SCDOT contract 2074200 bid tabulation
SC 200 Bridge Replacement over Minton Creek - Asset ID 278. Let by South Carolina DOT on November 12, 2025, Fairfield, District 4. 10 bids received; low bid $5,797,696 by Lee Construction Company of the.
- Owner
- South Carolina DOT
- Letting
- 12 NOV 2025
- Pay items
- 88
- Data through
- 13 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Lee Construction Company of the | $5,797,696 | Low |
| 2 | Aos Specialty Contractors, Inc. | $5,914,752 | +2.0% |
| 3 | Kemp Sigmon Construction Co., Inc. | $5,995,053 | +3.0% |
| 4 | Lowcountry Sitework, LLC | $6,677,211 | +15% |
| 5 | Mastec Civil, LLC | $6,709,165 | +16% |
| 6 | Dane Construction, LLC | $6,850,743 | +18% |
| 7 | United Infrastructure Group, Inc. | $6,961,748 | +20% |
| 8 | Republic Contracting Corporation | $7,961,594 | +37% |
| 9 | Reeves Construction Company | $8,821,401 | +52% |
| 10 | Dellinger, Inc. | $9,219,609 | +59% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Lee Construction Company of the | 2. Aos Specialty Contractors, Inc. | 3. Kemp Sigmon Construction Co., Inc. | 4. Lowcountry Sitework, LLC | 5. Mastec Civil, LLC | 6. Dane Construction, LLC |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Mobilization (1031000) | LS | 1 | $287,000 | $227,132 | $298,000 | $650,000 | $308,000 | $342,535 |
| 0020 | Bonds and insurance (1032010) | LS | 1 | $114,000 | $54,409 | $119,000 | $250,000 | $200,000 | $205,520 |
| 0030 | Construction stakes, lines & grades (1050800) | EACH | 1 | $75,000 | $64,473 | $25,000 | $125,000 | $60,000 | $60,000 |
| 0040 | CPM progress schedule (1080300) | LS | 1 | $10,000 | $26,810 | $25,000 | $25,000 | $5,400.00 | $23,000 |
| 0050 | Clearing & grubbing within right of way (2011000) | LS | 1 | $160,000 | $138,282 | $385,000 | $100,000 | $465,000 | $145,000 |
| 0060 | Removal of exist. guardrail (2027801) | LF | 2,617 | $1.00 | $1.20 | $1.00 | $3.00 | $1.00 | $1.00 |
| 0070 | Removal & disposal of existing bridge (2028100) | LS | 1 | $225,000 | $258,452 | $500,000 | $200,000 | $466,000 | $426,040 |
| 0080 | Unclassified excavation (2031000) | CY | 21,284 | $7.50 | $7.30 | $25.00 | $10.00 | $13.00 | $7.50 |
| 0090 | Borrow excavation (2033000) | CY | 13,567 | $29.00 | $24.75 | $15.00 | $10.00 | $21.00 | $28.75 |
| 0100 | Fine grading (2081001) | SY | 7,504 | $10.00 | $8.00 | $7.50 | $9.00 | $11.00 | $10.00 |
| 0110 | Flowable fill (2103000) | CY | 12 | $300.00 | $660.00 | $350.00 | $300.00 | $390.00 | $300.00 |
| 0120 | Maintenance stone (3059900) | TON | 50 | $75.00 | $104.00 | $40.00 | $50.00 | $54.00 | $75.00 |
| 0130 | Liquid asphalt binder PG64-22 (4011004) | TON | 254 | $725.00 | $943.00 | $755.00 | $740.00 | $688.00 | $625.00 |
| 0140 | Milling existing asphalt pavement (variable) (4013990) | SY | 200 | $25.00 | $34.00 | $55.00 | $25.00 | $78.00 | $70.70 |
| 0150 | Asphalt base course - type B (4020320) | TON | 3,719 | $105.00 | $138.00 | $112.00 | $135.00 | $110.00 | $100.05 |
| 0160 | Asphalt intermediate course type C (4030330) | TON | 795 | $115.00 | $135.00 | $129.00 | $145.00 | $130.00 | $118.50 |
| 0170 | Asphalt surface course type C (4040340) | TON | 719 | $118.00 | $135.00 | $132.00 | $145.00 | $133.00 | $119.85 |
| 0180 | Traffic control (6011000) | LS | 1 | $50,000 | $23,142 | $50,000 | $67,788 | $33,000 | $15,000 |
| 0190 | Barricade - type III (6041200) | LF | 150 | $25.00 | $24.00 | $25.00 | $25.00 | $27.00 | $25.00 |
| 0200 | Permanent construction signs (ground mounted) (6051120) | SF | 128 | $10.00 | $9.00 | $8.00 | $9.00 | $8.00 | $6.85 |
| 0210 | Permanent construction signs (barricade mounted) (6051125) | SF | 282 | $10.00 | $9.00 | $8.00 | $9.00 | $8.00 | $8.75 |
| 0220 | Construction zone electric changeable message sign (trailer (6062000) | EACH | 2 | $10,000 | $6,209.00 | $15,000 | $15,000 | $16,500 | $7,500.00 |
| 0230 | Type B - flashing light (608100B) | EACH | 16 | $100.00 | $108.00 | $125.00 | $200.00 | $235.00 | $200.00 |
| 0240 | Pavement markings(temp- paint) 4" yellow broken lines (609105B) | LF | 500 | $0.15 | $0.17 | $0.15 | $0.25 | $0.16 | $0.15 |
| 0250 | Pavement markings(temporary-paint)-4" white solid lines (609115A) | LF | 11,000 | $0.15 | $0.17 | $0.15 | $0.25 | $0.16 | $0.15 |
| 0260 | Pavement markings(temporary-paint)-4" yellow solid lines (609115B) | LF | 11,000 | $0.15 | $0.17 | $0.15 | $0.25 | $0.16 | $0.15 |
| 0270 | 4" white solid lines (PVT. edge lines) epoxy paint slow cure (6261010) | LF | 560 | $6.00 | $7.00 | $6.00 | $11.00 | $6.48 | $6.00 |
| 0280 | 4"yellow solid lines- PVT.edge&no passing zone - epoxy paint slow cure (6261110) | LF | 560 | $6.00 | $7.00 | $6.00 | $11.00 | $6.48 | $6.00 |
| 0290 | 4" white solid lines (PVT. edge lines) thermo.- 90 mil. (6271010) | LF | 4,310 | $0.75 | $0.85 | $0.75 | $1.00 | $0.81 | $0.75 |
| 0300 | 4" yellow solid lines(PVT.edge lines) thermo- 90 mil. (6271074) | LF | 4,310 | $0.75 | $0.85 | $0.75 | $1.00 | $0.81 | $0.75 |
| 0310 | Permanent yellow pavement markers BI-dir.- 4"X4" (6301100) | EACH | 48 | $10.00 | $9.00 | $7.50 | $11.00 | $8.10 | $7.50 |
| 0320 | Furnish & install 2.0" schedule 80 PVC conduit (6750278) | LF | 1,124 | $10.00 | $12.00 | $14.00 | $15.00 | $18.00 | $17.00 |
| 0330 | Conc. for structures - class 4000 (7011400) | CY | 675.50 | $1,000.00 | $1,165.00 | $1,000.00 | $1,900.00 | $1,600.00 | $1,620.00 |
| 0340 | Grooved surface finish (7023200) | SY | 1,118 | $5.00 | $6.20 | $7.00 | $5.50 | $9.00 | $3.29 |
| 0350 | Reinf. steel for structures (bridge) (7031200) | LB | 217,833 | $2.50 | $2.19 | $1.50 | $1.30 | $1.60 | $2.50 |
| 0360 | Hoop reinforcing steel for structures (bridge) (7031220) | LB | 13,048 | $4.00 | $4.10 | $3.00 | $3.35 | $3.76 | $4.75 |
| 0370 | Prestressed conc. beam (type III) (7043000) | LF | 1,422 | $400.00 | $392.00 | $350.00 | $350.00 | $400.00 | $600.00 |
| 0380 | 42" MASH concrete barrier parapet/railing wall (7051050) | LF | 560 | $150.00 | $125.00 | $100.00 | $145.00 | $110.00 | $100.00 |
| 0390 | Pile driving set-UP (7110010) | EACH | 14 | $1,250.00 | $5,610.00 | $2,000.00 | $9,000.00 | $5,000.00 | $4,750.00 |
| 0400 | Reinf. pile tips (HP14 X 73) (7111560) | EACH | 14 | $400.00 | $212.00 | $200.00 | $750.00 | $200.00 | $675.00 |
| 0410 | Steel H bearing piling (HP14 X 73) (7112220) | LF | 630 | $100.00 | $66.00 | $65.00 | $75.00 | $87.00 | $60.00 |
| 0420 | Drilled shaft set-UP (7120006) | EACH | 6 | $12,500 | $8,015.00 | $25,000 | $12,500 | $6,000.00 | $3,470.00 |
| 0430 | Crosshole sonic logging setup (7120010) | EACH | 6 | $2,500.00 | $2,258.00 | $1,000.00 | $6,000.00 | $3,500.00 | $900.00 |
| 0440 | Drilled shaft with rock excavation - 54" diameter (7120172) | LF | 119 | $1,500.00 | $1,637.00 | $1,250.00 | $1,675.00 | $1,600.00 | $1,750.00 |
| 0450 | Drilled shaft with wet & dry excavation - 60" diameter (7120181) | LF | 143 | $1,500.00 | $1,637.00 | $1,250.00 | $1,675.00 | $1,540.00 | $1,925.00 |
| 0460 | Construction casing - 60" diameter (7120185) | LF | 211 | $500.00 | $511.00 | $575.00 | $800.00 | $640.00 | $625.00 |
| 0470 | 18" smooth wall pipe (7143618) | LF | 172 | $98.50 | $167.00 | $125.00 | $100.00 | $85.00 | $98.50 |
| 0480 | 24" smooth wall pipe (7143624) | LF | 136 | $115.00 | $191.00 | $150.00 | $130.00 | $310.00 | $115.00 |
| 0490 | Drop inlet type 112 (7192040) | EACH | 1 | $7,850.00 | $9,637.00 | $5,000.00 | $6,000.00 | $11,000 | $7,850.00 |
| 0500 | Manhole (7192105) | EACH | 2 | $7,850.00 | $5,705.00 | $5,000.00 | $6,000.00 | $8,050.00 | $7,850.00 |
| 0510 | Beveling of pipe end (7199100) | EACH | 2 | $275.00 | $435.00 | $2,500.00 | $600.00 | $630.00 | $275.00 |
| 0520 | 4' slope flume (6" curb style with cutoffs) (7199200) | LF | 155 | $200.00 | $184.00 | $150.00 | $225.00 | $225.00 | $345.00 |
| 0530 | Concrete curb and gutter(2'-0") vertical face (7203210) | LF | 100 | $50.00 | $97.00 | $56.00 | $65.00 | $68.00 | $150.00 |
| 0540 | Elastomeric bearing (7243100) | EACH | 36 | $400.00 | $1,375.00 | $500.00 | $25.00 | $1,500.00 | $900.00 |
| 0550 | Waterproofing (7282000) | SY | 28 | $100.00 | $107.00 | $60.00 | $100.00 | $90.00 | $105.00 |
| 0560 | Aggregate underdrain(agg#789)with 4"perf.pipe for struc (8011210) | TON | 155 | $100.00 | $130.00 | $100.00 | $120.00 | $89.00 | $90.00 |
| 0570 | 12" temporary pipe slope drain (8034120) | LF | 260 | $45.00 | $29.00 | $15.00 | $30.00 | $27.00 | $45.00 |
| 0580 | Rip-rap (class A) (8041010) | TON | 15 | $115.00 | $164.00 | $100.00 | $300.00 | $90.00 | $112.50 |
| 0590 | Rip-rap (class B) (8041020) | TON | 1,658 | $115.00 | $118.00 | $80.00 | $95.00 | $100.00 | $115.00 |
| 0600 | Geotextile for erosion control under riprap(class 2)type C (8048210) | SY | 3,226 | $3.50 | $4.15 | $3.00 | $2.00 | $3.00 | $3.50 |
| 0610 | MT3 leading end treatment TL3 (8051151) | EACH | 7 | $3,200.00 | $4,239.00 | $3,200.00 | $3,500.00 | $4,500.00 | $3,200.00 |
| 0620 | MGS3 GR standard shoulder (8052100) | LF | 1,650 | $23.00 | $27.00 | $23.00 | $28.00 | $26.00 | $23.00 |
| 0630 | MTBBC3 MASH thrie-beam barrier connector TL3 (8053253) | EACH | 4 | $2,600.00 | $3,805.00 | $2,600.00 | $3,800.00 | $3,700.00 | $2,600.00 |
| 0640 | Flume inlet at guardrail (handwork) (8053257) | EACH | 4 | $5,000.00 | $3,278.00 | $2,000.00 | $1,800.00 | $6,700.00 | $4,250.00 |
| 0650 | Non-mow strip under guardrail (8055250) | SY | 945 | $130.00 | $81.00 | $40.00 | $80.00 | $75.00 | $85.00 |
| 0660 | Premash type T TL3 leading 50' (8057100) | EACH | 1 | $3,000.00 | $3,215.00 | $3,000.00 | $3,687.91 | $3,075.00 | $3,000.00 |
| 0670 | Temporary barrier fence (orange) (8068301) | LF | 1,000 | $5.00 | $3.00 | $3.00 | $5.59 | $3.25 | $4.00 |
| 0680 | Right of way marker(rebar and cap) (8091010) | EACH | 26 | $250.00 | $169.00 | $300.00 | $150.00 | $250.00 | $225.00 |
| 0690 | Right of way plat (8091050) | LS | 1 | $5,000.00 | $8,466.00 | $3,700.00 | $5,000.00 | $5,400.00 | $2,500.00 |
| 0700 | Permanent cover (8100100) | ACRE | 4.80 | $1,700.00 | $2,371.00 | $1,460.00 | $1,500.00 | $1,833.00 | $1,460.00 |
| 0710 | Temporary cover (8100200) | ACRE | 2.40 | $1,500.00 | $1,863.00 | $1,320.00 | $1,350.00 | $1,387.00 | $1,320.00 |
| 0720 | Compost (8101105) | CY | 194 | $64.24 | $88.00 | $37.00 | $40.00 | $60.00 | $37.00 |
| 0730 | Fertilizer (nitrogen) (8104005) | LB | 480.10 | $2.00 | $1.75 | $3.75 | $4.00 | $2.22 | $3.75 |
| 0740 | Fertilizer (phosphoric acid) (8104010) | LB | 480.10 | $2.00 | $1.75 | $3.75 | $4.00 | $2.22 | $3.75 |
| 0750 | Fertilizer (potash) (8104015) | LB | 480.10 | $2.00 | $1.75 | $3.75 | $4.00 | $2.22 | $3.75 |
| 0760 | Agricultural granular lime (8105005) | LB | 9,602 | $0.60 | $0.34 | $0.45 | $0.50 | $0.56 | $0.45 |
| 0770 | Selective watering (8109050) | GAL | 54,300 | $0.03 | $0.17 | $0.09 | $0.10 | $0.01 | $0.09 |
| 0780 | Mowing (8109901) | ACRE | 14.40 | $85.00 | $621.00 | $479.90 | $500.00 | $530.00 | $480.00 |
| 0790 | Turf reinforcement matting (TRM) type 1 (8151101) | MSY | 2.78 | $4,500.00 | $4,121.00 | $3,600.00 | $4,000.00 | $4,235.00 | $3,600.00 |
| 0800 | Temporary erosion control blanket (ecb) (8151110) | MSY | 16.41 | $3,500.00 | $1,750.00 | $1,700.00 | $1,900.00 | $1,815.76 | $1,700.00 |
| 0810 | Hydraulic erosion control product (hecp) - type 3 (8151203) | ACRE | 4.80 | $4,500.00 | $4,515.00 | $3,150.00 | $3,500.00 | $3,575.63 | $3,150.00 |
| 0820 | Inlet structure filter- type F (non-weighted) (8152006) | LF | 817 | $15.00 | $13.00 | $15.00 | $15.00 | $10.45 | $10.00 |
| 0830 | Sediment tubes for ditch checks (8152007) | LF | 2,215 | $9.00 | $11.50 | $14.00 | $15.00 | $10.45 | $20.00 |
| 0840 | Silt fence (8153000) | LF | 13,000 | $3.00 | $4.00 | $3.35 | $4.00 | $3.25 | $3.35 |
| 0850 | Replace/repair silt fence (8153090) | LF | 1,300 | $3.00 | $6.00 | $5.00 | $5.00 | $3.00 | $5.00 |
| 0860 | Removal of silt retained by silt fence (8154050) | LF | 3,250 | $4.00 | $8.50 | $5.00 | $4.50 | $2.00 | $20.00 |
| 0870 | Inlet structure filter - type B (8156210) | EACH | 10 | $300.00 | $398.00 | $150.00 | $500.00 | $302.00 | $35.00 |
| 0880 | Stabilized construction entrance (8156490) | SY | 550 | $50.00 | $22.00 | $25.00 | $50.00 | $27.00 | $18.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from SCDOT's tabulation for this contract. SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.
Every contract let that day: SCDOT letting of November 12, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.