SCDOT contract 2669360 bid tabulation

2025 Horry Rehabilitation. Let by South Carolina DOT on March 11, 2025, Horry, District 5. 2 bids received; low bid $13,812,914 by King Asphalt, Inc..

Owner
South Carolina DOT
Letting
11 MAR 2025
Pay items
67
Data through
13 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1King Asphalt, Inc.$13,812,914Low
2Palmetto Corp. of Conway$15,171,872+10%
SCDOT contract 2669360: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. King Asphalt, Inc.2. Palmetto Corp. of Conway
0010Mobilization (1031000)LS1$400,000$350,000
0020Bonds and insurance (1032010)LS1$63,000$285,000
0030Removal & disposal of existing pavement (2023000)SY3,800$35.50$19.25
0040Removal & disposal of existing curb (2024100)LF1,000$16.25$17.10
0050Borrow excavation (2033000)CY4,566$77.00$47.00
0060Excavation for shoulder paving (2036000)STA1,649.47$32.00$30.50
0070Hauling of excavated shoulder material (2072000)STA1,649.47$76.00$63.10
0080Maintenance stone (3059900)TON296$56.00$110.00
0090HMA shoulder widening course (3104000)TON9,791.76$67.80$82.80
0100Liquid asphalt binder PG64-22 (4011004)TON3,670.99$685.00$600.00
0110Aramid fiber (4011500)LB1,982.44$44.00$63.85
0120Full depth asph. pav. patching 8" unif (4012080)SY29,100$69.20$72.75
0130Full depth asph. pav. patching 10"unif (4012100)SY500$82.60$123.40
0140Milling existing asphalt pavement 2.0" (4013120)SY293,158$2.80$3.05
0150Milling existing asphalt pavement (variable) (4013990)SY1,850$21.85$25.70
0160Asphalt surface course type B (4040320)TON33,471.26$79.65$115.00
0170Asphalt surface course type C (4040340)TON18,001.09$66.45$85.00
0180Asphalt surface course type D (4040350)TON1,420$88.45$129.50
0190Driveway paving-surface type D (4047230)TON1,755.63$134.50$205.00
0200Traffic control (6011000)LS1$840,000$598,700
0210Permanent construction signs (ground mounted) (6051120)SF5,476$6.15$5.35
02204" white broken lines -(gaps excluded)-fast dry paint (6240005)LF55,566$0.10$0.10
02304" white solid lines (PVT. edge lines)-fast dry paint (6240010)LF783,060$0.10$0.10
02406" white solid lines (PVT. edge lines)-fast dry paint (6240012)LF7,929$0.10$0.10
02508"white solid lines (crosswalk& channelization)fast dry paint (6240015)LF16,416$0.10$0.10
026024" white solid lines (stop/diagonal lines)-fast dry paint (6240025)LF18,726$0.10$0.25
0270White single arrow (left, straight, right)-fast dry paint (6240030)EACH267$5.00$15.00
0280White word message "only"- fast dry paint (6240035)EACH132$5.00$15.00
0290White combination arrow(STR.& RT.or STR.& LT.)fast dry paint (6240040)EACH12$5.00$15.00
03004" yellow broken lines(gaps exc) - fast dry paint (6240105)LF33,555$0.10$0.10
03104"yellow solid line(PVT.edge&no passing zone)-fast dry paint (6240110)LF540,165$0.10$0.10
03206" yellow solid line on curb/median - fast dry paint (6240112)LF1,035$2.00$1.50
03304" white broken lines(gaps excl.)thermoplastic- 90 mil. (6271005)LF18,522$0.47$0.75
03404" white solid lines (PVT. edge lines) thermo.- 90 mil. (6271010)LF199,244$0.45$0.42
03506" white solid lines (PVT. edge lines) thermo.- 90 mil. (6271012)LF64,419$0.60$0.60
03608" white solid lines thermoplastic - 125 mil. (6271015)LF5,472$3.00$2.00
037012IN X 18IN white triang. yield bar (gaps exc)thermo-125MIL (6271023)LF30$30.00$25.00
038024" white solid lines (stop/diag lines)-thermo.-125 mil (6271025)LF7,085$12.00$6.00
0390White single arrows (LT, STRGHT, RT) thermo.-125 mil. (6271030)EACH77$125.00$75.00
0400White word message "only" - thermoplastic - 125 mil. (6271035)EACH44$189.00$75.00
0410White combination arrows(STR&RT.or STR& LT)thermo-125MIL (6271040)EACH4$189.00$100.00
0420White lane drop arrow(LT.or RT.)thermo-125MIL (6271043)EACH12$200.00$150.00
04304" yellow broken lines(gaps exc)thermoplastic - 90 mil. (6271064)LF10,885$0.47$0.42
04404" yellow solid lines(PVT.edge lines) thermo- 90 mil. (6271074)LF179,755$0.45$0.42
045024" yellow solid lines - thermoplastic - 125 mil. (6271080)LF370$10.25$6.00
0460Permanent clear pavement markers- mono-dir.- 4"X4" (6300005)EACH910$5.00$5.00
0470Permanent yellow pavement markers BI-dir.- 4"X4" (6301100)EACH1,656$4.00$5.00
0480Milled-in rumble strip (6321000)MI42.90$514.50$500.00
0490Pref.flex.retro.PVMT.mark(T- 1)perm.60MIL4"WH.broken (6351100)LF600$5.00$4.50
0500Pref.flex.retro.PVMT.mark(T- 1)perm.(60MIL)4"WH.solid (6351150)LF3,601$5.00$4.50
0510Pref.flex.retro.PVMT.mark(T- 1)perm.(60MIL)6"WH.solid (6351155)LF180$7.00$6.50
0520Pref.flex.retro.PVMT.mark(T- 1)perm.(60MIL)24"WH.sol (6351300)LF15$30.00$24.00
0530Pref.flex.retro.PVMT.mark(T- 1)perm.(60MIL)4"yel.sol. (6351450)LF2,886$7.00$4.50
0540Furnish & install 1.0" schedule 80 PVC conduit (6750275)LF520$25.00$24.75
0550Furnish & install 2.0" schedule 80 PVC conduit (6750278)LF520$16.50$16.25
0560Furnish & instl no. 14 copper wire,1-conductor for loop wire (6770413)LF19,500$0.60$0.56
0570Sawcut for loop detector (6780495)LF7,680$9.15$9.00
0580F&I-13"X24"X18"D.elec.flush undgrd.enclos- (STR.poly.conc.)HD (6800518)EACH19$715.00$703.00
0590Temporary adjustment of traffic signal equipment (6885993)EACH10$9,250.00$9,000.00
0600Concrete curb and gutter(1'-6") vertical face (7203110)LF150$36.50$30.90
0610Concrete curb and gutter(2'-0") vertical face (7203210)LF850$40.00$43.50
0620Concrete sidewalk(4" uniform) (7204100)SY2,150$95.50$77.80
0630Detectable warning material (7204900)SF675$60.00$35.00
0640Concrete driveway(6" uniform) (7205000)SY300$117.00$135.40
0650Pedestrian ramp construction (7209000)SY1,350$142.00$132.45
0660Surface applied detectable warning (7209100)SF387.50$60.00$45.00
0670Permanent grassing for non-permitted resurfacing projects (8100102)ACRE16.19$3,200.00$3,200.00
SCDOT contract 2669360: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from SCDOT's tabulation for this contract. SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.

Every contract let that day: SCDOT letting of March 11, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy