SCDOT contract 2069920 bid tabulation
Three Bridge Replacements in Fairfield County. Let by South Carolina DOT on September 9, 2026, Fairfield, District 4. 9 bids received; low bid $7,464,407 by Kemp Sigmon Construction Co., Inc..
- Owner
- South Carolina DOT
- Letting
- 09 SEP 2026
- Pay items
- 115
- Data through
- 13 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Kemp Sigmon Construction Co., Inc. | $7,464,407 | Low |
| 2 | Republic Contracting Corporation | $7,700,133 | +3.0% |
| 3 | Palmetto Infrastructure, Inc. | $8,149,264 | +9.0% |
| 4 | United Infrastructure Group, Inc. | $8,228,079 | +10% |
| 5 | Dane Construction, LLC | $8,390,344 | +12% |
| 6 | Aos Specialty Contractors, Inc. | $9,342,556 | +25% |
| 7 | Coogler Construction, Inc. | $9,433,247 | +26% |
| 8 | Eagle Construction Company | $9,513,265 | +27% |
| 9 | Cekra, Inc. | $10,885,318 | +46% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Kemp Sigmon Construction Co., Inc. | 2. Republic Contracting Corporation | 3. Palmetto Infrastructure, Inc. | 4. United Infrastructure Group, Inc. | 5. Dane Construction, LLC | 6. Aos Specialty Contractors, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Mobilization (1031000) | LS | 1 | $372,000 | $250,000 | $400,000 | $411,404 | $419,515 | $912,187 |
| 0020 | Bridge construction access (1031200) | LS | 1 | $100,000 | $70,000 | $90,000 | $164,562 | $419,515 | $84,555 |
| 0030 | Bonds and insurance (1032010) | LS | 1 | $149,000 | $77,000 | $150,000 | $246,842 | $167,805 | $86,922 |
| 0040 | Construction stakes, lines & grades (1050800) | EACH | 3 | $40,000 | $115,000 | $35,000 | $30,000 | $67,500 | $40,539 |
| 0050 | Small public water relocation no. ____ 01 (1052100) | EACH | 1 | $85,480 | $92,910 | $49,892 | $85,480 | $49,892 | $104,244 |
| 0060 | CPM progress schedule (1080300) | LS | 1 | $30,000 | $20,000 | $15,750 | $3,000.00 | $30,000 | $59,072 |
| 0070 | Clearing & grubbing within right of way (2011000) | LS | 1 | $800,000 | $255,000 | $560,000 | $325,870 | $75,000 | $70,696 |
| 0080 | Removal & disposal item no. 01 (2022000) | LS | 1 | $1,000.00 | $5,000.00 | $500.00 | $0.01 | $2,500.00 | $4,054.00 |
| 0090 | Removal & disposal item no. 02 (2022000) | LS | 1 | $1,500.00 | $5,000.00 | $1,000.00 | $0.01 | $2,500.00 | $8,687.00 |
| 0100 | Removal & disposal of existing asphalt pavement (2025000) | SY | 1,678 | $12.00 | $15.00 | $10.00 | $30.00 | $10.00 | $11.60 |
| 0110 | Removal & disposal of existing bridge (2028100) | LS | 1 | $775,000 | $230,000 | $455,000 | $350,000 | $300,520 | $407,542 |
| 0120 | Unclassified excavation (2031000) | CY | 4,071 | $25.00 | $14.50 | $28.00 | $12.81 | $12.50 | $17.40 |
| 0130 | Borrow excavation (2033000) | CY | 11,320 | $15.00 | $30.50 | $33.00 | $29.20 | $28.50 | $34.75 |
| 0140 | Wet & dry excavation for bridges (2043500) | CY | 160 | $100.00 | $70.00 | $35.00 | $80.00 | $30.00 | $107.50 |
| 0150 | Rock excavation for bridges (2044000) | CY | 18 | $750.00 | $160.00 | $500.00 | $200.00 | $1,024.55 | $1,034.50 |
| 0160 | Fine grading (2081001) | SY | 7,300 | $10.00 | $11.00 | $10.00 | $10.25 | $10.00 | $11.60 |
| 0170 | Flowable fill (2103000) | CY | 15 | $250.00 | $330.00 | $350.00 | $307.40 | $300.00 | $504.00 |
| 0180 | Graded aggregate base course (6" uniform) (3050106) | SY | 130 | $50.00 | $27.50 | $25.00 | $26.13 | $25.00 | $30.00 |
| 0190 | Maintenance stone (3059900) | TON | 67 | $60.00 | $80.50 | $75.00 | $80.44 | $78.50 | $135.75 |
| 0200 | Liquid asphalt binder PG64-22 (4011004) | TON | 153.40 | $830.00 | $830.00 | $834.25 | $838.30 | $830.00 | $966.00 |
| 0210 | Milling existing asphalt pavement (variable) (4013990) | SY | 603 | $14.00 | $14.00 | $20.55 | $14.14 | $14.00 | $23.80 |
| 0220 | Asphalt base course - type B (4020320) | TON | 2,069 | $115.00 | $115.00 | $115.00 | $116.15 | $115.00 | $133.20 |
| 0230 | Asphalt intermediate course type C (4030330) | TON | 374 | $100.00 | $100.00 | $150.00 | $101.00 | $100.00 | $173.75 |
| 0240 | Asphalt surface course type C (4040340) | TON | 619 | $100.00 | $100.00 | $150.00 | $101.00 | $100.00 | $173.75 |
| 0250 | Asphalt surface course type E (4040360) | TON | 20 | $100.00 | $200.00 | $310.00 | $202.00 | $200.00 | $359.00 |
| 0260 | Driveway paving-surface type C (4047220) | TON | 22 | $200.00 | $200.00 | $425.00 | $202.00 | $200.00 | $492.25 |
| 0270 | Traffic control (6011000) | LS | 1 | $50,000 | $100,000 | $11,800 | $150,000 | $10,500 | $130,861 |
| 0280 | Barricade - type III (6041200) | LF | 168 | $21.00 | $40.00 | $13.00 | $21.00 | $35.00 | $24.30 |
| 0290 | Permanent construction signs (ground mounted) (6051120) | SF | 384 | $7.40 | $10.25 | $6.90 | $7.40 | $7.25 | $8.70 |
| 0300 | Permanent construction signs (barricade mounted) (6051125) | SF | 274 | $7.40 | $11.25 | $6.50 | $7.40 | $7.25 | $8.70 |
| 0310 | Construction zone electric changeable message sign (trailer (6062000) | EACH | 2 | $12,000 | $60,000 | $1,500.00 | $15,000 | $5,000.00 | $15,636 |
| 0320 | Type B - flashing light (608100B) | EACH | 32 | $125.00 | $170.00 | $115.00 | $125.00 | $182.80 | $144.75 |
| 0330 | 4" white solid lines (PVT. edge lines) epoxy paint fast cure (6262010) | LF | 1,670 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 | $5.80 |
| 0340 | 4" yellow broken lines(gaps exc) epoxy paint fast cure (6262105) | LF | 700 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 | $5.80 |
| 0350 | 4"yellow solid lines- PVT.edge&no passing zone - epoxy paint fast cure (6262110) | LF | 970 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 | $5.80 |
| 0360 | 4" white solid lines (PVT. edge lines) thermo.- 90 mil. (6271010) | LF | 3,720 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.15 |
| 0370 | 4" yellow solid lines(PVT.edge lines) thermo- 90 mil. (6271074) | LF | 3,720 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.15 |
| 0380 | Permanent yellow pavement markers BI-dir.- 4"X4" (6301100) | EACH | 48 | $10.00 | $10.00 | $10.00 | $10.00 | $10.00 | $11.60 |
| 0390 | Milled-in rumble strip (6321000) | MI | 0.82 | $10,000 | $18,000 | $12,000 | $4,500.00 | $4,494.52 | $8,687.00 |
| 0400 | Pref.flex.retro.PVMT.mark(T- 1)perm.(60MIL)4"WH.solid (6351150) | LF | 280 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 | $5.80 |
| 0410 | Pref.flex.retro.PVMT.mark(T- 1)perm.(60MIL)4"yel.sol. (6351450) | LF | 280 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 | $5.80 |
| 0420 | Flat sheet, type III, fixed SZ. & MSG. sign (6510105) | SF | 12 | $33.00 | $30.00 | $46.00 | $35.00 | $25.00 | $38.25 |
| 0430 | U-section post for sign supports - 3P (6531210) | LF | 44 | $18.00 | $20.00 | $33.30 | $20.00 | $15.00 | $20.85 |
| 0440 | Furnish & install 2.0" schedule 80 PVC conduit (6750278) | LF | 1,972 | $17.00 | $60.00 | $20.00 | $9.00 | $13.25 | $24.60 |
| 0450 | Conc. for structures - class 4000 (7011400) | CY | 678.40 | $900.00 | $1,500.00 | $2,050.00 | $2,650.00 | $1,650.00 | $1,880.25 |
| 0460 | Conc. for structures - class 4000DS (7011510) | CY | 7 | $2,500.00 | $1,400.00 | $2,000.00 | $1,000.00 | $1,350.00 | $3,629.50 |
| 0470 | Grooved surface finish (7023200) | SY | 389 | $20.00 | $17.00 | $120.00 | $25.00 | $20.60 | $6.95 |
| 0480 | Reinf. steel for structures (bridge) (7031200) | LB | 185,697 | $1.50 | $1.45 | $1.75 | $1.50 | $1.75 | $2.92 |
| 0490 | 3'-0" X 3'-3" box beam (7046220) | LF | 1,298.40 | $350.00 | $520.00 | $375.00 | $400.00 | $575.00 | $454.00 |
| 0500 | 42" MASH concrete barrier parapet/railing wall (7051050) | LF | 980 | $110.00 | $157.00 | $120.00 | $100.00 | $125.00 | $127.40 |
| 0510 | Structural steel (7091100) | LS | 1 | $1,500,000 | $1,440,000 | $1,400,000 | $1,300,000 | $1,920,000 | $1,600,500 |
| 0520 | Pile driving set-UP (7110010) | EACH | 28 | $1,500.00 | $1,900.00 | $4,000.00 | $3,500.00 | $2,700.00 | $7,593.00 |
| 0530 | Reinf. pile tips (HP14 X 89) (7111565) | EACH | 14 | $200.00 | $245.00 | $200.00 | $214.00 | $575.00 | $543.00 |
| 0540 | Steel H bearing piling (HP14 X 73) (7112220) | LF | 749 | $80.00 | $112.00 | $75.00 | $63.00 | $80.00 | $108.85 |
| 0550 | Steel H bearing piling (HP14 X 89) (7112230) | LF | 518 | $100.00 | $123.00 | $75.00 | $79.00 | $95.00 | $83.30 |
| 0560 | 18" RC pipe cul.-class III (7141113) | LF | 180 | $110.00 | $100.50 | $115.00 | $100.93 | $98.50 | $115.85 |
| 0570 | 15" smooth wall pipe (7143615) | LF | 56 | $110.00 | $96.50 | $100.00 | $94.78 | $92.50 | $110.05 |
| 0580 | 18" smooth wall pipe (7143618) | LF | 112 | $110.00 | $99.50 | $115.00 | $96.83 | $94.50 | $110.05 |
| 0590 | Drilled pile set-UP (7160008) | EACH | 7 | $2,000.00 | $5,500.00 | $5,500.00 | $10,000 | $6,000.00 | $8,439.00 |
| 0600 | Soil excavation for drilled pile foundations - 30" diameter (7160023) | LF | 119 | $150.00 | $195.00 | $450.00 | $181.00 | $830.00 | $318.50 |
| 0610 | Rock excavation for drilled pile foundations - 30" diameter (7160063) | LF | 35 | $825.00 | $1,650.00 | $1,000.00 | $1,545.00 | $2,350.00 | $955.60 |
| 0620 | Construction casing - 30" diameter (7160405) | LF | 119 | $150.00 | $275.00 | $250.00 | $0.01 | $275.00 | $238.30 |
| 0630 | Catch basin -type 16 (7191605) | EACH | 1 | $5,000.00 | $9,500.00 | $10,000 | $8,043.52 | $7,850.00 | $15,913 |
| 0640 | Manhole (7192105) | EACH | 1 | $5,000.00 | $7,900.00 | $7,000.00 | $5,994.22 | $5,850.00 | $7,529.00 |
| 0650 | Beveling of pipe end (7199100) | EACH | 6 | $1,500.00 | $275.00 | $400.00 | $281.78 | $275.00 | $764.90 |
| 0660 | 4' slope flume (6" curb style with cutoffs) (7199200) | LF | 143.20 | $260.00 | $285.00 | $450.00 | $225.00 | $350.00 | $265.75 |
| 0670 | Concrete curb and gutter(2'-0") vertical face (7203210) | LF | 198 | $52.00 | $52.00 | $80.00 | $38.50 | $125.00 | $91.45 |
| 0680 | Elastomeric bearing (7243100) | EACH | 42 | $350.00 | $800.00 | $400.00 | $1,000.00 | $425.00 | $1,271.05 |
| 0690 | Elastomeric bearing assembly (flat slab) (7243150) | EACH | 1 | $2,000.00 | $1,000.00 | $2,000.00 | $0.01 | $3,250.00 | $4,088.00 |
| 0700 | Waterproofing (7282000) | SY | 82 | $60.00 | $220.00 | $75.00 | $100.00 | $90.00 | $119.90 |
| 0710 | Liquid membrane waterproofing (bridge deck) (7283100) | SY | 409.30 | $25.00 | $200.00 | $65.00 | $200.00 | $125.00 | $93.35 |
| 0720 | Aggregate underdrain(agg#789)with 4"perf.pipe for struc (8011210) | TON | 196 | $100.00 | $81.50 | $125.00 | $150.00 | $110.00 | $137.30 |
| 0730 | Rip-rap (class A) (8041010) | TON | 72.80 | $85.00 | $120.00 | $100.00 | $117.83 | $115.00 | $146.40 |
| 0740 | Rip-rap (class B) (8041020) | TON | 962 | $85.00 | $119.00 | $100.00 | $117.83 | $115.00 | $133.20 |
| 0750 | Rip-rap (class C) (8041030) | TON | 425 | $85.00 | $145.00 | $100.00 | $143.45 | $140.00 | $162.00 |
| 0760 | Geotextile for erosion control under riprap(class 1)type C (8048110) | SY | 450 | $2.50 | $8.50 | $8.00 | $7.68 | $7.50 | $2.05 |
| 0770 | Geotextile for erosion control under riprap(class 2)type B (8048205) | SY | 743 | $2.50 | $8.00 | $8.00 | $7.68 | $7.50 | $8.35 |
| 0780 | Geotextile for erosion control under riprap(class 2)type C (8048210) | SY | 851 | $2.50 | $9.50 | $8.00 | $7.68 | $7.50 | $8.35 |
| 0790 | MT3 leading end treatment TL3 (8051151) | EACH | 7 | $3,000.00 | $3,000.00 | $3,100.00 | $3,000.00 | $3,000.00 | $4,343.50 |
| 0800 | MT2 leading end treatment TL2 (8051155) | EACH | 3 | $2,850.00 | $2,770.00 | $2,900.00 | $2,850.00 | $2,850.00 | $4,054.00 |
| 0810 | MB trailing end treatment (8051710) | EACH | 2 | $1,600.00 | $1,850.00 | $2,000.00 | $1,600.00 | $1,600.00 | $1,795.35 |
| 0820 | MGS3 GR standard shoulder (8052100) | LF | 1,787.50 | $25.00 | $26.00 | $25.60 | $25.00 | $25.00 | $30.15 |
| 0830 | MTBBC3 MASH thrie-beam barrier connector TL3 (8053253) | EACH | 7 | $2,650.00 | $3,018.56 | $3,200.00 | $2,650.00 | $2,650.00 | $2,954.00 |
| 0840 | MTBBC2 MASH thrie-beam barrier connector TL2 (8053255) | EACH | 5 | $1,450.00 | $1,600.00 | $2,000.00 | $1,450.00 | $1,450.00 | $2,635.00 |
| 0850 | Flume inlet at guardrail (handwork) (8053257) | EACH | 4 | $4,000.00 | $4,000.00 | $4,000.00 | $4,500.00 | $3,000.00 | $5,403.00 |
| 0860 | Non-mow strip under guardrail (8055250) | SY | 1,779 | $38.00 | $38.00 | $60.00 | $38.38 | $38.00 | $120.15 |
| 0870 | Temporary barrier fence (orange) (8068301) | LF | 1,500 | $2.89 | $3.50 | $2.89 | $3.89 | $3.00 | $2.35 |
| 0880 | Right of way marker(rebar and cap) (8091010) | EACH | 39 | $350.00 | $200.00 | $300.00 | $150.00 | $150.00 | $231.65 |
| 0890 | Right of way plat (8091050) | LS | 1 | $5,000.00 | $9,000.00 | $12,000 | $5,500.00 | $7,500.00 | $29,536 |
| 0900 | Permanent cover (8100100) | ACRE | 4.25 | $1,850.00 | $1,400.00 | $1,850.00 | $1,850.00 | $1,700.00 | $1,911.00 |
| 0910 | Temporary cover (8100200) | ACRE | 3.62 | $1,189.00 | $1,225.00 | $1,189.00 | $1,189.00 | $1,000.00 | $1,506.00 |
| 0920 | Compost (8101105) | CY | 848 | $5.00 | $38.00 | $5.00 | $5.00 | $15.00 | $57.95 |
| 0930 | Fertilizer (nitrogen) (8104005) | LB | 425 | $1.95 | $4.00 | $1.95 | $1.95 | $5.00 | $2.90 |
| 0940 | Fertilizer (phosphoric acid) (8104010) | LB | 425 | $1.95 | $4.00 | $1.95 | $1.95 | $5.00 | $2.90 |
| 0950 | Fertilizer (potash) (8104015) | LB | 425 | $1.95 | $4.00 | $1.95 | $1.95 | $5.00 | $2.90 |
| 0960 | Agricultural granular lime (8105005) | LB | 8,500 | $1.00 | $0.40 | $1.00 | $1.00 | $0.09 | $0.40 |
| 0970 | Selective watering (8109050) | GAL | 162,900 | $0.05 | $0.09 | $0.05 | $0.05 | $0.12 | $0.12 |
| 0980 | Mowing (8109901) | ACRE | 15.73 | $500.00 | $525.00 | $500.00 | $500.00 | $300.00 | $868.00 |
| 0990 | Enhanced stacked ditch checks (8151050) | LF | 12 | $50.00 | $42.50 | $155.00 | $50.00 | $50.00 | $98.50 |
| 1000 | Turf reinforcement matting (TRM) type 1 (8151101) | MSY | 1.00 | $3,656.57 | $3,500.00 | $3,656.57 | $3,657.00 | $4,000.00 | $5,154.00 |
| 1010 | Turf reinforcement matting (TRM) type 2 (8151102) | MSY | 0.63 | $4,250.00 | $3,800.00 | $4,250.00 | $4,250.00 | $4,000.00 | $6,081.00 |
| 1020 | Temporary erosion control blanket (ecb) (8151110) | MSY | 9.39 | $2,132.00 | $1,700.00 | $2,132.00 | $2,132.00 | $1,650.00 | $2,142.00 |
| 1030 | Temporary erosion control blanket (ecb) (8151150) | SY | 21,213 | $2.13 | $1.70 | $2.13 | $2.13 | $1.65 | $2.32 |
| 1040 | Hydraulic erosion control product (hecp) - type 3 (8151203) | ACRE | 12.73 | $2,405.00 | $2,900.00 | $2,405.00 | $2,405.00 | $3,800.00 | $4,112.00 |
| 1050 | Inlet structure filter- type F (non-weighted) (8152006) | LF | 1,575 | $11.25 | $17.00 | $15.00 | $11.25 | $15.00 | $14.50 |
| 1060 | Sediment tubes for ditch checks (8152007) | LF | 1,060 | $11.25 | $17.00 | $12.00 | $11.25 | $15.00 | $13.35 |
| 1070 | Silt fence (8153000) | LF | 8,734 | $3.45 | $3.25 | $4.45 | $4.45 | $3.00 | $3.20 |
| 1080 | Replace/repair silt fence (8153090) | LF | 675 | $4.43 | $4.75 | $4.43 | $4.43 | $3.00 | $3.20 |
| 1090 | Cleaning silt basins (8154010) | CY | 58 | $125.00 | $60.00 | $20.00 | $30.36 | $30.00 | $47.80 |
| 1100 | Removal of silt retained by silt fence (8154050) | LF | 1,689 | $3.00 | $7.00 | $1.90 | $1.90 | $20.00 | $13.90 |
| 1110 | Inlet filter cleaning (8154155) | EACH | 53 | $250.00 | $110.00 | $100.00 | $96.71 | $100.00 | $260.60 |
| 1120 | Inlet structure filter - type B (8156210) | EACH | 4 | $350.00 | $575.00 | $400.00 | $229.00 | $125.00 | $521.25 |
| 1130 | Aggregate no.5 or 57 for erosion control (8156410) | TON | 27.10 | $200.00 | $80.00 | $75.00 | $89.28 | $150.00 | $78.90 |
| 1140 | Stabilized construction entrance (8156490) | SY | 1,650 | $20.00 | $30.50 | $22.00 | $29.20 | $28.50 | $34.75 |
| 1150 | Temporary flexible pipe slope drain - 12" (8157012) | LF | 150 | $30.00 | $50.00 | $45.00 | $23.12 | $30.00 | $47.30 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from SCDOT's tabulation for this contract. SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.
Every contract let that day: SCDOT letting of September 9, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.