Republic Contracting Corporation: SCDOT bid record

Republic Contracting Corporation submitted 15 bids on South Carolina DOT contracts in the data, from 12 APR 2022 to 09 SEP 2026, and was the low bidder on 1 of them (7%). When it was not low, its total sat a median +19% above the low bid.

Owner
South Carolina DOT
Low bid volume
$3,285,672
Latest bid
09 SEP 2026
Data through
13 OCT 2026
15Bids
1Low bids
7Win rate, percent
+19%Median gap to the low bid when not low, 14 bids

By year

YearBidsLow bidsWin rate
20225120%
2023100%
2024200%
2025400%
2026300%
Republic Contracting Corporation, SCDOT: bids and low bids by year of letting

By district

DistrictBidsLow bidsWin rate
District 78113%
District 4300%
District 5200%
District 1100%
Republic Contracting Corporation, SCDOT: bids and low bids by district

Pay items where it is most often lowest

Pay itemCodeUnitLines bidLowest on the lineIts median priceAll bidders' median
Pile driving set-UP7110010EACH138 (62%)$1,700.00$3,598.22
Permanent cover8100100ACRE115 (45%)$2,000.00$1,950.00
Flowable fill2103000CY85 (63%)$295.00$392.00
Type B - flashing light608100BEACH134 (31%)$160.00$125.00
Permanent yellow pavement markers BI-dir.- 4"X4"6301100EACH114 (36%)$8.50$6.50
Geogrid reinforcement (uniaxial)2037000SY54 (80%)$12.00$11.00
Reinf. steel for structures (bridge)7031200LB133 (23%)$1.50$2.00
Liquid asphalt binder PG64-224011004TON123 (25%)$750.00$715.00
Unclassified excavation2031000CY113 (27%)$28.75$42.80
Stabilized construction entrance8156490SY113 (27%)$27.00$23.00
Temporary cover8100200ACRE113 (27%)$1,350.00$1,450.00
Fine grading2081001SY113 (27%)$13.00$8.00
Republic Contracting Corporation, SCDOT: pay items where its unit price was the lowest on the line

A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.

Who it meets most

FirmContracts in commonThat firm ranked ahead
Dane Construction, LLC125 of 12
United Infrastructure Group, Inc.96 of 9
Dellinger, Inc.76 of 7
Reeves Construction Company62 of 6
Aos Specialty Contractors, Inc.61 of 6
Cekra, Inc.52 of 5
Lee Construction Company of the53 of 5
Lowcountry Sitework, LLC42 of 4
Coogler Construction, Inc.31 of 3
Clearwater Construction, Inc. DBA21 of 2
Republic Contracting Corporation, SCDOT: the firms on the same contracts most often

Latest bids

LetContractDistrictProjectRankIts bidAgainst the low bid
09 SEP 20262069920District 4Three Bridge Replacements in Fairfield County2 of 9$7,700,133+3.0%
12 MAY 20262575620District 7Bridge Replacement - Rock Spring Road (S-25-51) over Mill Creek2 of 8$2,006,078+2.0%
13 JAN 20263562410District 5SC 9 BUS (Cheraw St) Bridge Replacement over Crooked Creek3 of 4$8,573,629+24%
09 DEC 20253866050District 7Bridge Replacement of Closed FA/Non-NHS Secondary Bridge4 of 8$2,108,192+10%
12 NOV 20252074200District 4SC 200 Bridge Replacement over Minton Creek - Asset ID 2788 of 10$7,961,594+37%
09 SEP 20253865910District 7SC 332 Bridge Replacement over Willow Swamp3 of 6$2,694,483+13%
12 AUG 20253866040District 7Bridge Replacement. Closed FA/Non-NHS Secondary bridge.4 of 6$1,905,943+44%
12 MAR 20242863960District 1S-349 BRO Sandy Branch, Kershaw Co4 of 6$2,279,023+12%
09 JAN 20242059640S-258 (Blink Bonnie Rd) Bridge Replacement over Thorntree Cr3 of 5$2,255,527+15%
12 DEC 20233559650District 5Rehabilitation - S-165 (Marlboro Co)3 of 3$2,898,311+23%
13 DEC 20225763560District 7Bridge Rehabilitation - District 75 of 5$1,761,837+98%
08 NOV 20220363550District 7Bridge Maintenance - Allendale Co1 of 4$3,285,672Low, 15% under the second
08 NOV 20220563800District 7Bridge Maintenance - District 77 of 7$6,189,255+131%
12 JUL 20222959571District 4Enhancement - Lancaster Co2 of 4$1,586,785+68%
12 APR 20223825740District 7Bridge Replacement - US 301 (Snake Swamp)3 of 7$4,637,871+8.0%
Republic Contracting Corporation: latest SCDOT bids in the data

How this record was read

SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.

  • Every bid counted here matched its published total to within one dollar; SCDOT's rank decides who was low.
  • The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
  • A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.

A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.

Your own bid history, read the same way