SCDOT contract 2575620 bid tabulation
Bridge Replacement - Rock Spring Road (S-25-51) over Mill Creek. Let by South Carolina DOT on May 12, 2026, Hampton, District 7. 8 bids received; low bid $1,967,470 by Southeastern Site Development, Inc..
- Owner
- South Carolina DOT
- Letting
- 12 MAY 2026
- Pay items
- 76
- Data through
- 13 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Southeastern Site Development, Inc. | $1,967,470 | Low |
| 2 | Republic Contracting Corporation | $2,006,078 | +2.0% |
| 3 | Dane Construction, LLC | $2,084,653 | +6.0% |
| 4 | Rakes Building and Maintenance | $2,109,268 | +7.0% |
| 5 | Palmetto Infrastructure, Inc. | $2,215,299 | +13% |
| 6 | Cape Romain Contractors, Inc. | $2,276,675 | +16% |
| 7 | Lowcountry Sitework, LLC | $2,375,000 | +21% |
| 8 | Coogler Construction, Inc. | $2,387,386 | +21% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Southeastern Site Development, Inc. | 2. Republic Contracting Corporation | 3. Dane Construction, LLC | 4. Rakes Building and Maintenance | 5. Palmetto Infrastructure, Inc. | 6. Cape Romain Contractors, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Mobilization (1031000) | LS | 1 | $126,823 | $165,000 | $104,230 | $60,000 | $110,000 | $110,000 |
| 0020 | Bridge construction access (1031200) | LS | 1 | $7,251.00 | $60,000 | $41,690 | $5,000.00 | $10,000 | $65,000 |
| 0030 | Bonds and insurance (1032010) | LS | 1 | $32,730 | $25,000 | $41,690 | $42,000 | $45,000 | $49,474 |
| 0040 | Construction stakes, lines & grades (1050800) | EACH | 1 | $15,826 | $70,000 | $18,251 | $4,200.00 | $35,000 | $49,816 |
| 0050 | CPM progress schedule (1080300) | LS | 1 | $20,778 | $11,000 | $20,515 | $12,500 | $7,350.00 | $24,335 |
| 0060 | Clearing & grubbing within right of way (2011000) | LS | 1 | $17,252 | $200,000 | $200,000 | $3,500.00 | $225,000 | $160,000 |
| 0070 | Removal & disposal of existing bridge (2028100) | LS | 1 | $27,191 | $50,000 | $75,445 | $130,000 | $285,000 | $125,106 |
| 0080 | Unclassified excavation (2031000) | CY | 251 | $28.43 | $27.50 | $25.00 | $45.00 | $25.00 | $25.00 |
| 0090 | Borrow excavation (2033000) | CY | 4,893 | $52.00 | $33.00 | $30.00 | $60.00 | $30.00 | $30.00 |
| 0100 | Muck excavation (2034000) | CY | 1,274 | $44.68 | $27.50 | $25.00 | $45.00 | $25.00 | $25.00 |
| 0110 | Geotextile, separation (2036020) | SY | 1,038 | $2.27 | $9.00 | $9.00 | $15.00 | $9.00 | $9.00 |
| 0120 | Geogrid reinforcement (biaxial) (2037010) | SY | 1,663 | $3.09 | $11.00 | $11.00 | $14.00 | $11.00 | $11.00 |
| 0130 | Stone bridge lift material (2052010) | TON | 998 | $92.93 | $70.00 | $65.00 | $100.00 | $65.00 | $65.00 |
| 0140 | Granular bridge lift material (2052020) | CY | 100 | $135.16 | $80.00 | $75.00 | $60.00 | $75.00 | $75.00 |
| 0150 | Fine grading (2081001) | SY | 1,175 | $5.86 | $16.00 | $15.00 | $6.00 | $15.00 | $21.44 |
| 0160 | Flowable fill (2103000) | CY | 50 | $417.68 | $425.00 | $325.00 | $340.00 | $400.00 | $238.00 |
| 0170 | Maintenance stone (3059900) | TON | 10 | $84.21 | $110.00 | $100.00 | $90.00 | $100.00 | $100.00 |
| 0180 | HMA shoulder widening course (3104000) | TON | 80 | $439.43 | $379.00 | $405.00 | $366.00 | $345.00 | $345.00 |
| 0190 | Liquid asphalt binder PG64-22 (4011004) | TON | 40 | $868.00 | $1,006.00 | $800.00 | $175.00 | $915.00 | $915.00 |
| 0200 | Milling existing asphalt pavement (variable) (4013990) | SY | 100 | $135.63 | $270.00 | $125.00 | $50.00 | $246.00 | $246.00 |
| 0210 | Asphalt base course - type B (4020320) | TON | 163 | $298.38 | $283.00 | $275.00 | $366.00 | $258.00 | $258.00 |
| 0220 | Asphalt intermediate course type C (4030330) | TON | 319 | $217.00 | $202.00 | $200.00 | $366.00 | $184.00 | $184.00 |
| 0230 | Asphalt surface course type D (4040350) | TON | 191 | $298.38 | $180.00 | $275.00 | $366.00 | $164.00 | $164.00 |
| 0240 | Traffic control (6011000) | LS | 1 | $42,508 | $60,000 | $7,500.00 | $12,000 | $10,000 | $59,863 |
| 0250 | Barricade - type III (6041200) | LF | 96 | $24.41 | $22.50 | $22.50 | $60.00 | $21.00 | $32.14 |
| 0260 | Permanent construction signs (ground mounted) (6051120) | SF | 402 | $6.26 | $5.77 | $5.77 | $15.00 | $7.40 | $11.32 |
| 0270 | Permanent construction signs (barricade mounted) (6051125) | SF | 119 | $6.71 | $6.18 | $6.18 | $15.00 | $7.40 | $11.32 |
| 0280 | Type B - flashing light (608100B) | EACH | 16 | $43.40 | $40.00 | $85.00 | $220.00 | $250.00 | $191.32 |
| 0290 | Pavement markings(temporary-paint)-4" white solid lines (609115A) | LF | 1,500 | $0.16 | $0.25 | $0.25 | $2.00 | $0.25 | $0.25 |
| 0300 | Pavement markings(temporary-paint)-4" yellow solid lines (609115B) | LF | 1,500 | $0.16 | $0.25 | $0.25 | $2.00 | $0.25 | $0.25 |
| 0310 | 4" white solid lines (PVT. edge lines) thermo.- 90 mil. (6271010) | LF | 2,900 | $0.71 | $1.00 | $1.00 | $5.50 | $1.00 | $1.32 |
| 0320 | 4" yellow broken lines(gaps exc)thermoplastic - 90 mil. (6271064) | LF | 200 | $0.71 | $1.00 | $1.00 | $6.00 | $1.00 | $1.32 |
| 0330 | 4" yellow solid lines(PVT.edge lines) thermo- 90 mil. (6271074) | LF | 2,300 | $0.71 | $1.00 | $1.00 | $6.00 | $1.00 | $1.32 |
| 0340 | Permanent yellow pavement markers mono-dir.- 4"X 4" perm. yel. (6301005) | EACH | 20 | $8.68 | $8.50 | $8.50 | $30.00 | $8.50 | $11.25 |
| 0350 | Permanent yellow pavement markers BI-dir.- 4"X4" (6301100) | EACH | 30 | $8.68 | $8.50 | $8.50 | $27.00 | $8.50 | $11.25 |
| 0360 | Furnish & install 2.0" schedule 80 PVC conduit (6750278) | LF | 404 | $23.34 | $27.00 | $30.16 | $25.00 | $30.00 | $35.49 |
| 0370 | Conc. for structures - class 4000 (7011400) | CY | 88.80 | $2,303.59 | $1,225.00 | $1,830.00 | $1,000.00 | $3,000.00 | $2,114.68 |
| 0380 | Reinf. steel for structures (bridge) (7031200) | LB | 31,138 | $2.11 | $1.50 | $2.25 | $2.20 | $2.00 | $2.02 |
| 0390 | 3'-0" X 2'-0" cored slabs (7046020) | LF | 718.50 | $306.62 | $315.00 | $520.00 | $412.00 | $280.00 | $406.26 |
| 0400 | 42" MASH concrete barrier parapet/railing wall (7051050) | LF | 200 | $257.99 | $148.00 | $155.00 | $232.00 | $186.00 | $211.21 |
| 0410 | Pile driving set-UP (7110010) | EACH | 12 | $3,992.59 | $1,500.00 | $3,250.00 | $1,500.00 | $4,500.00 | $4,122.81 |
| 0420 | Steel H bearing piling (HP14 X 73) (7112220) | LF | 642 | $102.03 | $105.00 | $75.00 | $190.00 | $100.00 | $115.71 |
| 0430 | 15" smooth wall pipe (7143615) | LF | 32 | $70.76 | $150.00 | $150.00 | $206.00 | $150.00 | $150.00 |
| 0440 | 4' slope flume (6" curb style with cutoffs) (7199200) | LF | 30 | $318.99 | $340.00 | $315.00 | $50.00 | $315.00 | $416.76 |
| 0450 | Concrete curb and gutter(2'-0") vertical face (7203210) | LF | 52 | $70.53 | $145.00 | $125.00 | $65.00 | $125.00 | $165.38 |
| 0460 | Elastomeric bearing (7243100) | EACH | 24 | $290.48 | $630.00 | $700.00 | $375.00 | $250.00 | $1,232.33 |
| 0470 | Waterproofing (7282000) | SY | 225.60 | $134.94 | $65.00 | $190.00 | $115.00 | $45.00 | $420.38 |
| 0480 | Rip-rap (class B) (8041020) | TON | 283 | $128.91 | $110.00 | $100.00 | $180.00 | $100.00 | $120.00 |
| 0490 | Geotextile for erosion control under riprap(class 2)type B (8048205) | SY | 312 | $5.76 | $9.00 | $9.00 | $12.00 | $9.00 | $9.00 |
| 0500 | Geotextile for erosion control under riprap(class 2)type C (8048210) | SY | 50 | $8.80 | $9.00 | $9.00 | $12.00 | $9.00 | $9.00 |
| 0510 | MT3 leading end treatment TL3 (8051151) | EACH | 3 | $3,210.03 | $3,740.00 | $3,400.00 | $6,000.00 | $3,200.00 | $4,528.13 |
| 0520 | MT2 leading end treatment TL2 (8051155) | EACH | 1 | $3,101.94 | $3,520.00 | $3,200.00 | $6,000.00 | $3,000.00 | $4,375.66 |
| 0530 | MGS3 GR standard shoulder (8052100) | LF | 62.50 | $30.33 | $26.40 | $24.00 | $60.00 | $28.00 | $42.77 |
| 0540 | MTBBC3 MASH thrie-beam barrier connector TL3 (8053253) | EACH | 3 | $3,976.35 | $3,080.00 | $2,800.00 | $3,700.00 | $3,700.00 | $5,609.11 |
| 0550 | MTBBC2 MASH thrie-beam barrier connector TL2 (8053255) | EACH | 1 | $1,957.80 | $1,980.00 | $1,800.00 | $3,500.00 | $3,200.00 | $2,761.71 |
| 0560 | Flume inlet at guardrail (handwork) (8053257) | EACH | 2 | $4,991.00 | $3,800.00 | $3,500.00 | $3,200.00 | $3,500.00 | $4,276.56 |
| 0570 | Non-mow strip under guardrail (8055250) | SY | 191 | $227.85 | $127.00 | $117.00 | $120.00 | $145.00 | $117.00 |
| 0580 | Temporary barrier fence (orange) (8068301) | LF | 1,000 | $2.22 | $2.50 | $6.00 | $8.00 | $2.00 | $2.39 |
| 0590 | Right of way marker(rebar and cap) (8091010) | EACH | 13 | $400.42 | $250.00 | $120.00 | $100.00 | $250.00 | $130.00 |
| 0600 | Right of way plat (8091050) | LS | 1 | $3,049.69 | $10,250 | $3,675.00 | $5,000.00 | $6,000.00 | $6,606.97 |
| 0610 | Permanent cover (8100100) | ACRE | 0.47 | $2,056.09 | $2,400.00 | $8,000.00 | $16,000 | $2,200.00 | $1,798.46 |
| 0620 | Temporary cover (8100200) | ACRE | 0.70 | $1,405.07 | $1,550.00 | $4,000.00 | $16,000 | $1,400.00 | $1,382.83 |
| 0630 | Compost (8101105) | CY | 125 | $54.25 | $50.00 | $25.00 | $60.00 | $50.00 | $22.79 |
| 0640 | Fertilizer (nitrogen) (8104005) | LB | 46.50 | $2.44 | $5.00 | $6.00 | $8.00 | $5.00 | $1.96 |
| 0650 | Fertilizer (phosphoric acid) (8104010) | LB | 46.50 | $2.44 | $5.00 | $6.00 | $8.00 | $5.00 | $1.96 |
| 0660 | Fertilizer (potash) (8104015) | LB | 46.50 | $2.44 | $5.00 | $6.00 | $8.00 | $5.00 | $1.96 |
| 0670 | Agricultural granular lime (8105005) | LB | 930 | $0.76 | $0.75 | $0.12 | $6.00 | $0.75 | $0.96 |
| 0680 | Mowing (8109901) | ACRE | 2.50 | $320.08 | $500.00 | $350.00 | $800.00 | $500.00 | $410.94 |
| 0690 | Hydraulic erosion control product (hecp) - type 3 (8151203) | ACRE | 6.98 | $4,123.00 | $4,300.00 | $2,600.00 | $4,630.00 | $4,200.00 | $3,410.26 |
| 0700 | Sediment tubes for ditch checks (8152007) | LF | 210 | $14.11 | $20.00 | $20.00 | $22.00 | $20.00 | $10.82 |
| 0710 | Silt fence (8153000) | LF | 2,600 | $3.20 | $4.00 | $3.50 | $8.00 | $3.50 | $4.65 |
| 0720 | Replace/repair silt fence (8153090) | LF | 260 | $4.07 | $5.50 | $3.50 | $8.00 | $5.00 | $3.64 |
| 0730 | Floating turbidity barrier- heavy duty(5'depth) (8153305) | LF | 400 | $63.47 | $33.00 | $50.00 | $70.00 | $30.00 | $32.24 |
| 0740 | Cleaning silt basins (8154010) | CY | 1 | $683.56 | $100.00 | $100.00 | $1,200.00 | $100.00 | $100.00 |
| 0750 | Removal of silt retained by silt fence (8154050) | LF | 650 | $4.88 | $5.00 | $15.00 | $1.80 | $5.00 | $1.54 |
| 0760 | Stabilized construction entrance (8156490) | SY | 550 | $30.56 | $30.00 | $30.00 | $5.00 | $30.00 | $30.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from SCDOT's tabulation for this contract. SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.
Every contract let that day: SCDOT letting of May 12, 2026. Compiled by Mirage Metrics.