.00 | $900.00 | $1,110.00 | $735.00 | $280.00 | $2,000.00 |
| 0340 | BR004 - reinforced concrete repair type 1 (8990018) | CF | 5 | $400.00 | $2,500.00 | $795.00 | $1,770.00 | $850.00 | $3,000.00 |
| 0350 | BR005 - reinforced concrete repair type 2 (8990019) | CF | 55 | $400.00 | $2,500.00 | $800.00 | $2,000.00 | $950.00 | $3,000.00 |
| 0360 | BR010 – deck joint repair type 1 (8990020) | LF | 378 | $34.25 | $85.00 | $40.00 | $65.00 | $85.00 | $150.00 |
| 0370 | BR018 - beam end web and flange repair (8990022) | LF | 192 | $2,500.00 | $1,200.00 | $870.00 | $1,455.00 | $300.00 | $4,250.00 |
| 0380 | BR040 – corrosion inhibiting bonding agent (8990023) | SF | 325 | $20.00 | $100.00 | $24.00 | $19.25 | $25.00 | $165.00 |
| 0390 | Cleaning & painting existing steel piling (8990026) | EACH | 28 | $5,000.00 | $1,800.00 | $7,250.00 | $5,500.00 | $2,500.00 | $6,250.00 |
| 0400 | Polyester polymer concrete (PCC) overlay (8990044) | CY | 52 | $5,000.00 | $3,800.00 | $5,190.00 | $4,000.00 | $4,200.00 | $3,800.00 |
| 0410 | Place & finish polyester polymer concrete (PCC) material (8990045) | SY | 1,663 | $22.00 | $80.00 | $130.00 | $95.00 | $75.00 | $80.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from SCDOT's tabulation for this contract. SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.
Every contract let that day: SCDOT letting of May 13, 2025. Compiled by Mirage Metrics.