Temporary cover, SCDOT 8100200
Low bidders on SCDOT contracts carried a median of $1,355.25 per ACRE for this item, over the 24 months to 13 OCT 2026, across 98 low bids. Half of all 437 bids fell between $1,189.00 and $1,955.00.
- Owner
- South Carolina DOT
- Item
- 8100200
- Unit
- ACRE
- Data through
- 13 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2022 | 31 | 31 | $1,300.00 | 102 | $1,250.25 |
| 2023 | 30 | 30 | $1,475.00 | 84 | $1,521.87 |
| 2024 | 45 | 45 | $1,550.00 | 150 | $1,625.00 |
| 2025 | 55 | 55 | $1,394.31 | 231 | $1,450.00 |
| 2026 | 34 | 34 | $1,400.00 | 176 | $1,400.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| District 4 | 17 | $1,475.52 | 107 | $1,500.00 |
| District 7 | 12 | $1,400.00 | 72 | $1,402.53 |
| District 5 | 20 | $1,237.50 | 58 | $1,310.00 |
| District 3 | 13 | $1,400.00 | 56 | $1,450.00 |
| District 1 | 11 | $1,300.00 | 51 | $1,550.00 |
| District 6 | 15 | $1,315.03 | 46 | $1,318.76 |
| District 2 | 8 | $1,300.00 | 37 | $1,300.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (ACRE) | Low bids | Low-bid median |
|---|---|---|
| 0.05 to 0.62 | 24 | $2,800.00 |
| 0.67 to 1.45 | 25 | $1,475.52 |
| 1.51 to 4.24 | 24 | $1,194.50 |
| 4.40 to 70.76 | 25 | $1,300.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Palmetto Corp. of Conway | 41 | 26 (63%) |
| Dane Construction, LLC | 56 | 23 (41%) |
| Reeves Construction Company | 45 | 9 (20%) |
| United Infrastructure Group, Inc. | 30 | 9 (30%) |
| S and S Construction, Inc. of Anderson | 12 | 9 (75%) |
| Palmetto Sitework Services, LLC | 24 | 7 (29%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 13 OCT 2026 | 1075380 | District 6 | 0.35 | $2,600.00 | $3,350.00 | 7 | Ben Cox, LLC | SCDOT |
| 13 OCT 2026 | 2378290 | District 3 | 0.25 | $3,838.00 | $4,069.00 | 8 | Reeves Construction Company | SCDOT |
| 13 OCT 2026 | 2973031 | District 4 | 1.45 | $1,100.00 | $1,707.00 | 9 | Truerock Construction, LLC | SCDOT |
| 13 OCT 2026 | 4673600 | District 4 | 0.33 | $3,200.00 | $3,195.16 | 8 | Kemp Sigmon Construction Co., Inc. | SCDOT |
| 09 SEP 2026 | 0772100 | District 6 | 2.60 | $1,700.00 | $1,500.00 | 3 | Apac-Atlantic Inc. | SCDOT |
| 09 SEP 2026 | 0965790 | District 7 | 8.50 | $1,370.00 | $1,390.88 | 8 | Palmetto Sitework Services, LLC | SCDOT |
| 09 SEP 2026 | 2069920 | District 4 | 3.62 | $1,189.00 | $1,189.00 | 9 | Kemp Sigmon Construction Co., Inc. | SCDOT |
| 09 SEP 2026 | 2375800 | District 3 | 0.31 | $1,400.00 | $1,400.00 | 5 | Wright Brothers Construction Company, | SCDOT |
| 09 SEP 2026 | 4672780 | District 4 | 5.05 | $1,490.00 | $1,490.00 | 3 | Aos Specialty Contractors, Inc. | SCDOT |
| 11 AUG 2026 | 1871410 | District 6 | 3.25 | $1,200.00 | $1,200.00 | 4 | United Infrastructure Group, Inc. | SCDOT |
| 11 AUG 2026 | 2970980 | District 4 | 2.72 | $1,110.00 | $1,300.00 | 7 | United Infrastructure Group, Inc. | SCDOT |
| 11 AUG 2026 | 3873080 | District 7 | 1.07 | $1,400.00 | $1,500.00 | 7 | Dane Construction, LLC | SCDOT |
| 11 AUG 2026 | 4275670 | District 3 | 0.62 | $2,500.00 | $2,111.11 | 10 | United Infrastructure Group, Inc. | SCDOT |
| 09 JUN 2026 | 2163100 | District 5 | 1.20 | $1,500.00 | $1,500.00 | 5 | Cherokee, Inc. | SCDOT |
| 12 MAY 2026 | 0876380 | District 6 | 4 | $1,500.00 | $1,400.00 | 5 | Green Wave Contracting, Inc. | SCDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the SCDOT explorer.
How these prices were read
SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are SCDOT's own: this item is compared with SCDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the SCDOT letting of 13 OCT 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.