Republic Contracting Corporation: SCDOT bid record
Republic Contracting Corporation submitted 15 bids on South Carolina DOT contracts in the data, from 12 APR 2022 to 09 SEP 2026, and was the low bidder on 1 of them (7%). When it was not low, its total sat a median +19% above the low bid.
- Owner
- South Carolina DOT
- Low bid volume
- $3,285,672
- Latest bid
- 09 SEP 2026
- Data through
- 13 OCT 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2022 | 5 | 1 | 20% |
| 2023 | 1 | 0 | 0% |
| 2024 | 2 | 0 | 0% |
| 2025 | 4 | 0 | 0% |
| 2026 | 3 | 0 | 0% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| District 7 | 8 | 1 | 13% |
| District 4 | 3 | 0 | 0% |
| District 5 | 2 | 0 | 0% |
| District 1 | 1 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Pile driving set-UP | 7110010 | EACH | 13 | 8 (62%) | $1,700.00 | $3,598.22 |
| Permanent cover | 8100100 | ACRE | 11 | 5 (45%) | $2,000.00 | $1,950.00 |
| Flowable fill | 2103000 | CY | 8 | 5 (63%) | $295.00 | $392.00 |
| Type B - flashing light | 608100B | EACH | 13 | 4 (31%) | $160.00 | $125.00 |
| Permanent yellow pavement markers BI-dir.- 4"X4" | 6301100 | EACH | 11 | 4 (36%) | $8.50 | $6.50 |
| Geogrid reinforcement (uniaxial) | 2037000 | SY | 5 | 4 (80%) | $12.00 | $11.00 |
| Reinf. steel for structures (bridge) | 7031200 | LB | 13 | 3 (23%) | $1.50 | $2.00 |
| Liquid asphalt binder PG64-22 | 4011004 | TON | 12 | 3 (25%) | $750.00 | $715.00 |
| Unclassified excavation | 2031000 | CY | 11 | 3 (27%) | $28.75 | $42.80 |
| Stabilized construction entrance | 8156490 | SY | 11 | 3 (27%) | $27.00 | $23.00 |
| Temporary cover | 8100200 | ACRE | 11 | 3 (27%) | $1,350.00 | $1,450.00 |
| Fine grading | 2081001 | SY | 11 | 3 (27%) | $13.00 | $8.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Dane Construction, LLC | 12 | 5 of 12 |
| United Infrastructure Group, Inc. | 9 | 6 of 9 |
| Dellinger, Inc. | 7 | 6 of 7 |
| Reeves Construction Company | 6 | 2 of 6 |
| Aos Specialty Contractors, Inc. | 6 | 1 of 6 |
| Cekra, Inc. | 5 | 2 of 5 |
| Lee Construction Company of the | 5 | 3 of 5 |
| Lowcountry Sitework, LLC | 4 | 2 of 4 |
| Coogler Construction, Inc. | 3 | 1 of 3 |
| Clearwater Construction, Inc. DBA | 2 | 1 of 2 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 09 SEP 2026 | 2069920 | District 4 | Three Bridge Replacements in Fairfield County | 2 of 9 | $7,700,133 | +3.0% |
| 12 MAY 2026 | 2575620 | District 7 | Bridge Replacement - Rock Spring Road (S-25-51) over Mill Creek | 2 of 8 | $2,006,078 | +2.0% |
| 13 JAN 2026 | 3562410 | District 5 | SC 9 BUS (Cheraw St) Bridge Replacement over Crooked Creek | 3 of 4 | $8,573,629 | +24% |
| 09 DEC 2025 | 3866050 | District 7 | Bridge Replacement of Closed FA/Non-NHS Secondary Bridge | 4 of 8 | $2,108,192 | +10% |
| 12 NOV 2025 | 2074200 | District 4 | SC 200 Bridge Replacement over Minton Creek - Asset ID 278 | 8 of 10 | $7,961,594 | +37% |
| 09 SEP 2025 | 3865910 | District 7 | SC 332 Bridge Replacement over Willow Swamp | 3 of 6 | $2,694,483 | +13% |
| 12 AUG 2025 | 3866040 | District 7 | Bridge Replacement. Closed FA/Non-NHS Secondary bridge. | 4 of 6 | $1,905,943 | +44% |
| 12 MAR 2024 | 2863960 | District 1 | S-349 BRO Sandy Branch, Kershaw Co | 4 of 6 | $2,279,023 | +12% |
| 09 JAN 2024 | 2059640 | S-258 (Blink Bonnie Rd) Bridge Replacement over Thorntree Cr | 3 of 5 | $2,255,527 | +15% | |
| 12 DEC 2023 | 3559650 | District 5 | Rehabilitation - S-165 (Marlboro Co) | 3 of 3 | $2,898,311 | +23% |
| 13 DEC 2022 | 5763560 | District 7 | Bridge Rehabilitation - District 7 | 5 of 5 | $1,761,837 | +98% |
| 08 NOV 2022 | 0363550 | District 7 | Bridge Maintenance - Allendale Co | 1 of 4 | $3,285,672 | Low, 15% under the second |
| 08 NOV 2022 | 0563800 | District 7 | Bridge Maintenance - District 7 | 7 of 7 | $6,189,255 | +131% |
| 12 JUL 2022 | 2959571 | District 4 | Enhancement - Lancaster Co | 2 of 4 | $1,586,785 | +68% |
| 12 APR 2022 | 3825740 | District 7 | Bridge Replacement - US 301 (Snake Swamp) | 3 of 7 | $4,637,871 | +8.0% |
How this record was read
SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.
- Every bid counted here matched its published total to within one dollar; SCDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.