Detectable warning material, SCDOT 7204900
Low bidders on SCDOT contracts carried a median of $55.00 per SF for this item, over the 24 months to 13 OCT 2026, across 142 low bids. Half of all 421 bids fell between $45.00 and $65.00.
- Owner
- South Carolina DOT
- Item
- 7204900
- Unit
- SF
- Data through
- 13 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2022 | 92 | 92 | $45.00 | 278 | $45.00 |
| 2023 | 53 | 53 | $50.00 | 142 | $50.00 |
| 2024 | 99 | 99 | $55.00 | 242 | $52.00 |
| 2025 | 79 | 79 | $53.59 | 239 | $55.00 |
| 2026 | 49 | 49 | $55.00 | 145 | $55.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| District 1 | 20 | $55.00 | 83 | $50.00 |
| District 7 | 28 | $60.00 | 71 | $59.00 |
| District 3 | 22 | $52.00 | 71 | $58.00 |
| District 4 | 22 | $55.00 | 70 | $51.75 |
| District 5 | 25 | $50.00 | 64 | $55.00 |
| District 6 | 13 | $60.00 | 32 | $61.92 |
| District 2 | 12 | $88.00 | 30 | $86.70 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (SF) | Low bids | Low-bid median |
|---|---|---|
| 12.50 to 37.50 | 35 | $60.50 |
| 40 to 100 | 36 | $56.88 |
| 105 to 325 | 35 | $50.00 |
| 350 to 1,613 | 36 | $55.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Palmetto Corp. of Conway | 182 | 153 (84%) |
| King Asphalt, Inc. | 109 | 21 (19%) |
| Reeves Construction Company | 77 | 21 (27%) |
| Aos Specialty Contractors, Inc. | 28 | 11 (39%) |
| Banks Construction Company | 19 | 11 (58%) |
| C.R. Jackson, Inc. | 106 | 10 (9%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 09 SEP 2026 | 0277810 | District 7 | 25 | $52.80 | $66.40 | 2 | Satterfield Construction Company, Inc. | SCDOT |
| 09 SEP 2026 | 0277850 | District 7 | 12.50 | $52.80 | $53.90 | 2 | Satterfield Construction Company, Inc. | SCDOT |
| 09 SEP 2026 | 1877890 | District 6 | 30 | $60.00 | $66.00 | 3 | Banks Construction Company | SCDOT |
| 09 SEP 2026 | 2375800 | District 3 | 100 | $55.75 | $55.75 | 5 | Wright Brothers Construction Company, | SCDOT |
| 09 SEP 2026 | 2376930 | District 3 | 37.50 | $68.00 | $65.00 | 4 | Rogers Group, Inc. | SCDOT |
| 09 SEP 2026 | 2777910 | District 6 | 30 | $63.85 | $65.00 | 3 | Blythe Construction, Inc. | SCDOT |
| 09 SEP 2026 | 2977880 | District 4 | 350 | $60.00 | $37.15 | 4 | C.R. Jackson, Inc. | SCDOT |
| 09 SEP 2026 | 3277620 | District 1 | 75 | $55.00 | $51.44 | 4 | C.R. Jackson, Inc. | SCDOT |
| 09 SEP 2026 | 3477780 | District 5 | 225 | $52.00 | $52.00 | 3 | C.R. Jackson, Inc. | SCDOT |
| 09 SEP 2026 | 4276800 | District 3 | 137.50 | $45.00 | $66.50 | 4 | Palmetto Corp. of Conway | SCDOT |
| 09 SEP 2026 | 4672780 | District 4 | 270 | $84.75 | $60.00 | 3 | Aos Specialty Contractors, Inc. | SCDOT |
| 09 SEP 2026 | 5577840 | District 5 | 75 | $55.00 | $50.00 | 2 | C.R. Jackson, Inc. | SCDOT |
| 09 SEP 2026 | 5777540 | District 7 | 110 | $65.00 | $60.00 | 2 | Blythe Construction, Inc. | SCDOT |
| 09 SEP 2026 | 5777760 | District 7 | 35 | $55.00 | $55.00 | 3 | C.R. Jackson, Inc. | SCDOT |
| 11 AUG 2026 | 1077530 | District 6 | 60 | $95.00 | $85.00 | 2 | Walker Brothers, Inc. | SCDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the SCDOT explorer.
How these prices were read
SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are SCDOT's own: this item is compared with SCDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the SCDOT letting of 13 OCT 2026 and was rebuilt on 26 NOV 2026.