SCDOT contract 2375800 bid tabulation
S-507 Brooks Ave Bridge Replacement in Greenville County. Let by South Carolina DOT on September 9, 2026, Greenville, District 3. 5 bids received; low bid $4,661,447 by Wright Brothers Construction Company,.
- Owner
- South Carolina DOT
- Letting
- 09 SEP 2026
- Pay items
- 100
- Data through
- 13 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Wright Brothers Construction Company, | $4,661,447 | Low |
| 2 | Dane Construction, LLC | $4,936,909 | +6.0% |
| 3 | United Infrastructure Group, Inc. | $5,068,558 | +9.0% |
| 4 | Eagle Construction Company | $5,406,849 | +16% |
| 5 | Rakes Building and Maintenance | $6,619,749 | +42% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Wright Brothers Construction Company, | 2. Dane Construction, LLC | 3. United Infrastructure Group, Inc. | 4. Eagle Construction Company | 5. Rakes Building and Maintenance |
|---|---|---|---|---|---|---|---|---|
| 0010 | Mobilization (1031000) | LS | 1 | $119,000 | $246,845 | $253,428 | $270,000 | $70,000 |
| 0020 | Mobilization - subcontractor (1031100) | LS | 1 | $230,000 | $246,845 | $253,428 | $270,000 | $30,000 |
| 0030 | Bridge construction access (1031200) | LS | 1 | $100,000 | $75,000 | $126,714 | $60,000 | $15,000 |
| 0040 | Bonds and insurance (1032010) | LS | 1 | $25,700 | $98,735 | $152,057 | $49,000 | $131,000 |
| 0050 | Construction stakes, lines & grades (1050800) | EACH | 1 | $64,000 | $25,000 | $50,000 | $57,500 | $40,000 |
| 0060 | Utility staking (1052001) | LS | 1 | $2,200.00 | $2,500.00 | $1.00 | $7,200.00 | $5,000.00 |
| 0070 | Installation of monitoring wells (1072420) | LF | 20 | $293.00 | $265.00 | $500.00 | $300.00 | $300.00 |
| 0080 | CPM progress schedule (1080300) | LS | 1 | $17,700 | $20,000 | $5,000.00 | $5,000.00 | $25,000 |
| 0090 | Clearing & grubbing within roadway (2012000) | LS | 1 | $351,600 | $91,465 | $50,000 | $225,500 | $25,000 |
| 0100 | Removal & disposal of contaminated soil (2021205) | TON | 990 | $110.00 | $200.00 | $450.00 | $300.00 | $200.00 |
| 0110 | Removal & disposal of contaminated liquids (2021250) | GAL | 1,080 | $29.65 | $10.00 | $295.00 | $15.00 | $8.00 |
| 0120 | Removal & disposal of existing pavement (2023000) | SY | 315 | $23.00 | $35.00 | $30.00 | $15.00 | $60.00 |
| 0130 | Removal & disposal of existing bridge (2028100) | LS | 1 | $200,000 | $80,000 | $55,000 | $190,000 | $220,000 |
| 0140 | Unclassified excavation (2031000) | CY | 664 | $52.80 | $80.00 | $40.00 | $50.00 | $45.00 |
| 0150 | Borrow excavation (2033000) | CY | 4,989 | $54.90 | $47.50 | $50.00 | $68.00 | $60.00 |
| 0160 | Fine grading (2081001) | SY | 2,987 | $5.90 | $5.00 | $20.00 | $4.00 | $6.00 |
| 0170 | Flowable fill (2103000) | CY | 5 | $590.00 | $400.00 | $340.00 | $700.00 | $550.00 |
| 0180 | Maintenance stone (3059900) | TON | 25 | $63.10 | $50.00 | $65.00 | $53.00 | $150.00 |
| 0190 | Liquid asphalt binder PG64-22 (4011004) | TON | 66 | $960.00 | $875.13 | $687.97 | $1,000.00 | $650.00 |
| 0200 | Milling existing asphalt pavement (variable) (4013990) | SY | 492 | $39.45 | $19.00 | $21.40 | $22.00 | $25.00 |
| 0210 | Asphalt base course - type B (4020320) | TON | 784 | $180.00 | $131.28 | $147.79 | $140.00 | $290.00 |
| 0220 | Asphalt intermediate course type C (4030330) | TON | 313 | $192.00 | $137.51 | $152.88 | $173.00 | $290.00 |
| 0230 | Asphalt surface course type C (4040340) | TON | 247 | $207.00 | $144.06 | $152.88 | $200.00 | $290.00 |
| 0240 | Traffic control (6011000) | LS | 1 | $50,000 | $5,000.00 | $76,557 | $46,000 | $30,000 |
| 0250 | Barricade - type III (6041200) | LF | 115 | $27.90 | $35.00 | $21.00 | $28.00 | $32.00 |
| 0260 | Permanent construction signs (ground mounted) (6051120) | SF | 172 | $8.20 | $7.10 | $7.40 | $12.00 | $7.00 |
| 0270 | Pavement markings(temp- paint) 4" white broken lines (609105A) | LF | 200 | $0.30 | $0.25 | $0.25 | $0.30 | $1.10 |
| 0280 | Pavement markings(temporary-paint)-4" yellow solid lines (609115B) | LF | 5,580 | $0.30 | $0.25 | $0.25 | $0.30 | $1.10 |
| 0290 | Pavement markings(temporary-paint)-8" white solid lines (609125A) | LF | 410 | $0.30 | $0.25 | $0.25 | $0.50 | $1.50 |
| 0300 | Pavement markings(temporary-paint)- 24"white solid lines (609135A) | LF | 340 | $1.10 | $1.00 | $1.00 | $1.25 | $3.60 |
| 0310 | Pavement markings(temporary-paint)- white single arrow (609160A) | EACH | 6 | $27.90 | $25.00 | $25.00 | $35.00 | $602.00 |
| 0320 | Pavement markings(temp.- paint)-white combination arrows (609165A) | EACH | 4 | $27.90 | $25.00 | $25.00 | $35.00 | $500.00 |
| 0330 | Pavement markings(temporary-paint)- white word 'only (609180A) | EACH | 4 | $27.90 | $25.00 | $25.00 | $35.00 | $475.00 |
| 0340 | 4" white broken lines -(gaps excluded) - epoxy paint fast cure (6262005) | LF | 40 | $5.60 | $5.00 | $5.00 | $6.00 | $7.50 |
| 0350 | White single arrows (left, straight, right) epoxy paint fast cure (6262030) | EACH | 2 | $560.00 | $500.00 | $500.00 | $600.00 | $900.00 |
| 0360 | White word message "only" - epoxy paint fast cure (6262035) | EACH | 1 | $560.00 | $500.00 | $500.00 | $600.00 | $700.00 |
| 0370 | White combination arrow (STR.&RT.or STR.<) epoxy paint fast cure (6262040) | EACH | 1 | $560.00 | $500.00 | $500.00 | $600.00 | $900.00 |
| 0380 | 4"yellow solid lines- PVT.edge&no passing zone - epoxy paint fast cure (6262110) | LF | 350 | $5.60 | $5.00 | $5.00 | $6.00 | $7.50 |
| 0390 | 4" white broken lines(gaps excl.)thermoplastic- 90 mil. (6271005) | LF | 60 | $2.25 | $4.00 | $2.00 | $2.50 | $4.75 |
| 0400 | 8" white solid lines thermoplastic - 125 mil. (6271015) | LF | 205 | $3.35 | $3.00 | $3.00 | $3.60 | $10.00 |
| 0410 | 24" white solid lines (stop/diag lines)-thermo.-125 mil (6271025) | LF | 170 | $10.05 | $9.00 | $9.00 | $11.00 | $15.00 |
| 0420 | White single arrows (LT, STRGHT, RT) thermo.-125 mil. (6271030) | EACH | 1 | $167.00 | $150.00 | $150.00 | $200.00 | $210.00 |
| 0430 | White word message "only" - thermoplastic - 125 mil. (6271035) | EACH | 1 | $167.00 | $150.00 | $150.00 | $200.00 | $265.00 |
| 0440 | White combination arrows(STR&RT.or STR& LT)thermo-125MIL (6271040) | EACH | 1 | $167.00 | $150.00 | $150.00 | $200.00 | $296.00 |
| 0450 | 4" yellow solid lines(PVT.edge lines) thermo- 90 mil. (6271074) | LF | 2,440 | $2.25 | $2.00 | $2.00 | $2.50 | $4.75 |
| 0460 | Permanent clear pavement markers- mono-dir.- 4"X4" (6300005) | EACH | 4 | $11.15 | $10.00 | $10.00 | $12.50 | $236.00 |
| 0470 | Permanent yellow pavement markers BI-dir.- 4"X4" (6301100) | EACH | 20 | $11.15 | $10.00 | $10.00 | $12.50 | $65.00 |
| 0480 | Flat sheet, type III, fixed SZ. & MSG. sign (6510105) | SF | 6.25 | $33.45 | $25.00 | $33.00 | $60.00 | $36.00 |
| 0490 | U-section post for sign supports - 3P (6531210) | LF | 13 | $13.40 | $15.00 | $18.00 | $25.00 | $15.00 |
| 0500 | Furnish & install 2.0" schedule 80 PVC conduit (6750278) | LF | 1,050 | $11.20 | $20.00 | $10.00 | $40.00 | $20.00 |
| 0510 | Conc. for structures - class 4000 (7011400) | CY | 704.80 | $1,300.00 | $1,500.00 | $1,400.00 | $1,300.00 | $2,800.00 |
| 0520 | Grooved surface finish (7023200) | SY | 557 | $13.00 | $12.50 | $7.00 | $30.00 | $26.00 |
| 0530 | Reinf. steel for structures (bridge) (7031200) | LB | 173,649 | $1.45 | $2.35 | $1.25 | $3.00 | $2.90 |
| 0540 | Hoop reinforcing steel for structures (bridge) (7031220) | LB | 4,153 | $2.85 | $6.75 | $2.50 | $4.00 | $5.50 |
| 0550 | Prestressed concrete florida I-beam(36") (7045436) | LF | 923.40 | $409.00 | $620.00 | $365.00 | $550.00 | $1,200.00 |
| 0560 | 42" MASH concrete barrier parapet/railing wall (7051050) | LF | 348 | $128.00 | $130.00 | $115.00 | $165.00 | $315.00 |
| 0570 | Pile driving set-UP (7110010) | EACH | 14 | $1,700.00 | $3,750.00 | $3,600.00 | $6,000.00 | $1,200.00 |
| 0580 | Reinf. pile tips (HP14 X 117) (7111575) | EACH | 14 | $230.00 | $550.00 | $165.00 | $450.00 | $350.00 |
| 0590 | Steel H bearing piling (HP14 X 117) (7112250) | LF | 490 | $328.00 | $130.00 | $108.00 | $140.00 | $320.00 |
| 0600 | Drilled shaft set-UP (7120006) | EACH | 4 | $1,100.00 | $12,100 | $19,000 | $40,000 | $25,000 |
| 0610 | Crosshole sonic logging setup (7120010) | EACH | 4 | $3,800.00 | $2,500.00 | $2,500.00 | $6,500.00 | $5,000.00 |
| 0620 | Drilled shaft with wet & dry excavation - 42" diameter (7120151) | LF | 16 | $1,400.00 | $1,575.00 | $669.11 | $750.00 | $600.00 |
| 0630 | Drilled shaft with rock excavation - 42" diameter (7120152) | LF | 20 | $1,400.00 | $5,200.00 | $3,700.98 | $3,000.00 | $2,000.00 |
| 0640 | Drilled shaft with wet & dry excavation - 48" diameter (7120161) | LF | 102.30 | $1,400.00 | $1,970.00 | $589.65 | $500.00 | $650.00 |
| 0650 | Construction casing - 48" diameter (7120165) | LF | 102.30 | $510.00 | $500.00 | $450.00 | $700.00 | $750.00 |
| 0660 | 18" smooth wall pipe (7143618) | LF | 828 | $120.00 | $154.00 | $155.00 | $80.00 | $115.00 |
| 0670 | Catch basin -type 16 (7191605) | EACH | 9 | $9,900.00 | $7,500.00 | $12,000 | $7,800.00 | $8,400.00 |
| 0680 | Beveling of pipe end (7199100) | EACH | 2 | $820.00 | $750.00 | $1,500.00 | $900.00 | $2,600.00 |
| 0690 | Concrete curb and gutter(2'-0") vertical face (7203210) | LF | 1,519 | $37.75 | $40.20 | $39.00 | $41.00 | $54.00 |
| 0700 | Concrete sidewalk(4" uniform) (7204100) | SY | 922 | $92.45 | $77.00 | $98.00 | $99.00 | $110.00 |
| 0710 | Detectable warning material (7204900) | SF | 100 | $55.75 | $26.00 | $164.16 | $180.00 | $40.00 |
| 0720 | Concrete flume (7207001) | LF | 37 | $390.00 | $350.00 | $191.52 | $500.00 | $90.00 |
| 0730 | Pedestrian ramp construction (7209000) | SY | 80 | $170.00 | $310.00 | $317.38 | $400.00 | $120.00 |
| 0740 | Elastomeric bearing (7243100) | EACH | 28 | $2,500.00 | $525.00 | $1,462.72 | $1,400.00 | $1,200.00 |
| 0750 | Waterproofing (7282000) | SY | 43.60 | $57.05 | $85.00 | $160.00 | $180.00 | $500.00 |
| 0760 | Aggregate underdrain(agg#789)with 4"perf.pipe for struc (8011210) | TON | 252 | $81.80 | $85.00 | $80.00 | $100.00 | $200.00 |
| 0770 | Rip-rap (class B) (8041020) | TON | 335 | $106.00 | $110.00 | $110.00 | $85.50 | $192.00 |
| 0780 | Geotextile for erosion control under riprap(class 2)type C (8048210) | SY | 669 | $4.75 | $5.00 | $9.00 | $6.00 | $9.00 |
| 0790 | Non-mow strip under guardrail (8055250) | SY | 56 | $158.00 | $250.00 | $218.88 | $300.00 | $110.00 |
| 0800 | Premash short triebeam bridge con TBBC2 (8056900) | EACH | 4 | $1,800.00 | $2,460.00 | $1,600.00 | $3,100.00 | $2,880.00 |
| 0810 | Premash type T TL2 leading 25FT (8057050) | EACH | 4 | $3,200.00 | $1,575.49 | $2,850.00 | $2,000.00 | $12,000 |
| 0820 | Moving item no. moving item 1 - wire fence (8081000) | LS | 1 | $12,700 | $15,000 | $13,500 | $18,500 | $5,000.00 |
| 0830 | Right of way marker(rebar and cap) (8091010) | EACH | 17 | $200.00 | $135.00 | $200.00 | $300.00 | $120.00 |
| 0840 | Right of way plat (8091050) | LS | 1 | $1,100.00 | $1,800.00 | $7,500.00 | $4,500.00 | $5,000.00 |
| 0850 | Permanent cover (8100100) | ACRE | 0.62 | $2,100.00 | $2,000.00 | $2,000.00 | $2,650.00 | $7,000.00 |
| 0860 | Temporary cover (8100200) | ACRE | 0.31 | $1,400.00 | $1,400.00 | $1,400.00 | $4,800.00 | $6,500.00 |
| 0870 | Fertilizer (nitrogen) (8104005) | LB | 62 | $2.50 | $5.00 | $5.00 | $4.75 | $7.50 |
| 0880 | Fertilizer (phosphoric acid) (8104010) | LB | 62 | $2.50 | $5.00 | $5.00 | $4.75 | $7.50 |
| 0890 | Fertilizer (potash) (8104015) | LB | 62 | $2.50 | $5.00 | $5.00 | $4.75 | $10.00 |
| 0900 | Agricultural granular lime (8105005) | LB | 1,240 | $0.80 | $0.09 | $0.09 | $1.25 | $6.00 |
| 0910 | Selective watering (8109050) | GAL | 54,300 | $0.15 | $0.12 | $0.12 | $0.11 | $0.60 |
| 0920 | Mowing (8109901) | ACRE | 1.86 | $329.00 | $300.00 | $300.00 | $1,150.00 | $800.00 |
| 0930 | Temporary erosion control blanket (ecb) (8151110) | MSY | 0.94 | $1,600.00 | $1,692.80 | $1,700.00 | $2,850.00 | $3,000.00 |
| 0940 | Inlet structure filter - type F (weighted) (8152004) | LF | 90 | $19.90 | $35.00 | $12.00 | $18.00 | $22.00 |
| 0950 | Silt fence (8153000) | LF | 1,295 | $2.85 | $3.50 | $3.50 | $4.50 | $7.00 |
| 0960 | Replace/repair silt fence (8153090) | LF | 129.50 | $1.00 | $3.50 | $3.50 | $7.00 | $7.00 |
| 0970 | Removal of silt retained by silt fence (8154050) | LF | 323.75 | $6.70 | $6.00 | $10.00 | $7.00 | $4.00 |
| 0980 | Cleaning inlet structure filters (8156200) | EACH | 27 | $92.55 | $250.00 | $700.00 | $250.00 | $200.00 |
| 0990 | Aggregate no.5 or 57 for erosion control (8156410) | TON | 5 | $152.00 | $75.00 | $100.00 | $91.50 | $153.00 |
| 1000 | Stabilized construction entrance (8156490) | SY | 550 | $31.50 | $25.00 | $30.00 | $32.50 | $10.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from SCDOT's tabulation for this contract. SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.
Every contract let that day: SCDOT letting of September 9, 2026. Compiled by Mirage Metrics.